Nuclear energy is becoming an increasingly important part of long-term energy planning in the GCC as governments seek to diversify power generation, strengthen energy security and meet decarbonisation targets.

The signing of a civil nuclear cooperation deal between Saudi Arabia and the US in July marked the most significant development in the kingdom’s nuclear programme for several years, providing a framework for bilateral cooperation as Riyadh advances preparations for its first commercial nuclear power plant.

The agreement also comes as the regional power market is setting the stage for a broader nuclear revival. Rapid growth in electricity demand from industry, desalination and digital infrastructure is increasing the need for reliable low-carbon electricity.

With the UAE operating the Middle East’s first commercial nuclear power station, Saudi Arabia targeting up to 17GW of nuclear generating capacity by 2040 and Bahrain evaluating small modular reactor (SMR) technologies, nuclear energy is set to play an increasingly important role in the GCC’s long-term power projects pipeline.

Nuclear ambitions

Saudi Arabia’s nuclear ambitions are not new. The kingdom announced plans in 2011 to build 16 nuclear reactors over 20 years as part of its energy diversification strategy.

Riyadh views nuclear power not only as a source of low-carbon electricity, but also as a way to reduce domestic consumption of oil and natural gas while supporting industrial growth and expanding desalination capacity.

Since then, the programme has evolved to focus initially on the development of two large-scale reactors, while also supporting longer-term plans for SMRs, domestic fuel-cycle development and the regulatory institutions required for a civilian nuclear industry.

Despite progress being slower than initially envisaged, Saudi Arabia has continued to develop the regulatory, institutional and procurement framework for its nuclear programme, and has established the Nuclear and Radiological Regulatory Commission and the Saudi Nuclear Energy Holding Company.

The US-Saudi civil nuclear agreement is the latest milestone in that process. It follows a joint declaration signed last November and lays the legal foundation for a decades-long, multibillion-dollar partnership between the two countries. 

According to the US Department of Energy, the agreement will also provide access for US companies to Saudi Arabia’s nuclear energy programme and “expand American nuclear technology exports”.

The deal is part of a broader US effort to regain a stronger position in the global civil nuclear market. An executive order signed by President Donald Trump in May 2025 directed the US government to promote American nuclear exports and expand international nuclear cooperation. The Saudi deal explicitly builds on that policy.

While the agreement does not determine which company will build Saudi Arabia’s first reactors, it creates a clearer route for US firms to participate in the kingdom’s civilian nuclear programme, subject to the necessary regulatory and congressional approvals.

Nuclear is set to play an increasingly important role in the GCC’s long-term power projects pipeline

Flagship project

Saudi Arabia’s first commercial nuclear power plant is central to the kingdom’s nuclear ambitions. Planned at Khor Duwaiheen on the Gulf coast, the project comprises two 1.4GW reactors and is being advanced by King Abdullah City for Atomic & Renewable Energy under the Saudi National Atomic Energy Project.

Technical bids were invited in 2022 and Saudi Arabia has since continued technical and commercial discussions with shortlisted reactor vendors, despite bid deadlines being extended several times. 

The four nuclear technology providers reported to be pursuing the project are China National Nuclear Corporation, Electricite de France (EDF), Korea Electric Power Corporation and Russia’s State Atomic Energy Corporation Rosatom. 

US nuclear technology company Westinghouse was previously involved in the Duwaiheen project procurement, although it had dropped out of the race by March 2025, according to sources.

The US nuclear industry’s own revival could help to strengthen its ability to compete in overseas markets. Westinghouse confidentially filed for a US initial public offering in July, highlighting renewed investor interest as Washington seeks to broaden investment in the sector.

Meanwhile, the Nuclear Energy Agency identifies Saudi Arabia’s procurement process as one of the important unresolved reactor competitions in the international market. About 40% of proposed nuclear projects globally have yet to select a technology supplier, leaving markets such as Saudi Arabia open to major international vendors.

The scale of the opportunity also extends beyond the reactor contract itself. The planned 2.8GW facility represents only about a sixth of Saudi Arabia’s stated aim of developing 17GW of nuclear capacity by 2040, suggesting the kingdom’s first commercial power plant is likely to be the beginning of a broader programme rather than a standalone project.

Beyond the reactor

While the engineering, procurement and construction (EPC) contract for the reactor will be the programme’s highest-profile award, it is only one element of the wider investment needed to establish a civilian nuclear industry. Nuclear programmes require extensive ecosystems of supporting infrastructure, specialist engineering capabilities, fuel supply, workforce development and regulatory oversight that extends well beyond construction.

This is illustrated by the UAE’s Barakah programme, which entered commercial operations in September 2024. According to Emirates Nuclear Energy Company (Enec), more than 2,000 UAE firms have secured contracts worth over $6.7bn supporting the construction, operations and maintenance of the Barakah plant.

Enec says the programme has helped develop a local nuclear supply chain, while the plant’s long-term operation continues to create opportunities in maintenance, spare parts and other services. 

In July 2025, Enec and Westinghouse signed an agreement to explore fuel supply chain cooperation and the expansion of Westinghouse’s support for operations and maintenance at Barakah.

Saudi Arabia has also made clear that its ambitions extend beyond large commercial reactors. The kingdom’s long-term strategy includes plans for SMRs, the development of domestic uranium resources and elements of the nuclear fuel cycle.

Energy Minister Prince Abdulaziz Bin Salman has said Saudi Arabia intends to use its domestic uranium resources across the nuclear fuel cycle, including in the production of yellowcake and low-enriched uranium. 

These plans could significantly broaden the future projects market in the kingdom. In addition to power generation assets, opportunities could emerge in uranium exploration, mining, processing, fuel services, research facilities, specialist manufacturing and long-term operations and maintenance.

The kingdom’s long-term strategy includes plans for SMRs, the development of domestic uranium resources and elements of the nuclear fuel cycle

Regional outlook

Saudi Arabia’s programme forms part of a broader shift towards civilian nuclear energy across the Gulf. 

The UAE has already demonstrated the region’s ability to develop, finance and operate large-scale nuclear infrastructure through the 5.6GW Barakah nuclear power plant, which now supplies approximately a quarter of the country’s electricity through its four installed units.

The country’s next nuclear expansion is at an early stage. Additional nuclear capacity of 2.8GW is not expected to be installed until 2039, implying procurement discussions could begin next year.

The UAE’s Federal Authority for Nuclear Regulation said in February that it is prepared for future capacity additions and is ready to adopt new nuclear technologies, although it had yet to receive a formal proposal for an expansion. Tariff comparisons with the UAE’s growing pipeline of round-the-clock renewables projects are also expected to influence the viability and timing of further nuclear schemes.

Elsewhere in the region, Bahrain is exploring the use of nuclear power for domestic consumption, as well as for the potential export of surplus. State energy conglomerate Bapco Energies is tasked with studying the prospect of building a modular nuclear power plant in the country.

According to sources, the proposed project is being led by BeVentures, the venture capital arm of Bapco Energies, which was launched in July 2024. Under the plan that is being studied, power produced by a nuclear facility would be supplied mainly to major industrial complexes in the country, such as Aluminium Bahrain and Bapco Refining, for the clean production of aluminium and refined products.

Meanwhile, Egypt is making progress with its first commercial nuclear power plant. Construction is under way on the four-unit, 4.8GW El-Dabaa project being developed with Russia’s Rosatom. 

In July, the reactor pressure vessel was installed at Unit 2 of the plant. The project is expected to begin generating electricity from its first units in 2028. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/19229350/main.gif
Mark Dowdall
Related Articles
  • Algeria tenders 310km Tamanrasset railway

    16 October 2026

     

    Algeria’s state railway project developer, Agence Nationale d’Etudes et de Suivi de la Realisation des Investissements Ferroviaires (Anesrif), has invited national and international contractors to bid for the construction of a 310-kilometre (km) railway line between Hotel Station and Moulay Lahcen Station. 

    The planned line is a key segment of the proposed railway corridor connecting El-Menea, In-Salah and Tamanrasset across the southern wilayas of In-Salah and Tamanrasset.

    The tender notice was issued on 12 October, with bids due by 10 November.

    The tender is open to single contractors and consortiums. To qualify, single firms must have executed at least 200km of new railway lines or track-doubling works since 2010, with accepted project certificates covering sections of at least 100km, along with a cumulative 800 metres of railway bridges with individual spans exceeding 30 metres.

    Bidders must also provide at least two rail-tamping machines, two ballast regulators, and a project director with an engineering degree and at least five years of railway construction management experience.

    From a commercial and classification perspective, single bidders and consortium leaders must hold a category-nine (IX) professional qualification in public works.

    Bidders must also demonstrate an average annual turnover in construction of at least DZ260bn ($1.96bn) across the 2023-2025 financial period.

    For joint ventures, the cumulative turnover of all members must meet the $1.96bn threshold, with the consortium leader accounting for at least $1.3bn.

    Offers must be accompanied by a bid bond exceeding 1% of the total bid value for submissions exceeding $7.4m, with proposals remaining valid for 90 days beyond the submission date.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20665591/main.jpg
    Yasir Iqbal
  • Joint venture wins $246m RCRC bridges contract

    16 October 2026

     

    A joint venture of local contractor Mofarreh Group and Turkey-based Gulsan Holding has won an estimated SR923m ($246m) contract from the Royal Commission for Riyadh City (RCRC) to construct a series of grade-separated steel flyovers across the capital.

    The contract, known as Package 2 (Groups 2 and 3), is part of RCRC’s urgent bridges programme under the wider project to build steel bridges at 10 junctions across Riyadh.

    The works have a 12-month execution timeline to fast-track traffic decongestion across major arterial corridors.

    The joint venture’s scope covers the engineering and construction of grade-separated steel bridge interchanges across seven key intersections:

    • IC04: Al-Khair Road and King Salman Bin Abdulaziz Road
    • IC05: Prince Turki Road and Imam Saud Road
    • IC06: Al-Takhassosi Road and Saeed Al-Sulami Road
    • IC07: Khurais Road and Al-Hareth Bin Abdullah Road
    • IC08: Khurais Road and Ash-Sharq Road
    • IC09: Khurais Road and Marmar Road
    • IC10: Al-Kharj Road and Al-Hilla Road

    The total length of the flyovers is 8.86 kilometres, excluding Junction IC10.

    In addition to the structural steel superstructures, concrete bridge foundations, decks and approach ramps, the contract includes retaining walls, utility diversions, temporary phased traffic arrangements, associated roadworks, drainage networks, roadway lighting, intelligent transportation systems and landscaping.

    The client received commercial proposals from several local and international contractors. Other bidders included:

    • Masco
    • Nesma & Partners
    • Al-Omaier Trading & Contracting Company 
    • Yuksel Saudia 
    • Batco 
    • Modern Building Leaders
    • Sapac

    The urgent bridges initiative is part of Riyadh’s rapid transport infrastructure programme to improve traffic throughput, enhance safety and ease vehicular congestion across central and ring-road corridors ahead of major events, including Expo 2030 and the 2034 Fifa World Cup.

    In July, Mofarreh Group and Turkiye’s Gulsan Holding formed a joint venture to bid for and deliver transport infrastructure projects in Riyadh for RCRC.

    The joint venture said it will target road, bridge, viaduct and interchange projects.

    Mofarreh will provide local market access and operational capacity, while Gulsan will contribute international experience in large-scale transport projects.

    The companies said the new venture will support knowledge transfer and localisation, and promote the use of international engineering and construction standards aligned with Saudi Arabia’s Vision 2030 infrastructure and sustainability goals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20663255/main.png
    Yasir Iqbal
  • Humain tenders 100MW Riyadh AI data centre

    16 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi artificial intelligence infrastructure developer Humain has issued a request for proposals for an engineering, procurement and construction (EPC) contract to deliver a 100MW artificial intelligence (AI) data centre facility in Riyadh’s Al-Saad area.

    The tender was issued on 17 September, with bids due by 8 November.

    The contract includes core-and-shell works; civil works; mechanical, electrical and plumbing installation; testing and commissioning; and site infrastructure across a 350,200-square-metre plot.

    The project also includes an optional expansion phase that could raise total site capacity to 200MW.

    The initial 100MW development is split into two equal 50MW phases, structured across two single-storey IT buildings housing four 25MW data halls.

    Phase one targets a ready-for-service date by October 2028, followed by phase two in January 2029.

    Under the optional phase three, an additional 100MW facility would be brought online by July 2029.

    The data centre will be designed to support high-density graphics processing unit clusters and AI-compute workloads, with rack densities of 240kW to 250kW.

    The facility will be built to Uptime Institute Tier III topology and LEED Silver standards as a baseline, targeting LEED Gold.

    The operational design targets an annualised power usage effectiveness below 1.35.

    Power will be delivered through four 33kV connections supplied by Saudi Electricity Company from two separate high-voltage/medium-voltage primary substations. The scope requires 15 transformers, 15 static 2,250kW IT uninterruptible power supply (UPS) units, and 450kW mechanical UPS systems with lithium-ion battery storage for each 25MW block. 

    Backup emergency diesel generators will be provided on an owner-furnished, contractor-installed basis, with the EPC contractor handling their installation, connection and testing. Fuel storage will provide 24 hours of autonomous run-time, split between on-site underground bulk tanks and generator belly tanks.

    Thermal management combines air and liquid cooling. High-density server racks will be equipped with direct-to-chip liquid cooling loops using coolant distribution units and technical water distribution, paired with air-cooled chillers operating in dual high- and low-temperature loops, alongside fan-wall units.

    The total construction timeline is capped at 25 months from site handover or contract signing, with pre-execution early mobilisation scheduled to start in January 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20661045/main.jpg
    Yasir Iqbal
  • Adnoc Onshore seeks bids for Bu Hasa field EOR project

    16 October 2026

     

    Register for MEED’s 14-day trial access 

    The onshore oil and gas business of Abu Dhabi National Oil Company (Adnoc Onshore) has sought bids from contractors for a key project to increase the oil production capacity of the Bu Hasa oil field, primarily through enhanced oil recovery (EOR) techniques.

    The main objective of the Bu Hasa-Shuaiba EOR Unit 1 (Phase 1) project is to achieve a targeted 70% increase in oil production, extend the Bu Hasa field development’s production plateau and maximise the field’s potential in an economical manner.

    The project aims to confirm and validate the optimum EOR technology for the top-ranked reservoirs/units; assess incremental recovery on top of the improved oil recovery (IOR) wedge; extend the field plateau for as long as is economically feasible; and achieve an ultimate recovery factor of 70% from the Shuaiba reservoir. It will evaluate and execute the recommended EOR option through pattern phasing for any technology proven by Adnoc.

    Adnoc Onshore is understood to have issued the tender for the project on 20 September, with an initial technical bid submission deadline of 8 October, according to sources. The client later extended the technical bid submission deadline to 17 October, sources told MEED.

    The chosen contractor will execute the project under a hybrid contracting strategy comprising:

    • A lump sum (turnkey) EPC scope covering the complete pipeline system from East Hub to the separation plant
    • A call-out-based scope for execution of all WAG injector and WSW tie-in works

    Unless otherwise specified, all activities defined under the contractor’s scope will be deemed included within the lump-sum contract price. This will cover engineering, procurement, construction, testing, pre-commissioning and support to commissioning for a complete and operable system.

    At the Bu Hasa field development, three remote degassing stations (RDS-1/2/3) and two satellite stations, Bida Al-Qemzan and Huwaila, are currently in operation. Production from oil wells completed in Shuaiba, Thamama B, Thamama F, Bida Al-Qemzan and Huwaila is routed via individual flowlines to the three remote degassing stations and the Bida Al-Qemzan and Huwaila stations across different parts of the field.

    Combined production from the wells at each of these stations is routed to the central degassing stations (CDS) via transfer lines ranging from 16 inches to 24 inches in diameter. In addition, some wells in the central part of the field are connected directly to the CDS.

    Previous studies have identified carbon dioxide (CO2) flooding as a promising tertiary recovery mechanism in the Shuaiba reservoir, delivering incremental recovery on top of the IOR wedge (P5 project), extending the field plateau as long as economically feasible, and achieving an ultimate recovery factor of 70% from the Bu Hasa Shuaiba units.

    Located 200 kilometres south of Abu Dhabi city, Bu Hasa is Adnoc Onshore’s westernmost producing field. It is one of Abu Dhabi's biggest onshore assets, with crude oil production capacity of 650,000 b/d. It is also one of the Adnoc Group’s oldest oil fields, having been discovered in 1962 and in production since May 1965.

    As part of the ongoing Bu Hasa Integrated Field Development Project (BUIFDP), 13 new well pads and two pad hubs have been added to the field. Oil, gas and water produced at these sites will be collected at a central gathering facility, then sent through production headers and transfer lines to the CDS for processing.

    Adnoc Onshore is the Adnoc Group’s largest oil-producing subsidiary, accounting for 2 million b/d of oil and about 7 billion cubic feet a day of associated gas production from four main onshore field developments in Abu Dhabi: Bab, Bu Hasa, North East Bab and South East.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20639750/main0548.jpg
    Indrajit Sen
  • OTTCO issues tender for Oman oil storage park expansion

    16 October 2026

     

    Register for MEED’s 14-day trial access 

    Oman Tank Terminal Company (OTTCO) has issued the main tender for a major project related to the expansion of the Ras Markaz crude oil storage complex at Duqm, on the sultanate’s Arabian Sea coast.

    The project, titled Trade Bridge, involves the engineering, procurement and construction (EPC) of eight large storage tanks, each with a capacity of 650,000 barrels. This will increase the Ras Markaz terminal’s total storage capacity by 5.2 million barrels.

    The project represents the next expansion phase (phase 1.4) of the Ras Markaz oil storage terminal within the Special Economic Zone at Duqm (Sezad).

    State-owned OTTCO issued the prequalification notice for the project on 28 July, with contractors submitting initial responses by 4 August and final responses by 19 August, MEED previously reported.

    According to sources, OTTCO issued the main tender for EPC works on Project Trade Bridge in the weeks following completion of the prequalification exercise.

    The following contractors, among others, are understood to have been prequalified by OTTCO to bid for Project Trade Bridge:

    • China Petroleum Pipeline Engineering Company (China)
    • China Tianchen Engineering Corporation (China)
    • Daqing Oilfield Construction Group Company (China)
    • Enppi Muscat (local branch of Egypt-based Enppi)
    • Gulf Petrochemical Services & Trading (Oman)
    • Hualu Engineering & Technology Company (China)
    • Rotary Engineering (Singapore)
    • Sinopec Ningbo Engineering Company (China)

    OTTCO commissioned the first phase of the Ras Markaz crude oil storage park, covering 10 square kilometres and with a capacity of 26.7 million barrels, in December 2022.

    The storage facility has two parts. The first is a marine services area, which includes a floating station for crude imports and exports. This zone is about 7 kilometres offshore and is connected via two 42-inch pipelines and associated facilities.

    In water depths of up to 42 metres, the floating station can accommodate very large crude carriers. It is linked to four main pumps that transfer crude oil to the storage area, which is located more than 120 metres above sea level. OTTCO could add pumps at a later stage to keep pace with future demand for oil storage.

    The second part of the storage facility features oil pumping systems, water treatment facilities, reservoirs, power station networks and other associated systems.

    Region’s largest oil storage park

    OTTCO will build the Ras Markaz oil storage facility in five phases over several years across an area of about 40 square kilometres, for which it signed a land agreement with Sezad in July 2017.

    It will be able to hold 200 million barrels of crude a year. Total investment in the scheme is understood to be $5.2bn.

    The storage terminal in the first phase of the Ras Markaz facility is connected to the estimated $7bn Duqm refinery and other oil-derivatives production plants at Sezad via a pipeline that will supply crude feedstock to the refinery when required.