Egypt utility contracts hit $5bn decade peak
9 February 2026

Egypt’s power and water sector had its strongest year in over a decade in 2025, hitting $5bn in contract awards for the first time since 2015. Power projects accounted for $4.2bn of the total, while water infrastructure awards rebounded to $823m after slumping to $128m the previous year.
Power contracts
In the power sector, the rise in major contract awards was led by wind, solar, waste-to-energy and transmission schemes. The most prominent award was the engineering, procurement and construction (EPC) contract for the 1.1GW Suez wind independent power project, secured by PowerChina.
The project is being developed by Suez Wind Energy, a special-purpose vehicle formed by Saudi Arabia’s Acwa and Egypt-based HAU Energy. Upon completion, it will be one of the largest onshore wind farms globally.
Despite dipping from the previous year, solar accounted for about $1bn of total awards.
Independent forecasts suggest Egypt’s renewable capacity could reach around 31.6GW and account for roughly 42% of the electricity mix by 2035, pointing to sustained growth in solar and wind.
In November, a consortium of local firms Hassan Allam Utilities and Infinity Power won contracts to develop two solar photovoltaic (PV) projects with a combined capacity of 1,200MW, supported by 720MWh of battery storage under agreements with the Ministry of Electricity & Renewable Energy and the Egyptian Electricity Transmission Company.
Meanwhile, a joint venture of China Energy Engineering Corporation and Jiangsu Power Design Institute was appointed main contractor for the country’s first waste-to-energy plant.
The Abu Rawash facility in Giza will process 1,200 tonnes of municipal waste a day to generate 30MW of electricity and is expected to begin operations in 2029.
Grid reinforcement also progressed with PowerChina awarded the EPC contract for lots two and three of the East Ismailia-Zagazig 500kV overhead transmission line, a 130-kilometre corridor crossing the Suez and Al-Sharqia governorates.
Project milestones
Beyond the main contract awards, several major projects passed key development stages.
In December, UAE’s Amea Power and Japan’s Kyuden International Corporation reached financial close on a $700m project comprising a 1,000MW solar plant and 600MWh battery system in Aswan. The scheme is backed by a $570m debt package led by the International Finance Corporation and is expected to become Africa’s largest single-asset solar and storage facility when it enters operation this year.
Amea also commissioned a separate 300MWh battery energy storage system in Aswan in July, integrated with its existing 500MW Abydos solar plant, marking Egypt’s first utility-scale storage deployment.
Hybrid projects have also seen increased investor interest, with France’s EDF Power Solutions recently acquiring a 20% stake in the 1.1GW Obelisk solar-battery scheme near Luxor, joining Scatec and Norfund as shareholders.
At El-Dabaa, the nuclear programme entered a new phase as Egypt placed its first fuel order with Rosatom and installed the initial VVER-1200 reactor pressure vessel for Unit 1. These steps mark the shift from civil construction to mechanical and systems installation, following the granting of construction permits for all four units between 2022 and 2023.
The focus of procurement is set to shift decisively towards water in the next 12 to 18 months, with $3.54bn of projects at the prequalification stage and $917m currently under bidding or bid evaluation
Water contracts
Egypt’s water sector showed early signs of recovery following a sharp slowdown the previous year. The largest award was secured in June by a joint venture of Hassan Allam Construction and Metito Utilities. It involves the Alexandria West wastewater treatment plant upgrade, which will convert the facility from primary to secondary treatment and lift capacity to 600,000 cubic metres a day (cm/d) through new sludge digestion, biogas and process units.
Hassan also won the main contract for the $150m Abu Qir seawater reverse osmosis plant, adding 80,000 cm/d of potable supply, as part of a consortium with Water & Environment Technologies Company (Wetico).
Further awards were led by local contractors including Intech, a Hassan Allam Holding subsidiary, appointed to deliver the EPC works for the Marsa Matrouh extension, doubling capacity to 60,000 cm/d.
Among international contractors, Kuwait’s Mohammed Abdulmohsin Al-Kharafi & Sons secured the main contract for the $104m Tanta rehabilitation project in Gharbia, delivering 100,000 cm/d of new treatment capacity.
Shift in focus
The focus of procurement is set to shift decisively towards water in the next 12 to 18 months, with $3.54bn of projects at the prequalification stage and $917m currently under bidding or bid evaluation.
Egypt is among the region’s most water-constrained countries, with demand exceeding renewable supply by about 7 billion cubic metres a year and per-capita availability of roughly 500 cubic metres, far below the international scarcity threshold.
As of February 2026, almost $500m-worth of water infrastructure contracts are under main bidding, including the $157m fourth extension of the Giza wastewater treatment plant, led by Construction Authority for Potable Water and Wastewater (CAPW).
The project will add 400,000 cm/d of treatment capacity to supply recycled water for the Barakat drainage system and support 29,000 acres of irrigation. The contract was recently retendered, with bids due by 30 March.
In the medium-to-long term, the scale of schemes moving through prequalification suggests Egypt could be on the cusp of a major upswing in water investment.
The pipeline is led by projects such as the Hammam desalination plant on the North Coast, the New Alamein and Matrouh seawater schemes, and new wastewater treatment and reuse facilities linked to agricultural development zones.
If a meaningful share of these $3.54bn projects moves into main tendering, annual water awards would likely surpass recent years and begin to rebalance a utilities market dominated by the power sector.
Exclusive from Meed
-
Safety and security matters3 April 2026
-
Saudi forecast remains one of growth3 April 2026
-
-
-
Oman’s Nama PWP tenders consultancy contract3 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Safety and security matters3 April 2026
Commentary
Colin Foreman
EditorRead the April issue of MEED Business Review
Employment and investment opportunities in a low or no-tax environment have been key attractions for people and businesses located in the GCC for decades. Another crucial factor has been safety and security.
That reputation has been tested by the missile and drone attacks that began on 28 February. Whether the GCC’s safe haven status has been damaged depends on perspective.
For some, the fact that attacks occurred fundamentally changes how the region is viewed. For others, the ability to absorb a serious shock, respond quickly, and keep daily life and businesses functioning demonstrates resilience.Any assessment of safety is also relative. Many people and businesses that relocate in the GCC do so not only for opportunity, but because of dissatisfaction elsewhere. Common reasons include limited economic prospects, high taxation, distrust in political leadership and concerns about personal safety. Even with the recent conflict, the GCC may still compare favourably for those considering these factors.
There is no doubt that missile and drone attacks are extremely dangerous, and the fear of further incidents can linger. Even if attacks are infrequent, the uncertainty matters. It can influence personal decisions, travel advice, and the cost of insurance and risk management. These perceptions will shape the region’s attractiveness.
Safety concerns vary. In many parts of the world, higher levels of crime are an everyday worry for residents and businesses. For some, the GCC may still feel like the better option, provided the current tensions do not become the new normal.
How this question is answered will play an important role in how the region’s economies perform in the period ahead. If confidence returns quickly and the risk is seen as contained and manageable, investment and hiring will likely rebound faster than many expect. If uncertainty persists or escalates, the road to recovery will be a long one.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16250747/main.gif -
Saudi forecast remains one of growth3 April 2026

MEED’s April 2026 report on Saudi Arabia includes:
> COMMENT: Risk accelerates Saudi spending shift
> GVT &: ECONOMY: Riyadh navigates a changed landscape
> BANKING: Testing times for Saudi banks
> UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
> DOWNSTREAM: Saudi downstream projects market enters lean period
> POWER: Wind power gathers pace in Saudi Arabia
> WATER: Sharakat plan signals next phase of Saudi water expansion
> CONSTRUCTION: Saudi construction enters a period of strategic readjustment
> TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure pushTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16250096/main.gif -
Dubai seeks consultants for Al-Khawaneej stormwater project3 April 2026
Dubai Municipality has issued a consultancy tender to assess and upgrade the stormwater drainage system serving the Al-Khawaneej First residential district in northeastern Dubai.
The project, listed as TF-22-E1, covers the upgrading and rehabilitation of the stormwater system in the area. The tender has been issued by the municipality’s Sewerage and Recycled Water Projects Department.
The bid submission deadline is 23 April.
The works form part of Dubai’s wider efforts to strengthen flood resilience and support sustainable urban infrastructure development.
Two separate consultancy tenders were issued in March as part of a broader review of the emirate’s water and wastewater infrastructure to support future population growth.
One involves a study to develop a sustainable urban drainage systems strategy across the emirate. The other covers a review of the emirate’s sewage treatment and recycled water distribution strategy.
The Al-Khawaneej First consultancy role will include data collection, site investigations and an assessment of existing drainage conditions.
Additionally, the consultant will be required to identify flooding hotspots and evaluate the performance of the current system.
The project covers the preparation of preliminary and detailed designs, tender documents and construction packages as well as construction supervision through to project handover.
The municipality added that integrated drainage solutions are to be developed as part of the package, including sustainable drainage systems (SuDS) and nature-based approaches to address current and future stormwater demand.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16249098/main.jpg -
Developer plans two residential schemes in Saudi Arabia3 April 2026
Saudi developer Alramz Real Estate is planning two new residential developments in Jeddah and Riyadh.
In a Tadawul filing on 31 March, Alramz said it had signed an agreement with Oud Capital to establish a sharia-compliant real estate investment fund to develop the Alramz Front project in Jeddah’s Al-Firdous district.
The fund is targeting approximately SR650m ($173m), with Alramz committing about SR81.6m. The company will also contribute land totalling around 47,800 square metres, valued at SR215m, as an in-kind contribution.
The project is expected to deliver nearly 900 residential units. Alramz will serve as developer and exclusive marketer under a development contract valued at about SR269m.
Separately, Alramz said it had acquired mixed-use plots in Riyadh’s Al-Malqa district for SR94.6m. The 8,600 sq m site will be developed into a residential scheme comprising approximately 135 apartments.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16249064/main.jpg -
Oman’s Nama PWP tenders consultancy contract3 April 2026
Oman’s Nama Power & Water Procurement Company (Nama PWP) has opened a tender for the provision of environmental, social and governance (ESG) reporting consultancy services.
The tender seeks proposals from interested parties to support the utility in assessing its ESG maturity and identifying gaps against the Oman Investment Authority’s ESG guidelines.
The deadline for firms to submit offers is 10 May.
According to the tender notice, the selected consultant will develop the required ESG policies, strategy, report and implementation roadmap.
Nama PWP, part of Nama Group, said the scope of work is intended to support the company’s wider ESG framework as it continues to procure new power and water capacity in Oman.
The utility also recently opened a tender seeking proposals from qualified law firms to provide legal consultancy services in Oman.
The selected firms will be included on a panel and engaged on an as-needed basis. They will deliver legal advisory services across a range of matters relevant to Nama PWP’s business.
The deadline for firms to submit offers is 21 April.
In March, the state utility released its latest seven-year plan outlining the rapid expansion of solar and wind projects.
It expects the renewable energy share of Oman’s power generation mix to increase steadily across the period, reaching 16% in 2028 and 21% in 2029 before rising to 30% in 2030. This compares to about 4% in 2024.
The pipeline includes a series of large-scale independent power projects scheduled for delivery between 2027 and 2031.
Solar photovoltaic capacity in the sultanate is projected to rise from 1.54GW in 2024 to 23.26GW by 2031. Wind capacity is expected to grow from 120MW to 6.75GW,
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16249021/main.jpg