Managing risk in the GCC construction market
19 December 2025

The scale and complexity of construction projects under way in the GCC region has attracted global attention. And while large-scale project announcements continue to dominate the headlines, the underlying risks – insufficient financing, harsh contract clauses and a tendency to delay dispute resolution – are often overlooked.
Around the region, many contractors are experiencing difficulties once projects have started because they mistakenly believe they have the necessary in-house skillsets to navigate these complex issues.
MEED has convened a panel of construction consultants and specialists to develop a checklist to help contractors and subcontractors operating in the region to navigate the market’s challenges as the sector moves into 2026.
The proactive steps are aimed at positioning a company so that it can maximise recovery and mitigate threats posed by unresolved claims and poor commercial or contractual administration.
Systemic risk
The regional market is characterised by several systemic issues that amplify risks for contractors.
The fundamental problem is finance. Projects frequently suffer because they are not fully financed from the start, which places financial strain on contractors. This problem is then compounded by the region’s traditional contractual environment, which means disputes are typically not finalised until well after jobs have been completed, creating cash flow problems for contractors, particularly near the end of such projects.
Further financial strain is created by unconditional performance guarantees and retention. The combined requirement for advance payment bonds, a 10% performance bond and sometimes 5%-10% retention represents a significant draw on contractors’ cash flow. The growing tendency of employers to pull bonds further exacerbates the situation.
Many contractors sign up to one-sided contracts so as to secure more work, rather than challenging their employers. Key contractual issues include:
> Unrealistic timelines: Contractors set themselves up to fail by accepting unrealistic timescales on projects, despite the knowledge that the work often takes twice as long.
> Deficient design: A major risk, particularly on high-profile projects, is a lack of specification and design progress. Many contracts, such as the heavily modified Silver Book – a standard contract published by the International Federation of Consulting Engineers (Fidic) for turnkey engineering, procurement and construction projects – presuppose that the contractor has sufficient information to design, build and deliver, even when there is substantive information missing, which renders lump-sum pricing obsolete and inevitably leads to dispute.
> Lowest-bid mentality: Contractors often fail to factor necessary commercial support from legal and claims specialists into their tender figures, making their bid appear more competitive but leaving them without a budget to seek help until it is too late. As a result, projects are managed with budgets that are barely sufficient, rather than being run properly to a successful conclusion.

Supply-chain erosion
The quality and capacity of the subcontractor market, particularly in the mechanical, electrical and plumbing (MEP) field, has eroded significantly.
Some major MEP players have closed or left the market due to underpricing, prompting contractors to call in their performance bonds. This means the region is receiving progressively lower quality for increasingly higher costs, further straining the delivery phase for main contractors.
The risk of subcontractor insolvency is increasing and must now be considered a primary project risk. Contractors should monitor financial health, diversify subcontractor dependencies, challenge allocated resources and secure step-in rights wherever possible.
Many Silver Book contracts in the GCC now include heavily amended, employer-friendly clauses that push design and ground-risk even further onto the contractor – often beyond what Fidic intended. These amendments require careful review and firm pushback.
The GCC remains a market of opportunity, but success in 2026 will belong to contractors that combine disciplined tendering, transparent commercial governance and early issue resolution. Optimism is not a strategy; preparation is.
A 10-point checklist for contractors in 2026
|
1. Mandate contractual due diligence: Invest time and money into a thorough contract review before signing. Be prepared to challenge harsh clauses, particularly those unfairly allocating risk, such as unknown conditions and full design responsibility. Assume that bespoke rather than standard amendments govern your entitlement. Treat the special conditions as the real contract. |
|
2. Factor commercial support into the budget: Do not omit the cost of essential commercial support from the tender, such as quantity surveyor teams, quantum and delay specialists, legal review and claims preparation. Even if not visible in the front-line figures, this cost – which could be as low as 0.01% of the project value – must be factored in to ensure a budget for early and continuous engagement. |
|
3. Prepare a realistic baseline programme: Stop committing to programmes just to fit the tender. Develop a realistic programme from the start, identifying risks and including necessary code books to track delays early. Consider commissioning an independent programme review at the tender stage – this is common internationally and reduces later arguments about logic, durations and sequencing. |
|
4. Confirm project funding: Ensure that the project financing is fully in position before starting work. Many problems stem from projects that are only partially financed, leading to cash running out near completion. Gone are the days of not asking employers for greater transparency when it comes to funding projects. |
|
5. Establish a strong commercial and claims function: This is where commercial management starts. Set up systems to ensure contractual compliance, including seven-day claim notifications. Variations are inevitable, and proper substantiation is required to secure entitlement – if it is not recorded, it cannot be recovered. Diaries, cost records and notice logs remain the foundation of entitlement. |
|
6. Seek early specialist engagement: Prevention is better than a cure. Bring in specialists early to examine time and cost issues before problems arise. Consultants can provide advice, help set up the correct commercial systems and prevent the escalation of unresolved issues. |
|
7. Adopt an old-school approach to claims management: Technology is useful, but nothing beats resolving issues face to face. Engage directly with the employer’s team regularly to negotiate and agree claims early. This manages the client’s expectations when it comes to budgeting and allows the contractor to secure cash flow sooner. A simple early-warning culture – even when not contractually required – prevents surprises and builds trust with the client. |
|
8. Avoid wasting resources: Focus claims efforts only on events that are actually recoverable and demonstrably critical. Contractors often waste time chasing things that will not be recoverable. Prioritise issues that are both time-critical and clearly fall under the employer’s risk – everything else should be logged but not pursued aggressively. |
|
9. Upskill internal teams: Use specialist involvement as an opportunity to upskill your in-house commercial team. Have them sit alongside specialist consultants to learn proper commercial and contractual administration processes, creating a lasting work-culture benefit. |
| 10. Push for faster dispute resolution: When a dispute arises, advocate for a swift resolution mechanism like adjudication, mediation or expert determination to temporarily resolve cash flow issues. Dispute adjudication boards are intended to give quick, interim decisions. However, if not set up from the start of the project, the process becomes protracted – sometimes taking many months – so fails to provide the cash-flow relief contractors urgently need. Where clients resist adjudication, propose interim binding mediation or expert determinations, or failing this, milestone-based dispute workshops – anything that accelerates getting cash back on site. |
MEED would like to thank Refki El-Mujtahed of REM Consultant Services (refki@rem-consultant.com; www.rem-consultant.com) for facilitating this article, as well as the following co-contributors:
Aevum Consult | Lawrence Baker | lawrence.baker@aevumconsult.com | www.aevumconsult.com
Decerno Consultancy | Lee Sporle | leesporle@decernoconsultancy.com | www.decernoconsultancy.com
Desimone Consulting | Mark Winrow | Mark.Winrow@de-simone.com | www.de-simone.com
Forttas | Derek O’Reilly & Martin Hall | derek.oreilly@forttas.com & martin.hall@forttas.com | www.forttas.com
IDH Consult | Ian Hedderick | ian.hedderick@idhconsult.com | www.idhconsult.com
White Consulting | Nigel White | nigelwhite@whiteconsulting-me.com | www.whiteconsulting-me.com
Exclusive from Meed
-
Dubai seeks consultants for drainage projects6 February 2026
-
Modon tenders Ras El-Hekma construction contracts6 February 2026
-
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
-
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
-
Chinese firm wins Ceer automotive supplier park deal6 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai seeks consultants for drainage projects6 February 2026
Dubai Municipality has invited consultants to qualify for a contract to supervise three stormwater drainage projects under the $8bn Tasreef programme.
The contract, titled TF-15-S1 Supervision of Stormwater Drainage System projects – Package 2, will be awarded as a single package with dedicated teams assigned to each project.
The request for qualifications (RFQs) was issued by the municipality’s Sewerage and Recycled Water Projects Department (SRPD).
The bid submission deadline is 26 February.
The first scheme under the package is TF-16-C1, which involves upgrading and rehabilitating the stormwater system east of the Dubai Canal.
The second, TF-15-C2, will deliver stormwater links along Umm Suqeim Road to serve the Al-Barsha and Al-Quoz communities.
The third project, TF-13-C1, focuses on developing a drainage system for the Al-Marmum area.
Several engineering, procurement and construction (EPC) contracts have been awarded under the Tasreef initiative, which aims to expand Dubai’s rainwater drainage capacity by 700% by 2033
In January, local firm DeTech Contracting won the main contract to construct a stormwater drainage system in Jebel Ali.
The project, listed under TF-05-C1, covers approximately 27 kilometres of stormwater network and will serve major transport routes, including Sheikh Zayed Road and Al-Jamayel Road.
Separately, Dubai Municipality has opened bidding for EPC contracts to expand and rehabilitate the emirate’s sewerage networks.
The four projects cover more than 95km of recycled water and sewerage pipelines.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593832/main.jpg -
Modon tenders Ras El-Hekma construction contracts6 February 2026

Abu Dhabi-based developer Modon Holding has tendered several contracts as part of the first phase of development at Ras El-Hekma, a planned new city on Egypt’s Mediterranean coast.
MEED understands that the tenders were issued in January.
These include:
DP3 assets: covering 146 residential villas, 590 three-bedroom townhouses, 356 four-bedroom townhouses, a mall and other associated works.
Bids due on 23 February.
DP4 assets: DP4 includes 54 villas, a clubhouse and other associated infrastructure.
Bids due on 2 March.
DP5 assets: The scope covers the construction of two hotels, branded residences, a retail facility and other associated works.
Bids due on 10 March.
DP6 assets: This package covers a 200-key Montage hotel, 96-unit Montage-branded residences and related infrastructure.
Bids due on 17 March.
DP7 assets: 120 five-bedroom villas, 230 seven-bedroom villas, 284 branded residential units and other infrastructural works.
Bids due on 3 March.
MEED understands that the contract duration for all these packages is 21 months from the start of construction.
Modon has accelerated development works at Ras El-Hekma this year. In January, MEED reported that Modon Holding had awarded a E£15bn ($316m) contract for the construction of a project at Ras El-Hekma.
The contract was awarded to the local firm Orascom Construction.
The scope of the contract covers the construction of residential units, commercial facilities and a 70-key hotel.
In September, MEED reported that Modon Holding had tendered contracts for the infrastructure works for the first phase of the Ras El-Hekma project.
As part of the first phase, Modon plans to develop more than 50 million square metres (sq m), including hotels and a marina.
Ras El-Hekma is on a spur of land on Egypt’s northern Mediterranean coastline, about 240 kilometres west of Alexandria.
Last year, Abu Dhabi-based holding company ADQ appointed Modon Holding as the master developer for the Ras El-Hekma project.
According to an official statement, Modon will act as the master developer for the entire development, which will cover more than 170 million sq m.
Modon Holding will develop the first phase of the project, which will cover 50 million sq m.
The remaining 120 million sq m will be developed in partnership with private developers under the supervision of the recently established ADQ subsidiary Ras El-Hekma Urban Development Project Company and Modon Holding.
In September 2024, Modon signed several memorandums of understanding (MoUs) with local and international firms to join the development. It signed a framework agreement with Orascom Construction to serve as the primary contractor for the project’s first phase.
Ras El-Hekma is planned as a combined business and leisure destination, with hotels, leisure facilities, a free zone, a financial district and residential components.
The master development has been billed as capable of attracting over $150bn in investment.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593388/main.jpg -
Egypt contractor secures €58m loan for Hungary power plant6 February 2026
Commercial International Bank Egypt (CIB) has provided €58m in credit facilities to local firm Elsewedy Electric for the construction of a combined-cycle gas turbine (CCGT) power plant in Hungary.
Located in Visonta, the plant will be the largest combined-cycle facility built in Hungary in decades and the country’s first power plant capable of using hydrogen.
Once complete, hydrogen will be able to supply up to 30% of the plant’s fuel needs.
The project is being developed through a consortium comprising Energy Projects, a subsidiary of Elsewedy Electric, and local firms Status KPRIA and West Hungaria Bau (WHB).
It was awarded by MVM Matra Energia, a subsidiary of Hungary’s state-owned power holding company Magya Villamos Muvek (MVM).
As MEED understands, the plant is expected to have a power generation capacity of between 500MW and 650MW.
Total investment in the scheme is estimated at about €700m, with CIB acting as the sole financier for Elsewedy Electric’s portion of the project.
Construction officially began last September, with commercial operations scheduled for 2028.
The scheme also represents Elsewedy Electric’s first major investment in Europe, adding to other foreign investment interests.
Last May, it was reported that Elsewedy Electric intends to build a $100m electrical cable manufacturing plant in Iraq. This project has yet to advance beyond the initial stages.
In 2024, the contractor connected three additional hydro turbine generators to Tanzania’s national power grid in partnership with The Arab Contractors.
This brought the total power supply from the Julius Nyerere hydroelectric power project to 705MW.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15593289/main.jpg -
AD Ports signs Jordan Aqaba port PPP deal6 February 2026
Abu Dhabi’s AD Ports Group has signed an agreement with Jordan’s Aqaba Development Corporation (ADC) to manage and operate the Aqaba multipurpose port.
AD Ports will manage and operate the port under a 30-year concession agreement.
Under the agreement, AD Ports and ADC will establish a joint venture to oversee port operations.
AD Ports will hold a 70% stake in the joint venture, with the remaining 30% held by ADC.
AD Ports Group will also invest AED141m ($38.4m) in the joint venture.
The signing ceremony was held at the Aqaba Special Economic Zone Authority headquarters in Aqaba on 5 February.
The agreement was signed by Hussein Safadi, CEO of ADC, and Ahmed Al-Mutawa, regional CEO of AD Ports Group.
Aqaba port handles about 80% of Jordan’s exports and 65% of its imports.
It serves as a key transit point for Jordan’s neighbouring countries, including Saudi Arabia and Iraq. The port has an annual handling capacity of 11 million tonnes, supported by nine berths, a quay length of 2 kilometres and a draft of 13.5 metres.
In 2025, the terminal handled over 5.3 million tonnes of cargo and nearly 85,000 car equivalent units of Ro-Ro imports.
Abu Dhabi has been deeply involved in making investments in Jordan’s infrastructure sector. In February last year, AD Ports Group signed an agreement to manage and operate the Al-Madouneh customs centre in Amman, as MEED reported.
The Al-Madouneh customs centre covers about 1.3 million square metres (sq m) and was inaugurated in June last year.
The announcement followed AD Ports Group’s signing of a shareholders’ agreement in January 2024 between its digital arm, Maqta Gateway, and Jordan’s Aqaba Development Corporation regarding their existing joint-venture company, Maqta Ayla.
The joint venture company will upgrade operations at the Aqaba port complex in Jordan by implementing a port community system “that leverages Maqta Gateway’s expertise, also marking the first-ever export of Abu Dhabi’s key port digitalisation solution”, AD Ports said in a statement.
AD Ports Group operates the Aqaba cruise terminal, and selected Dubai-based real estate developer Mag Group to lead the first phase of the Marsa Zayed mixed-use project.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592973/main.jpg -
Chinese firm wins Ceer automotive supplier park deal6 February 2026

Beijing-headquartered Metallurgical Construction Corporation (MCC) has won a contract to undertake the steel structure works on the Ceer automotive supplier park in King Abdullah Economic City (KAEC).
The supplier park is located next to Ceer’s electric vehicle (EV) production facility in KAEC.
The automotive supplier park will include production and ancillary facilities for various suppliers and provide the material supply infrastructure for Ceer’s EV plant.
The facilities include:
- Cold stamping, body-in-white assembly and stamping facility – Shin Young (South Korea)
- Hot stamping, sub-frames and axles subsystem supply facility – Benteler Group (Austria)
- Façade and exterior-trim supply facility – JVIS (US)
- Instrument panel, trims and console supply facility – Forvia (France)
- Seat supplier – Lear Corporation (US)
Earlier this week, MEED exclusively reported that Ceer had awarded a contract to build the automotive supplier park to Jeddah-based construction firm Modern Building Leaders (MBL).
Netherlands-based engineering firm Arcadis is the project consultant, and Pac Project Advisors is the project management consultant.
Ceer retendered the project in September last year.
The latest contract award is another significant contract win for MCC in Saudi Arabia. In January, MEED reported that MCC had won a contract to undertake the steel structure works on Mohammed Bin Salman Stadium at the Qiddiya City project on the outskirts of Riyadh.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
In January, MCC won another contract to undertake steel structure works for the expansion of Medina airport in Saudi Arabia.
The scope covers work on boarding bridges, Terminal Two and the renovation of Terminal One.
READ THE FEBRUARY 2026 MEED BUSINESS REVIEW – click here to view PDFSpending on oil and gas production surges; Doha’s efforts support extraordinary growth in 2026; Water sector regains momentum in 2025.
Distributed to senior decision-makers in the region and around the world, the February 2026 edition of MEED Business Review includes:
> AGENDA: Mena upstream spending set to soar> INDUSTRY REPORT: MEED's GCC water developer ranking> INDUSTRY REPORT: Pipeline boom lifts Mena water awards> MARKET FOCUS: Qatar’s strategy falls into place> CURRENT AFFAIRS: Iran protests elevate regional uncertainty> CONTRACT AWARDS: Contract awards decline in 2025> LEADERSHIP: Tomorrow’s communities must heal us, not just house us> INTERVIEW: AtkinsRealis on building faster> LEADERSHIP: Energy security starts with rethinking wasteTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/15592955/main.gif