Contractors submit bids for next Upper Zakum field expansion
28 November 2025

Register for MEED’s 14-day trial access
Contractors have submitted technical proposals for the next expansion phase of the Upper Zakum offshore field development in Abu Dhabi, aimed at increasing the asset’s oil production potential to 1.5 million barrels a day (b/d).
The offshore oil and gas production business of Abu Dhabi National Oil Company (Adnoc Offshore) is understood to have issued the main tender for engineering, procurement and construction (EPC) works for the UZ 1.5MMBD project in the third quarter of this year, according to sources.
Adnoc Offshore has divided the project's EPC scope of work into three packages, according to sources.
Contractors submitted technical bids for package 1 by 21 November, while proposals for packages 2 and 3 were submitted by 14 November, sources told MEED.
MEED reported last November that Adnoc Offshore had awarded a contract for front-end engineering and design (feed) and pre-feed services on the project to France-headquartered contractor Technip Energies.
A kick-off meeting between Adnoc Offshore and Technip Energies took place on 21 November last year, it was previously reported.
Located 84 kilometres offshore in Abu Dhabi, Upper Zakum is the world’s second-largest offshore oil field and fourth-largest oil field.
The UZ 1.5MMBD project is the latest crude output expansion project that Adnoc Offshore has undertaken at the Upper Zakum field development.
Upper Zakum expansion
The first phase of the programme to raise the Upper Zakum offshore field development’s oil production capacity to 1.2 million b/d was launched in 2019. The initial goal was to increase the field’s output potential to 1 million b/d by 2024, which was later increased to 1.2 million b/d, with the project execution timeline eventually extended.
In April last year, MEED reported that Adnoc Offshore had awarded the main EPC contract for the UZ 1.2MMBD EPC-1 project to UAE-based Target Engineering Construction Company. The value of the contract was estimated to be $825m.
The project’s main scope involved the EPC of several surface facilities and plants at the Upper Zakum offshore development’s four main artificial islands: Al-Ghallan, Umm Al-Anbar, Ettouk and Asseifiya – also known as Central Island, West Island, North Island and South Island, respectively.
Spanish contractor Tecnicas Reunidas won the contract for the feed works on the UZ 1.2MMBD EPC-1 project in 2019. UK-headquartered Wood Group was appointed as the project management consultant for the EPC phase.
In November 2024, MEED reported that Adnoc Offshore had also selected Target for the second phase of the Upper Zakum 1.2 million b/d project (UZ 1.2MMBD EPC-2). The value of the contract was estimated to be about $500m, according to sources.
Target began work on the project in December last year, MEED previously reported.
The scope of work on the UZ 1.2MMBD EPC-2 project covers the EPC of several structures on Assefiya Island.
Adnoc Offshore performed the feed work on the UZ 1.2MMBD EPC-2 project in-house.
Upper Zakum oil production
Adnoc Offshore has committed to a total capital expenditure budget of approximately $30bn, along with its operating partners in the Upper Zakum hydrocarbons concession, Japan Oil Development Company (Jodco) and US-based ExxonMobil.
The strategic objective is to first raise the asset’s oil output from 640,000 b/d to 750,000 b/d through the UZ 750 project, then to 1.2 million b/d through the two phases of the ongoing UZ 1.2MMBD project, and eventually to 1.5 million b/d.
Zakum Development Company (Zadco), which later merged into Adnoc Offshore, awarded EPC contracts for the UZ 750 project in 2012 and early 2013.
The $817m first package was awarded to a consortium of Abu Dhabi’s NMDC Energy (then known as National Petroleum Construction Company) and Technip Energies. Package two, the project’s largest EPC package, worth $3.7bn, was awarded to a consortium of UK-headquartered Petrofac and South Korea’s Daewoo Shipbuilding & Engineering.
EPC work on UZ 750 began in 2014 and was completed in 2022.
In October 2022, Adnoc Group subsidiary Adnoc Drilling set a world record for drilling the longest oil and gas well at the Upper Zakum concession, stretching 50,000 feet.
The extended-reach wells will tap into an undeveloped part of the Upper Zakum reservoir, potentially increasing the field’s production capacity by 15,000 b/d without expanding or building any new infrastructure, Adnoc said.
ALSO READ: Adnoc strives to build long-term upstream potential
Exclusive from Meed
-
Malaysian contractor wins $299m Burj Azizi deal14 April 2026
-
Local firm executing Yasref tail gas treatment project14 April 2026
-
Kuwait sets April deadline for $718m drainage tender14 April 2026
-
Local firm makes hydrocarbon discovery in Oman’s Block 714 April 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Malaysian contractor wins $299m Burj Azizi deal14 April 2026
Malaysia’s Eversendai Corporation has secured a AED1.1bn ($299m) contract to carry out steel structure works on the Burj Azizi tower on Sheikh Zayed Road in Dubai.
The contract was awarded by local real estate developer Azizi Developments.
The main construction works on the tower are being carried out by Gardinia Contracting, a subsidiary of Azizi Developments.
Construction of the 131-storey tower is under way and is expected to be completed by 2029.
Azizi has appointed France’s Soletanche Bachy to perform the foundation works.
MEED reported in July 2023 that Azizi Developments had announced plans to construct the Burj Azizi in Dubai.
Previously, another Dubai-based developer, Meydan, had planned to build the 100-storey Meydan Tower on the same site, but the project was put on hold shortly after initial works began in 2017.
In September 2022, Azizi Developments purchased a plot of land from Meydan on Sheikh Zayed Road next to World Trade Centre Metro Station 2. No further details were officially released at the time, although the developer said it was working on the design for a large, iconic development on the plot.
In June 2023, Azizi Developments announced it would build what it called “Dubai’s newest seven-star hotel”.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16384636/main.jpeg -
Local firm executing Yasref tail gas treatment project14 April 2026

Yanbu Aramco Sinopec Refining Company (Yasref) is overseeing progress on a key project to build a tail gas treatment unit (TGTU) at its crude refinery complex, located in Yanbu on the west coast of Saudi Arabia.
Yasref is a joint venture in which Saudi Aramco owns the majority 62.5% stake and China Petroleum & Chemical Corporation (Sinopec) owns the other 37.5%. The Yasref refinery was commissioned in 2015 and has a crude oil refining capacity of 400,000 barrels a day (b/d).
The aim of the project, which Yasref calls the tail gas synergy project, is to significantly reduce emissions of sulphur dioxide (SO₂) and hydrogen sulphide (H₂S) from its production complex. The 'synergy' comes from integrating primary treatment (such as the Claus process, which typically recovers about 95-97% of sulphur) with advanced secondary treatment in a TGTU, to achieve overall sulphur recovery of nearly 99.9%.
Yasref awarded the main contract for the tail gas synergy project to Jeddah-based contractor Carlo Gavazzi Arabia earlier this year, according to information obtained by MEED Projects, with the contract estimated at $80m.
The local branch of London-headquartered Berkeley Engineering Consultants is acting as the project’s main consultant, according to MEED Projects.
The scope of work on Yasref’s tail gas synergy project includes the following:
- Construction of downstream TGTU with catalytic hydrogenation reactor and amine absorber train
- Modification of existing sulphur recovery units
- Construction of acid gas removal units employing amine solvent systems
- Construction of desulphurisation units including carbonyl sulphide hydrolysis
- Construction of associated utilities and auxiliary infrastructure: thermal exchangers, power and steam supplies, flare knockout drums
- Installation of safety and security systems hydrogen sulphide detection, overpressure relief, firewater deluge, access control, safety instrumented systems
- Integration of emission monitoring and process control instrumentation.
In April last year, Aramco, Sinopec and Yasref signed a venture framework agreement for a potential petrochemicals expansion of the Yasref refinery complex into a major integrated petrochemicals facility. The project would include a large-scale mixed-feed steam cracker with a capacity of 1.8 million tonnes a year (t/y) and a 1.5 million-t/y aromatics complex, along with associated downstream derivatives.
MEED understands that the Yasref petrochemicals expansion project, which is also referred to as Yasref+, is part of Aramco’s $100bn liquids-to-chemicals programme.
The central ambition of the strategic programme is to derive greater economic value from every barrel of crude produced in Saudi Arabia by converting 4 million b/d of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.
ALSO READ: Saudi downstream projects market enters lean period
https://image.digitalinsightresearch.in/uploads/NewsArticle/16383830/main3043.jpg -
Kuwait sets April deadline for $718m drainage tender14 April 2026
Kuwait’s Ministry of Public Works has set a 21 April deadline for a major tender estimated to be worth about KD222m ($718m).
The tender scope covers the construction of rainwater drainage networks across the residential areas of Sabah Al-Ahmad, South Sabah Al-Ahmad, Al-Khairan and Al-Wafra.
The Ministry of Public Works floated the tender on 22 March.
According to regional projects tracker MEED Projects, the works include the construction of a major concrete sewer, three collection basins and extensive stormwater drainage basins.
Rainwater collection tanks will be connected through an independent network, with outlets to the sea via the Nuwaiseeb exit to manage overflow.
The infrastructure will also filter pollutants such as oils, minerals and sediments to protect water quality and support environmental sustainability.
The project aims to reduce surface runoff, prevent street and urban flooding, and improve groundwater recharge.
UK analytics firm GlobalData expects Kuwait’s construction industry to grow by 5.1% in 2026-29, supported by government investment in the oil and gas sector aimed at raising production, as well as investment in the infrastructure sector.
In the short term, growth will be boosted by planned expenditure under the 2025-26 budget, which was approved in March 2025.
The construction industry in Kuwait is expected to record an annual average growth rate of 4.9% in 2026-29, supported by investments in renewable energy, transport, and oil and gas projects.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16383203/main.jpg -
Local firm makes hydrocarbon discovery in Oman’s Block 714 April 2026
Omani oil and gas exploration and production company Masar Petroleum has announced a discovery in the Hasirah Ridge in the sultanate’s Block 7.
Masar Petroleum was the inaugural operator to appraise and produce hydrocarbons from the Hasirah reservoir in Block 7 in 2017.
Building on that experience, Masar Petroleum has now successfully drilled a new exploration well south of its existing discoveries, validating the concept of the Hasirah Ridge — a geological trend 5 kilometres wide and 30km long mapped across Block 7 using 2D seismic data.
This discovery represents the first step towards unlocking the Ridge’s prospective resource base of 100 million to 380 million barrels, Masar Petroleum said in a statement.
Following this discovery, a planned 3D seismic survey and exploration and appraisal programme is expected to advance the development of the new resources by the end of 2028.
First production from this field is expected to come on stream during the last quarter of this year.
Masar Petroleum plans to rapidly advance appraisal and development opportunities across Block 7.
“Masar is a proud Omani E&P company that has delivered significant value through a continuous and focused effort on unlocking our potential,” Abdulsattar AlMurshidi, CEO of Masar Petroleum, said.
ALSO READ: Oman offers five hydrocarbon exploration blocks in new bidding round
https://image.digitalinsightresearch.in/uploads/NewsArticle/16383075/main2121.jpg -
Bidders get more time for Saudi water transmission projects14 April 2026

Saudi Arabia’s Water Transmission Company (WTCO) has extended the bid submission deadlines for engineering, procurement and construction (EPC) contracts for two major independent water transmission system projects.
The Jubail-Buraidah and Ras Mohaisen-Baha-Mecca transmission projects were first tendered last September under the public-private partnership model.
The deadlines for qualified contractors to submit technical and financial bids had initially been extended to March.
The new bid submission deadline for the Jubail-Buraidah project is 30 April.
Scheduled to begin construction in 2027, the scheme comprises an approximately 348-kilometre-long greenfield water transmission system with a capacity of 840,650 cubic metres a day (cm/d), delivering water from the Ashmasiah reservoirs to cities and towns in Al-Qassim province.
The project is large by WTCO standards. The company’s second phase of the Khobar-Hofuf system, completed in 2024, was 140km in length, with a capacity exceeding 530,000 cm/d.
Ras Mohaisen-Baha-Mecca
For the Ras Mohaisen-Baha-Mecca water transmission system project, the new bid submission deadline is 7 May.
The project involves constructing an approximately 325km-long greenfield independent water transmission system with a capacity of 542,000 cm/d, delivering water from Ras Mohaisen to the Adham and Aradhiyah regions.
Prequalification for both projects closed on 15 January.
It is understood that local firms Alkhorayef Water & Power Technologies and Mutlaq Al-Ghowairi Contracting Company (MGC) are among those qualified to bid for the Ras Mohaisen contract.
MGC secured the EPC contract for an even larger independent water transmission pipeline project in June last year.
The project, also linking Jubail and Buraidah, spans 587km and carries 650,000 cm/d.
According to regional project tracker MEED Projects, construction works recently commenced on the project, which is estimated to cost about SR8.5bn ($2.2bn).
WTCO is also planning to tender a contract for phase two of the Ras Mohaisen water transmission system project. This includes laying water transmission pipelines 408km in length with a capacity of 400,000 cm/d. This project is estimated to cost around $600m.
It is understood that the main contract tender will be issued in 2027.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16383056/main.jpg