Fertiglobe expects Rabdan final investment decision in 2026

26 May 2025

UAE-based fertiliser producer Fertiglobe expects to reach a final investment decision (FID) on its project to establish a new low-carbon hydrogen and ammonia production facility in Abu Dhabi in early 2026.

The planned Rabdan complex will use natural gas provided by Abu Dhabi National Oil Company (Adnoc), Fertiglobe’s parent company and majority shareholder, to produce up to 1 million tonnes a year (t/y) of low-carbon liquid ammonia, also known as blue ammonia.

The Rabdan facility, which will be built in Ruwais, will also have the capacity to produce 192,000 t/y of blue hydrogen and 892,000 t/y of nitrogen, to supply to a local offtaker.

Fertiglobe’s CEO, Ahmed El-Hoshy, said that the front-end engineering and design to engineering, procurement and construction (feed-to-EPC) competition process started later than expected, but that "this process has caught up", allowing for an FID decision in early 2026.

“The ultimate FID decision on Rabdan is dependent on having a competitive capex (capital expenditure) and [operational expenditure] profile and spoken-for offtake agreements. We are also monitoring regulatory developments,” he told MEED.

MEED reported in March that Adnoc was initiating a feed-to-EPC competition to deliver the Rabdan project. The model involves the project operator selecting contractors to execute the feed work and then choosing the contractor with the most competitive feed proposal to execute EPC works on the project, while also compensating the other contestants for their work.

The following contractors are understood to have submitted bids with Adnoc for the feed-to-EPC contest for the Rabdan project by the deadline of 8 March:

  • GS Engineering & Construction (South Korea)
  • Hyundai Engineering & Construction (South Korea)
  • Larsen & Toubro Energy Hydrocarbon (India)
  • Linde (Germany)
  • McDermott (US)
  • Saipem (Italy)
  • Samsung E&A (South Korea)
  • Technip Energies (France)
  • Tecnimont (Italy)

MEED has learnt from industry sources that Larsen & Toubro Energy Hydrocarbon, Linde and Technip Energies are in contention to be shortlisted by Adnoc to participate in the feed-to-EPC competition for the project.

“We haven’t provided a timeline on shortlisting contractors. Our selection will depend on contractors with the best estimates and experience in building similar projects, keeping in mind our attention to efficiency, technology and sustainability,” El-Hoshy said.

“Progress has been made on the offtake side,” he noted. Alongside the firm's Asian partners, the company has applied to the Japanese Contracts for Difference programme, which is currently under evaluation by the Japanese Economy, Trade & Industry Ministry.

He added that this was “similar to other projects globally also evaluating other support programmes”.

El-Hoshy further said: “Although we benefit from advantaged infrastructure with the Adnoc ecosystem, strong and improving cost structure and strategic locations, we want to further de-risk our growth projects by ensuring offtake agreements.”

Project Rabdan

The planned Rabdan facility is part of an expansion phase of the Taziz Industrial Chemicals Zone in Ruwais Industrial City.

In addition to the main blue ammonia production plant, the planned complex will also feature units for hydrogen production and synthesis gas purification, as well as pipelines for the transport of feedstock gas, hydrogen and nitrogen.

The Rabdan facility will have its own storage, exportutilities and offsite units, and will also tap into those from the wider Taziz ecosystem.

A carbon capture and storage (CCS) system within the Rabdan complex will capture, compress and transport carbon dioxide emissions from its operations to a larger Adnoc CCS hub in Ruwais.

Blue hydrogen and ammonia goals

Abu Dhabi is set to become a major producer of blue hydrogen and blue ammonia when the first phase of the complex in the Taziz Industrial Chemicals Zone, which is currently under construction, enters operations in 2027.

The complex, known as Project Harvest, will be located within the first phase of the Taziz Industrial Chemicals Zone, which is being developed by Abu Dhabi Chemicals Derivatives Company RSC (Taziz) – in which Adnoc and industrial holding company ADQ are 60:40 shareholders.

A joint venture of Fertiglobe, South Korea’s GS Energy Corporation and Japanese investment firm Mitsui & Company is the main stakeholder in Project Harvest, which will have an output capacity of 1 million t/y.

The joint venture awarded Tecnimont the main contract, worth $500m, for EPC works on the blue ammonia production project in May 2024. El-Hoshy said Fertiglobe and its partners expect to start operations at the Project Harvest complex in 2027.

“Project Harvest benefits from one of the most competitive capex structures globally, especially as we look at the other geographies that have structurally higher costs, including non-feedstock related costs. Our benefit stems from the Adnoc ecosystem leveraging common utility, site and logistical infrastructure in Taziz,” El-Hoshy told MEED.

Project Rabdan is understood to be the expansion phase of the Taziz blue hydrogen and ammonia complex. Upon commissioning, which is most likely to take place before the end of this decade, Fertiglobe – as the main nitrogen-based ammonia business of Adnoc Group – will become the operator of the Rabdan facility.

The two projects in Abu Dhabi could add 2 million t/y of output potential, more than doubling Fertiglobe’s current commercial ammonia capacity of 1.6 million t/y and increasing its total sellable capacity to 8.6 million t/y of net ammonia and urea combined, in addition to other announced global projects.

Fertiglobe financial performance

Adnoc became the majority shareholder in Fertiglobe after completing a transaction in October wherein it increased its shareholding in the company from 36.2% to 86.2%. The remaining 13.8% of Fertiglobe’s shares trade on the Abu Dhabi Securities Exchange, following the company’s stock listing in October 2022.

In the first quarter of this year, Fertiglobe announced revenues of $695m, representing a year-on-year growth of 26%. The company recorded adjusted profit attributable to shareholders of $73m, and adjusted earnings before interest, taxes, depreciation and amortisation (Ebitda) of $261m.

Fertiglobe attributed its positive first-quarter financial results to higher sales volumes, supported by operational improvements and strategic shipment deferrals from the last quarter of 2024, and higher urea prices.

Adjusted for turnarounds, asset utilisation and energy efficiency reached record highs across most plants in Q1 2025, driven by the ongoing phase one of the manufacturing improvement plan, which is now 80% complete.

As part of its 2030 growth strategy, Fertiglobe aims to become a $1bn-plus Ebitda “global integrated downstream product champion, well placed for the energy transition”. This encompasses four goals: achieving operational excellence of $165m-$175m, customer proximity of $30m-$45m, nitrogen product expansion of $75m-$100m and disciplined low-carbon ammonia growth of $70m-$100m.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13948557/main5604.jpg
Indrajit Sen
Related Articles
  • Oman secures over $500m from award of three mining blocks

    13 August 2025

    Oman’s Energy & Minerals Ministry has awarded exploration rights for three mining concessions in the sultanate to two local firms, securing investments worth more than $500m in the process.

     has awarded exploration and mining rights for concession area 11C to Gulf Minerals & Materials Company. Covering 1,089 square kilometres (sq km) in Buraimi Governorate, the block contain ophiolite rocks and is said to hold deposits of copper and chromium ore.

    Gulf Minerals & Materials Company will invest $4m in the initial two- to three-year phase of topographic, geochemical and geophysical surveys, in addition to drilling and exploratory trenching.

    Novel Muscat International has won exploration and mining rights for concession areas 51-G1 and 51-G2 in Al-Wusta Governorate and will invest about $500m in developing minerals from the blocks.

    In area 51-G1, which covers 558 sq km, the company will build a hydrated lime factory. Exploratory studies will assess the locations, quality and reserves of raw materials, focusing on silica, limestone and clay deposits.

    Novel Muscat will also build a factory in area 51-G2, which covers 30 sq km, to produce salts and sodium carbonate (soda ash) using seawater evaporated in basins.


    READ THE AUGUST 2025 MEED BUSINESS REVIEW – click here to view PDF

    Gulf heads into a new era of aviation; Maghreb’s resilience rises despite global pressures; GCC banks expand issuance amid demand

    Distributed to senior decision-makers in the region and around the world, the August 2025 edition of MEED Business Review includes:

    > MAGHREB MARKET FOCUS: Maghreb pushes for stability
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14461349/main03522714.jpeg
    Indrajit Sen
  • Oman unveils new incentives for hydrogen projects

    13 August 2025

    Oman’s Hydrom has unveiled new fiscal incentives aimed at enhancing the commercial viability of projects in its third green hydrogen auction round.

    The measures include a 90% reduction in land lease fees during the development stage, with the potential for further relief during the front-end engineering and design phase.

    Base royalties will also be significantly reduced during the initial years of production, while corporate tax exemptions will be available for up to 10 years.

    Hydrom, a subsidiary of Energy Development Oman, said the incentives are designed to support early-stage project economics.

    This includes accelerating progress towards final investment decisions.

    “The global hydrogen landscape is entering a phase of consolidation, with developers prioritising jurisdictions that provide regulatory certainty, strong project economics and credible offtake potential,” said Abdulaziz Al-Shidhani, managing director of Hydrom.

    The third auction round offers a land block of up to 300 square kilometres (sq km) in Duqm, with proposals invited for projects covering a minimum of 100 sq km.

    Bidders have the flexibility to define their own project footprint within the block, enabling tailored configurations that align with development strategies and market requirements.

    Hydrom has received almost 100 registrations from major industry players and consortiums across the green hydrogen value chain, highlighting sustained interest in Oman’s structured, policy-backed hydrogen market.

    The statement of qualification submission window will remain open until 31 October 2025.

    To support the formation of strong consortiums, Hydrom will also launch an updated consortium matchmaking list, a tool designed to connect qualified participants seeking strategic project partnerships.


    READ THE AUGUST 2025 MEED BUSINESS REVIEW – click here to view PDF

    Gulf heads into a new era of aviation; Maghreb’s resilience rises despite global pressures; GCC banks expand issuance amid demand

    Distributed to senior decision-makers in the region and around the world, the August 2025 edition of MEED Business Review includes:

    > MAGHREB MARKET FOCUS: Maghreb pushes for stability
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14461086/main3747.jpg
    MEED Editorial
  • Aldar launches Fahid Beach Terraces project

    13 August 2025

    Abu Dhabi-based private real estate developer Aldar Properties has launched the Fahid Beach Terraces project, located on Fahid Island, which is a new waterfront development located between Yas Island and Saadiyat Island

    The project is designed by Japanese architect Koichi Takada, with interiors from UK-based firm M&L.

    The six-building community will offer 501 one- to four-bedroom apartments, duplexes and six five-bedroom penthouses.

    The announcement follows Aldar's unveiling of the masterplan for Fahid Island in June. The island spans a total area of over 2.7 million square metres (sq m) with 11 kilometres (km) of coastline and 4.6km of beachfront.

    Aldar said that it has enrolled several architects to design the island’s residential assets, including Japan's Kengo Kuma and Koichi Takada. Other residential developments have been designed by London-headquartered Acme and UAE-based Naga Architects.

    The island will offer more than 6,000 apartments, townhouses and villas.

    In April last year, MEED reported that Aldar Properties planned to launch a project on Fahid Island.

    In February 2024, Aldar made a AED2.5bn ($680m) investment, to be paid over five years, for a 4 million sq m land bank on Fahid Island to build a waterfront development.

    In addition to residential units, the project will include a school, as well as retail and leisure facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14459970/main.jpg
    Yasir Iqbal
  • Contract award nears for Trump Tower Jeddah

    13 August 2025

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia-headquartered real estate developer Dar Global is preparing to award the main construction contract to build the Trump Tower development in Jeddah.

    "The bid evaluation process has reached the final stages, and the contract could be finalised in a few weeks," sources close to the project told MEED.

    The enabling works have already started and are being undertaken by local firm Specialised Italian Foundation Company.

    The 47-floor tower is expected to be developed at an estimated cost of SR2bn ($532m).

    Dar Global is developing the project in collaboration with the US-based Trump Organisation.

    The project is the latest addition to Dar Global's portfolio after it announced the development of two new projects in Riyadh with the Trump Organisation.

    The announcement follows a partnership deal signed by Dar Global in September last year with Geneva-based jeweller Mouawad to develop a residential project in Riyadh.

    The estimated SR880m ($234m) development will offer 200 residential villas north of Riyadh, close to the Expo 2030 site.

    The development is expected to be completed by 2026.

    According to an official statement, Dar Global has $7.5bn-worth of projects under development in six countries: the UAE, Oman, Qatar, the UK, Spain and Saudi Arabia.

    UK analytics firm GlobalData expects the kingdom's construction industry to record an annual average growth rate of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure projects and the Saudi gigaprojects programme.

    The industry will also be supported by the government’s aim of increasing homeownership from 62% in 2020 to 70% by 2030, as part of Saudi Vision 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14459905/main.jpeg
    Yasir Iqbal
  • Drake & Scull announces $381m in new contract awards

    13 August 2025

    Dubai-based contractor Drake & Scull International (DSI) has announced that it has secured three new contracts worth over AED1.4bn ($381m) in the UAE, Jordan and India.

    The first contract, worth over AED1bn ($272m), covers the infrastructure works for the Arabian Hills project in Dubai.

    The second contract, which is worth AED215m ($58m), includes the construction of the North Balqa wastewater treatment plant in Jordan.

    The third contract, valued at AED169m ($46m), covers the construction of a water treatment facility in Maharashtra, India.

    The firm has also announced its entry into Dubai’s commercial real estate sector with the purchase of a land parcel in the Majan area of the city, where it plans to develop an office building.

    DSI has also announced that in the first half of 2025, its revenues increased to AED78m. The firm posted a gross profit of about AED6m, while net profit stood at AED6.5m.

    In June last year, DSI announced that it had completed its financial restructuring plan after it was able to reach settlements with “a number of creditors”.

    "Settlements have been reached with creditors and the financial restructuring plan has been approved by the competent courts," said Shafiq Abdul Hamid, chairman of the board of directors of DSI.

    "The company has been successful in increasing its new capital by more than AED450m ($123m) and obtaining approval from the Securities & Commodities Authority," he added.

    Hamid said the move was expected to enable the company to resume its activities by bidding for new projects.

    According to the new operational plan, the company will be focusing on three core disciplines: mechanical, electrical and plumbing; oil and gas; and wastewater treatment.

    In November 2023, DSI's restructuring plan was approved by the Courts of Dubai.

    The company resumed trading on the Dubai Financial Market in May, following a suspension of more than five years for restructuring.

    DSI's restructuring advisory team includes Trussbridge, Allen & Overy, Hadef & Partners, Ibrahim & Partners, Aaronite, Linklaters and Deloitte.

    UK analytics firm GlobalData expects the UAE construction industry to register annual growth of 3.9% in 2025-27, supported by investments in infrastructure, renewable energy, oil and gas, housing, industrial and tourism projects.

    The residential construction sector is expected to expand by 2.7% in 2025-28, supported by private investment in the residential housing sector, along with government initiatives to meet rising housing demand.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14459688/main.jpg
    Yasir Iqbal