Aramco’s recalibrated chemicals goals reflect realism
26 March 2025

Saudi Aramco told consultants and contractors last year that it was revisiting its investment strategy and execution approach for its liquids-to-chemicals programme.
The central ambition of the strategic programme is to derive greater economic value from every barrel of crude produced in Saudi Arabia by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.
Aramco and its subsidiary, Saudi Basic Industries Corporation (Sabic), had been tasked with establishing 10-11 large mixed-feed crackers by 2030. These petrochemicals crackers, which included greenfield developments and expansions of existing facilities, were to be built both in Saudi Arabia and in overseas markets.
Achieving this ambition required Aramco and Sabic – the main stakeholders in the liquids-to-chemicals programme – to invest a sum of up to $100bn. Amid considerable cost pressures and significant overcapacity in the global chemicals sector, pushing forward with such a capital-intensive campaign was hard to justify.
However, while Aramco may have streamlined the programme’s remit, the primary goal of attaining a liquids-to-chemicals conversion rate of 4 million b/d within its global portfolio remains unchanged.
In a presentation detailing Aramco’s financial performance and operational activities in 2024, president and CEO Amin Nasser stated that the company had achieved 45% of the target of the liquids-to-chemicals programme as of the end of last year. Also, 53% of Aramco’s crude oil production is utilised by the downstream sector.
This has been achieved through “greater capital efficiency with low-equity and a high-placement strategy”, Nasser said in the presentation.
Moreover, large-scale petrochemicals projects undertaken by Aramco’s joint ventures with foreign partners in South Korea and Saudi Arabia, namely the Shaheen and Amiral developments, respectively, will significantly contribute to the liquids-to-chemicals target when they come online in 2026 and 2027.
Key chemical projects advance
Aramco continues to make progress with projects deemed crucial to its long-term petrochemicals objectives. One such project is the expansion of Aramco affiliate, Saudi Aramco Jubail Refinery Company (Sasref), into the petrochemicals sector.
Aramco has brought China-based Rongsheng Petrochemical Company on board as a joint-venture partner for the proposed project, which is part of the liquids-to-chemicals programme.
Their aim is to convert the Sasref refining complex in Jubail into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. The project also involves building an ethane cracker that will draw feedstock from the Sasref refinery.
The project is in the pre-front-end engineering and design (pre-feed) stage, with Aramco previously saying that the construction of large-scale steam crackers and the integration of associated downstream derivatives into the existing Sasref complex would enhance “its ability to meet growing demand for high-quality petrochemical products”.
Meanwhile, Sabic is in the bid evaluation stage with a major project that involves building an integrated blue ammonia and urea manufacturing complex at the existing facility of its affiliate, Sabic Agri-Nutrients Company, in Jubail.
The estimated $3bn project, called the low-carbon hydrogen San 6 complex, is part of Sabic’s Horizon-I low-carbon hydrogen (LCH) programme. Contractors submitted bids for the project in March last year.
The San 6 complex will have an output capacity of 3,500 metric tonnes a day, or 1.17 million tonnes a year (t/y), of blue ammonia, and a urea production capacity of 3,850 metric tonnes a day, or 1.28 million t/y.
Carbon dioxide (CO2) from the blue ammonia plant will be utilised for urea production, with surplus CO2 from the ammonia plant and post-combustion carbon capture unit to be exported via a third-party pipeline for subsequent sequestration.

Gas transportation and processing projects
Saudi Arabia was the biggest regional spender on midstream and downstream projects last year. To address incremental volumes of gas entering the grid as Aramco increases its conventional and unconventional gas production, the state enterprise spent more than $17bn on gas processing and transportation projects in 2024.
In April last year, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.
In June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn.
Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.
The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028, with the installation of about 4,000 kilometres of pipelines and 17 new gas compression trains.
So far this year, the Saudi energy giant has selected the main contractor for a major project to develop a large-scale carbon capture and storage (CCS) hub in Jubail Industrial City.
India’s Larsen & Toubro Energy Hydrocarbon has been picked to perform EPC work on the first phase of the project, which is called the Accelerated Carbon Capture and Sequestration (ACCS) scheme, worth $1.5bn.
The aim of the ACCS scheme, which is expected to have nine phases in total, is to capture CO2 from Aramco’s northern gas plants at Wasit, Fadhili and Khursaniyah, as well as from the operations of Sabic and Saudi industrial gases provider Air Products Qudra.
The first phase of the ACCS project will have the capacity to store and sequester up to 9 million t/y of CO2 in the planned CCS hub in Jubail. The main facility that will be built in Jubail will capture streams from the acid gas enrichment units of the Wasit, Fadhili and Khursaniyah plants. The CO2 will be compressed, dried and fed into the collection pipeline system.
MEED’s April 2025 report on Saudi Arabia also includes:
> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING: Saudi banks work to keep pace with credit expansion
Exclusive from Meed
-
Dubai extends bid deadlines for key drainage projects31 October 2025
-
Gas demand reshapes priorities31 October 2025
-
Dubai evaluates Al-Maktoum airport substructure bids31 October 2025
-
Financial close reached for Jubail-Buraydah link31 October 2025
-
Libya oil project expected to progress despite Petrofac collapse31 October 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai extends bid deadlines for key drainage projects31 October 2025
Dubai Municipality has extended the bid submission deadlines for two key drainage projects under the $8bn Tasreef programme to develop, rehabilitate and expand Dubai’s stormwater drainage network.
The first project, listed as TF-05-C1, involves a stormwater drainage system in Jebel Ali and the surrounding areas.
The new deadline is 10 November, a source close to the project told MEED.
The project covers approximately 27 kilometres of stormwater network and will serve major transport routes, including Sheikh Zayed Road and Al-Jamayel Road.
The bid submission date for the tender, was initially 2 October before being extended to 30 October.
The second project, listed under TF-11-C1, is for the development of a stormwater pond, evacuation line and pumping station.
The project includes a comprehensive stormwater drainage system, featuring a tunnel ranging from three to four metres in diameter along Dubai–Al Ain Road and the D54.
The new deadline is 4 November.
The bid submission date for the tender, was initially 25 September.
The schemes are being procured by the municipality’s Sewerage and Recycled Water Projects Department as part of the Tasreef programme.
In October, Dubai Municipality awarded contracts for two other major projects under the initiative.
Local firm DeTech Contracting won the main contract for the construction of a stormwater drainage system on Sheikh Mohammed Bin Zayed Road and Al-Yalayis Road in Dubai.
The municipality alos awarded a contract to Greece/Lebanon-based Archirodon for the construction of the Resilient Future Flow Outfall project.
The $25m project involves the construction of a 4-kilometre subsea pipeline with a 2-metre diameter and a discharge capacity of 9 cubic metres a second.
The Tasreef masterplan that will serve key areas across the emirate, including Nad Al-Hamar, the vicinity of Dubai International airport, Garhoud, Rashidiya, Al-Quoz, Zabeel, Al-Wasl, Jumeirah and Al-Badaa. The initiative aims to expand Dubai’s rainwater drainage capacity by 700% by 2033.
DeTech Consulting previously won the $136m contract to upgrade the West Deira stormwater system.
This project was the first of the five planned Tasreef projects to enter construction, earlier this year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14993856/main.jpg -
Gas demand reshapes priorities31 October 2025
Commentary
Colin Foreman
EditorRead the November issue of MEED Business Review
Gas has increasingly been regarded as a crucial transition fuel over the past decade as governments race to cut carbon emissions and meet climate pledges – including the Paris Agreement’s aim to keep warming well below 2°C and pursue efforts to limit it to 1.5°C.
Those commitments have driven the demand for liquefied natural gas (LNG) globally and this has reshaped investment priorities across the region, with Qatar, Oman and the UAE eyeing future export growth.QatarEnergy’s North Field expansion is the largest investment. The estimated $40bn programme will push Qatar’s LNG output towards 142 million tonnes a year by the end of this decade, almost doubling its present position and consolidating its role as a market anchor.
Abu Dhabi is also committed to expanding its capacity. Its downstream strategies include a major greenfield LNG terminal at Ruwais, due to enter service in 2028 with two 4.8 million t/y trains adding 9.6 million t/y to the UAE’s export capability.
These programmes are keeping contractors busy. Over the past five years, more than $44bn of LNG-related contracts have been awarded in the region – which is more than eight times the $5.3bn recorded in the previous five year period.
At the same time, there are ample opportunities for contractors as other countries in the region build import infrastructure. Projects are already under way in Kuwait, Iraq, Jordan, Egypt, Algeria and Morocco – and more are expected.
With base load concerns remaining for many countries when it comes to completely switching to renewables, gas is expected to be a fuel of choice for the decades to come. The investments made in production capacity mean the region will play a pivotal role in delivering the world’s energy needs.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14992876/main.gif -
Dubai evaluates Al-Maktoum airport substructure bids31 October 2025

Dubai Aviation Engineering Projects (DAEP) is evaluating the bids it received from contractors on 15 September for substructure works for the first phase of the expansion of Al-Maktoum International airport.
“The bid evaluation is ongoing and the project is expected to be awarded by the end of this year,” sources close to the project told MEED.
MEED understands that the bidders include:
- Alec (local)
- China Civil Engineering Construction Corporation (China)
- China State Construction Engineering Corporation (China)
- China Harbour Engineering Company (China)
- Dutco Construction (local)
- Innovo (local)
- Limak / PowerChina (Turkiye/China)
- Shapoorji Pallonji (India)
- Webuild / Tristar (Italy/local)
According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.
It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.
In August, MEED exclusively reported that DAEP had received bids from firms to build the APM at Al-Maktoum airport.
The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
Construction progress
Construction on the first phase has already begun. In May, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.
While speaking to the press on the sidelines of the Airport Show in Dubai in May, Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation, said the government of Dubai will award more packages this year, including for the APM and baggage handling systems.
“Several other packages are expected to be tendered this year, including the terminal substructure, 132kV substations and district cooling plants,” Al-Zaffin said.
Construction works on the project’s first phase are expected to be completed by 2032.
The government approved the updated designs and timelines for its largest construction project in April 2024.
In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
The statement added that the project will create housing demand for 1 million people around the airport.
In September last year, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.
Project history
The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.
An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.
Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14991651/main.jpg -
Financial close reached for Jubail-Buraydah link31 October 2025
Register for MEED’s 14-day trial access
Saudi Water Partnership Company (SWPC) has announced financial close for the Jubail-Buraydah independent water transmission pipeline (IWTP) project.
Saudi Arabia’s second IWTP project will link Jubail in the kingdom’s Eastern Province and Buraydah in the Qassim region via a 587-kilometre (km) pipeline that can transmit 650,000 cubic metres a day (cm/d) of water.
It will have a potable water storage capacity of 1.63 million cubic metres.
The project will have a total cost of SR8.5bn ($2.2bn).
A developer team comprising local companies Aljomaih Energy & Water, Nesma Company and Buhur for Investment Company was named as the preferred bidder for the contract last year.
The Aljomaih, Nesma and Buhur team had proposed to develop the project for SR3.59468 a cubic metre.
SWPC signed a contract agreement to develop and operate the Jubail-Buraydah IWTP project in May.
The project is being developed under a build-own-operate-transfer model with a 35-year concession period from the project’s commercial operation date.
Local content is expected to reach 45% during the construction phase and 70% during operations.
Commercial operation is scheduled for the first quarter of 2029.
READ THE NOVEMBER 2025 MEED BUSINESS REVIEW – click here to view PDFMena players up the ante in global LNG production race; Investment takes UAE non-oil economy from strength to strength; Project finance activity draws international lenders back to market
Distributed to senior decision-makers in the region and around the world, the November 2025 edition of MEED Business Review includes:
> AGENDA 1: Gulf LNG sector enters a new prolific phase> INDUSTRY REPORT 1: Region sees evolving project finance demand> INDUSTRY REPORT 2: Iraq leads non-GCC project finance activity> GREEN STEEL: Abu Dhabi takes the lead in green steel transition> DIGITISATION: Riyadh-based organisation drives digital growth> UAE MARKET FOCUS: Investment shapes UAE growth storyTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/14991282/main.jpg -
Libya oil project expected to progress despite Petrofac collapse31 October 2025

Register for MEED’s 14-day trial access
The tender process for Libya’s 6J North Gialo oil field development project is expected to progress following Petrofac’s announcement that it has gone into administration, according to industry sources.
UK-based Petrofac is one of just two companies that submitted bids for the project. The other is Egypt-based Petrojet.
In September, MEED revealed that the bids had been submitted for the project and were under evaluation.
The client on the project is Libya’s Waha Oil Company and Petrofac completed the front-end engineering and design (feed) for the project in 2020.
Waha is a joint venture of Libya’s National Oil Corporation (NOC), France’s TotalEnergies and US-based ConocoPhillips.
Commenting on the impact of Petrofac’s insolvency, one industry source said: “This has definitely increased uncertainty for the project.
“It could potentially mean that this contract is retendered, but there is a lot of confidence that this tender will still go ahead in some form.
“Waha Oil and Libya’s NOC have made it clear that this project is a priority and they want it to go ahead.
“Progress is still expected on this tender, but it is possible that there will be more delays before this contract is awarded and signed.”
The 6J North Gialo field development project is part of a series of tenders that are collectively expected to be worth $1bn.
The three projects are:
- NC98
- Gialo 3
- 6J North Gialo
All three projects will develop Libyan reservoirs that have not yet been tapped.
The 6J North Gialo project was the first to be tendered and it is expected to be followed by NC98, with the Gialo 3 project likely to be tendered last.
Together, the projects are expected to double Waha’s production from about 300,000 barrels a day (b/d) of oil to 600,000 b/d. The Waha concession covers 13 million acres.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14990491/main.png