Aramco’s recalibrated chemicals goals reflect realism

26 March 2025

 

Saudi Aramco told consultants and contractors last year that it was revisiting its investment strategy and execution approach for its liquids-to-chemicals programme.

The central ambition of the strategic programme is to derive greater economic value from every barrel of crude produced in Saudi Arabia by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.

Aramco and its subsidiary, Saudi Basic Industries Corporation (Sabic), had been tasked with establishing 10-11 large mixed-feed crackers by 2030. These petrochemicals crackers, which included greenfield developments and expansions of existing facilities, were to be built both in Saudi Arabia and in overseas markets.

Achieving this ambition required Aramco and Sabic – the main stakeholders in the liquids-to-chemicals programme – to invest a sum of up to $100bn. Amid considerable cost pressures and significant overcapacity in the global chemicals sector, pushing forward with such a capital-intensive campaign was hard to justify. 

However, while Aramco may have streamlined the programme’s remit, the primary goal of attaining a liquids-to-chemicals conversion rate of 4 million b/d within its global portfolio remains unchanged.

In a presentation detailing Aramco’s financial performance and operational activities in 2024, president and CEO Amin Nasser stated that the company had achieved 45% of the target of the liquids-to-chemicals programme as of the end of last year. Also, 53% of Aramco’s crude oil production is utilised by the downstream sector.

This has been achieved through “greater capital efficiency with low-equity and a high-placement strategy”, Nasser said in the presentation.

Moreover, large-scale petrochemicals projects undertaken by Aramco’s joint ventures with foreign partners in South Korea and Saudi Arabia, namely the Shaheen and Amiral developments, respectively, will significantly contribute to the liquids-to-chemicals target when they come online in 2026 and 2027.

Key chemical projects advance

Aramco continues to make progress with projects deemed crucial to its long-term petrochemicals objectives. One such project is the expansion of Aramco affiliate, Saudi Aramco Jubail Refinery Company (Sasref), into the petrochemicals sector.

Aramco has brought China-based Rongsheng Petrochemical Company on board as a joint-venture partner for the proposed project, which is part of the liquids-to-chemicals programme.

Their aim is to convert the Sasref refining complex in Jubail into an integrated refinery and petrochemicals complex by adding a mixed-feed cracker. The project also involves building an ethane cracker that will draw feedstock from the Sasref refinery.

The project is in the pre-front-end engineering and design (pre-feed) stage, with Aramco previously saying that the construction of large-scale steam crackers and the integration of associated downstream derivatives into the existing Sasref complex would enhance “its ability to meet growing demand for high-quality petrochemical products”.

Meanwhile, Sabic is in the bid evaluation stage with a major project that involves building an integrated blue ammonia and urea manufacturing complex at the existing facility of its affiliate, Sabic Agri-Nutrients Company, in Jubail. 

The estimated $3bn project, called the low-carbon hydrogen San 6 complex, is part of Sabic’s Horizon-I low-carbon hydrogen (LCH) programme. Contractors submitted bids for the project in March last year.

The San 6 complex will have an output capacity of 3,500 metric tonnes a day, or 1.17 million tonnes a year (t/y), of blue ammonia, and a urea production capacity of 3,850 metric tonnes a day, or 1.28 million t/y.

Carbon dioxide (CO2) from the blue ammonia plant will be utilised for urea production, with surplus CO2 from the ammonia plant and post-combustion carbon capture unit to be exported via a third-party pipeline for subsequent sequestration.

Gas transportation and processing projects

Saudi Arabia was the biggest regional spender on midstream and downstream projects last year. To address incremental volumes of gas entering the grid as Aramco increases its conventional and unconventional gas production, the state enterprise spent more than $17bn on gas processing and transportation projects in 2024.

In April last year, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.

In June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn. 

Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.

The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028, with the installation of about 4,000 kilometres of pipelines and 17 new gas compression trains.

So far this year, the Saudi energy giant has selected the main contractor for a major project to develop a large-scale carbon capture and storage (CCS) hub in Jubail Industrial City.

India’s Larsen & Toubro Energy Hydrocarbon has been picked to perform EPC work on the first phase of the project, which is called the Accelerated Carbon Capture and Sequestration (ACCS) scheme, worth $1.5bn.

The aim of the ACCS scheme, which is expected to have nine phases in total, is to capture CO2 from Aramco’s northern gas plants at Wasit, Fadhili and Khursaniyah, as well as from the operations of Sabic and Saudi industrial gases provider Air Products Qudra.

The first phase of the ACCS project will have the capacity to store and sequester up to 9 million t/y of CO2 in the planned CCS hub in Jubail. The main facility that will be built in Jubail will capture streams from the acid gas enrichment units of the Wasit, Fadhili and Khursaniyah plants. The CO2 will be compressed, dried and fed into the collection pipeline system.


MEED’s April 2025 report on Saudi Arabia also includes:

> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING:
 Saudi banks work to keep pace with credit expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/13477916/main.gif
Indrajit Sen
Related Articles
  • Adnoc-Covestro deal decision due in May

    2 April 2025

    EU antitrust regulators are expected to decide by 12 May whether to clear or extend the review of Abu Dhabi National Oil Company's (Adnoc) €15.9bn ($17.1bn) takeover of German chemicals producer Covestro.

    The 27-country EU competition enforcer can either clear the deal with or without conditions, or open a four-month investigation after its preliminary review, a Reuters report said, citing a filing on the European Commission's website.

    It was reported in October last year that Adnoc International, the overseas business arm of Adnoc Group, had signed an investment agreement Covestro in which it made a takeover offer of €14.7bn.

    Adnoc International said at the time that it will launch a voluntary public takeover of €62 ($69) a share, which implies an equity value for Covestro of about €11.7bn and represents a premium of about 54% to Covestro’s closing price on 19 June, the day before the first media coverage regarding a potential transaction.

    Leverkusen-headquartered Covestro’s supervisory and management boards supported the takeover offer.

    In addition, Adnoc International will subscribe to a 10% non-preemptive capital increase of €1.17bn in Covestro at the closing of the transaction.

    The offer will be subject to a minimum acceptance level of 50% plus one share and customary closing conditions, including merger control, foreign investment control and EU foreign subsidies clearances, the companies said.

    The agreement between Adnoc International and Covestro, which runs until the end of 2028, contains several obligations on the part of the Abu Dhabi energy producer, including maintaining Covestro’s existing business activities, corporate governance and organisational business structure.

    Adnoc approached Covestro about a potential takeover in September 2023, but initial advances were rejected, leading the Abu Dhabi state enterprise to raise the value of its offer.

    Adnoc’s initial approaches included a takeover price of €55 and then €57 a share, Bloomberg News reported at the time.

    Covestro’s expertise lies in chemicals recycling, which is key for the future of the energy industry and a target area for Adnoc.

    Russia's invasion of Ukraine in 2022 slashed deliveries of natural gas to Germany, resulting in a crisis that gripped the German chemicals industry, which accounts for about 5% of the country’s GDP.

    Precedent

    In September, the European Commission approved the takeover of the telecommunications assets of Czech investment group PPF by UAE telecoms group e&.

    Sovereign wealth fund Emirates Investment Authority holds a 60% stake in e&. The commission's review concluded that the “subsidies received by e& did not lead to actual or potential negative effects on competition in the acquisition process”.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13602719/main.jpg
    Jennifer Aguinaldo
  • Edgnex acquires Nordic data centre developer

    2 April 2025

    Register for MEED’s 14-day trial access 

    Edgnex, a subsidiary of Dubai-based property developer Damac, has acquired Helsinki-headquartered data centre-focused real estate developer Hyperco as part of its European expansion strategy.

    Damac announced the acquisition on 31 March.

    Hyperco operates data centres in Finland and Sweden, "leveraging the region’s renewable energy sources, mature digital ecosystem and high connectivity", local media reports said.

    Hyperco's three co-founders and existing team will continue to lead operations through the next phase of growth, according to a statement by the company.

    Hussain Sajwani, founder of Damac Group, said his firm plans to "build a significant future capacity in the Nordics and establish a strong foothold in the market".

    Edgnex’s recent European activities include a €150m ($161.9m) joint venture in Greece with Public Power Corporation to develop a 12.5MW facility, expandable to 25MW, and a €400m commitment to build a 40MW data centre in Madrid, Spain.

    In January, Sajwani pledged $20bn to develop data centres in the US.

    Sajwani and then US President-Elect Donald Trump announced the plan on 7 January in Florida, a day after the US Congress certified Trump as the winner of the 2024 presidential election.

    The project’s initial phase covers establishing data centres in Texas, Arizona, Oklahoma, Louisiana, Ohio, Illinois, Michigan and Indiana.

    It was previously reported that the Dubai-based property developer plans to develop $1bn-worth of data centres in countries in Europe, Asia, Africa, the Middle East and the Commonwealth of Independent States.

    Edgnex is constructing two data centre facilities in Dammam and Riyadh in Saudi Arabia that will deliver 55MW in 2025. There are also plans for a data centre in Amman, Jordan, and another in Turkiye in partnership with Vodafone.

    In May, Damac announced its entry into the Indonesian market with plans to build a 15MW data centre in Jakarta. The first construction phase for the facility is scheduled to be completed in the fourth quarter of 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13602668/main1456.jpg
    Jennifer Aguinaldo
  • Developers prepare Saudi round six solar IPP bids

    2 April 2025

     

    Register for MEED’s 14-day trial access 

    Prequalified developers are forming teams to bid for the contracts to develop solar farms under the sixth round of Saudi Arabia's National Renewable Energy Programme (NREP).

    MEED understands that bids are due for the four solar photovoltaic (PV) independent power projects (IPPs) by 1 June.

    The four solar IPPs have a combined capacity of 3,000MW.

    A 1,400MW solar PV IPP will be located in Najran, while the smallest – the 400MW Al-Sufun solar IPP – will be in Hail.

    The 600MW Samtah and 600MW Al-Darb solar IPPs will be located in Jizan, a region that has been placed under security-related travel alerts by some countries and international firms.

    Most of the prequalified bidders participated in site visits, which Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), conducted in late January.

    SPPC prequalified 16 companies that can bid as managing and technical members for the solar PV contracts. These are:

    • Abu Dhabi Future Energy Company (Masdar, UAE) 
    • Alfanar Company (local)
    • EDF Renewables (France)
    • Kahrabel (Engie, France)
    • FAS Energy (local)
    • Jinko Power (Hong Kong)
    • Korea Electric Power Corporation (Kepco, South Korea)
    • Marubeni Corporation (Japan)
    • Nesma Renewable Energy (local)
    • SPIC Hunaghe Hydropower Development (China)
    • Sumitomo Corporation (Japan)
    • TotalEnergies Renewables (France)
    • AlJomaih Energy & Water (local)
    • Sembcorp Utilities (Singapore)
    • AlGihaz Holding Company (local)
    • Korea Western Power Company (Kowepo, South Korea)

    The following five companies have been prequalified to bid as managing partners:

    • Jera Nex (Japan)
    • Power Construction Corporation of China (PowerChina)
    • China Power Engineering Consulting Group International Engineering (China)
    • Posco International (South Korea)
    • Saudi Electricity Company (SEC, local)

    Round six of the NREP will have a total combined capacity of 4,500MW, including the 1,500MW Dawadmi wind farm, for which a separate set of bidders has been prequalified.

    SPPC issued the prequalification request for round six of the NREP in September last year and received statements of qualifications from interested developers and developer consortiums the following month.

    SPPC is responsible for the pre-development, tendering and subsequent offtaking of the energy from the projects.

    US/India-based Synergy Consulting is the client's financial adviser for the NREP sixth-round tender. Germany’s Fichtner Consulting and US-headquartered CMS are the technical and legal consultants, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13602412/main0154.jpg
    Jennifer Aguinaldo
  • Mitsubishi Power confirms Rumah 1 and Nairiyah 1 deal

    2 April 2025

    Register for MEED’s 14-day trial access 

    Mitsubishi Power, part of Japan’s Mitsubishi Heavy Industries, has confirmed it has received two orders to supply six M501JAC gas turbines for the Rumah 1 and Al-Nairiyah 1 power generation projects in Saudi Arabia.

    Rumah 1 is located in the Central Region in Riyadh and is part of the previously planned Riyadh Power Plant 15. Nairiyah 1 is located in the Eastern Region.

    The scope includes the supply of generators and auxiliary equipment, Mitsubishi Power said in a statement.

    MEED exclusively reported that the Japanese original equipment manufacturer had been selected to supply its gas turbines for the independent power project (IPP) in November last year.

    A consortium comprising the local Saudi Electricity Company (SEC) and Acwa Power and South Korea’s Korea Electric Power Corporation (Kepco) won the contract to develop the Rumah 1 and Al-Nairiyah 1 IPP the same month.

    The power plants will deliver a combined 3.6GW, accounting for nearly 2.5% of the national grid’s capacity.

    The M501JAC turbines will be assembled at Mitsubishi Power Saudi Arabia’s Dammam factory.

    The 17,730 square-metre facility also provides services for gas turbine components.

    According to Mitsubishi Power, the plant features "a majority of Saudi employees, in line with the firm’s Saudi National programme".

    China’s Sepco 3 and South Korea's Doosan Enerbility will undertake the engineering, procurement and construction (EPC) contract for the projects, as MEED reported.

    The SEC, Acwa Power and Kepco team offered a levelised electricity cost (LCOE) of $cents 4.5859 a kilowatt-hour ($c/kWh) for Rumah 1 and 4.6114 $c/kWh for Al-Nairiyah 1.

    Acwa Power said that the two IPPs will require a combined investment of approximately SR15bn ($4bn). The IPPs are expected to reach commercial operations in Q2 2028. 

    Saudi Power Procurement Company (SPPC) received bids for the contracts for four thermal IPPs – the other two being the similarly configured Rumah 2 and Al-Nairiyah 2 – in August last year.

    The four power generation facilities will be developed using a build, own and operate model over 25 years. 

    SPPC’s transaction advisory team for the Rumah 1 and 2 and Al-Nairiyah 1 and 2 IPP projects comprises US/India-based Synergy Consulting, Germany’s Fichtner and US-headquartered Baker McKenzie. 

    Photo credit: Mitsubishi Power (for illustrative purposes only)

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13599792/main4910.jpg
    Jennifer Aguinaldo
  • Iraq approves two major energy project contracts

    2 April 2025

    Register for MEED’s 14-day trial access 

    Iraq’s Council of Ministers has approved two major energy contracts that form part of the $10bn Gas Growth Integrated Project (GGIP), according to a statement from the prime minister’s office.

    French oil and gas company TotalEnergies and its partners are developing the GGIP.

    TotalEnergies is the main operator of the GGIP. Basra Oil Company (30%) and QatarEnergy (25%) are the other stakeholders.

    One of the two awarded contracts is focused on the development of the Ratawi gas field and the other is focused on the Common Seawater Supply Project (CSSP), which will transport seawater to oil fields for injection to increase production.

    The statement said that Iraq's Council of Ministers had approved the award of tender CSSP-ITT-06 from state-owned Basra Oil Company to China Petroleum Pipeline Engineering Corporation (CPP).

    The contract awarded to CPP is for the pipeline package, which involves the construction of a seawater pipeline.

    MEED reported that CPP was a frontrunner to win the pipeline package in May last year.

    CPP is a subsidiary of China National Petroleum Corporation and the primary builder of pipelines in its home country.

    The pipeline package is one of two major packages in the CSSP. The other major package focuses on developing a water processing facility.

    The pipeline contract awarded to CPP will be executed over 54 months, including 42 months for engineering, procurement and construction and 12 months for operation, maintenance and training.

    The second contract that has been approved is for a planned gas processing plant at the Ratawi gas processing complex project.

    The Ratawi field is also sometimes called the Artawi field.

    This contract has been awarded by Iraq’s state-owned South Gas Company to China Petroleum Engineering & Construction Corporation (CPECC).

    In January, MEED revealed that CPECC had emerged as the frontrunner to win the contract, which is estimated to be worth about $1.7bn.

    When commissioned, the planned facility is expected to process 300 million cubic feet a day of gas. Its capacity is expected to double when a second expansion phase becomes operational in the future.

    The Ratawi gas processing facility project aims to improve Iraq’s electricity supply by capturing gas that would have otherwise been flared at several oil fields, including:

    • Luhais
    • Majnoon
    • Ratawi
    • West Qurna 2
    • Tuba

    Large gas volumes are flared from these oil fields, causing significant environmental damage. Collecting and processing flared gas will generate increased hydrocarbons revenues and reduce ecological damage.

    The gas tapped and processed from the oil fields will then be used to supply power plants, helping to reduce Iraq’s power import bill.

    As well as supplying Iraq’s national gas network to generate electricity, the Ratawi gas processing complex will increase the production of gas products, including liquefied petroleum gas (LPG) and condensates.

    US-based consultant KBR has performed the front-end engineering and design work on the project.