A case study in procurement

18 March 2025

 

Register for MEED’s 14-day trial access 

While it may not be in the headlines as much as some of its more eye-catching official gigaproject counterparts, Roshn has already delivered thousands of residential units in Saudi Arabia as it seeks to fill the upscale and community living housing map.

Launched in 2020, the Roshn gigaproject is a component of the Vision 2030 plan to achieve 70% home ownership among Saudi nationals by 2030. Alongside the National Housing Company, it is the delivery vehicle for government-backed housing construction as Riyadh seeks to meet the shortfall in available stock.

Its first project was its Sedra community in the north of the capital. Currently on its fourth of eight delivery phases, the multibillion-dollar masterplanned development will comprise 30,000 homes over 20 million square metres (sq m) when completed.

Roshn’s second Riyadh community under construction is Warefa in the northeast of the capital. More compact than Sedra, it will have 2,300 units over an area of 1.4 square kilometres, with 150,000 sq m of green open space.

Three years after the launch of its first projects, Roshn announced Marafy, its first scheme in Jeddah and its largest mixed-use development to date. Designed to accommodate more than 130,000 residents, Marafy will be built around an 11-kilometre, 100-metre-wide canal, linking with Obhur Creek in the northern outskirts of the kingdom’s second city.

Already breaking ground, Marafy’s first core component is the Alarous residential community, which will offer 18,000 units over a 4 million sq m land area.

Elsewhere in the kingdom, Roshn’s other planned community projects include Almanar in Mecca, Alfulwa in Hofuf and Aldanah in Dhahran. Between them, these schemes total more than 50,000 units. It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years.

Delivering such projects at many different locations is a complex exercise, requiring procurement strategies that not only encompass on-time and on-budget completion, but also ensure that local content is maximised while at the same time maintaining stringent quality standards.

Tasked with handling Roshn’s overall procurement strategy is Iain McBride, the gigaproject developer’s head of commercial.

It is expected that thousands of additional homes in other parts of the kingdom will be announced by the developer in the next two years

Like other gigaprojects in the kingdom, McBride and his procurement team have had to deal with the twin challenges of soaring cost inflation and maximising local content in materials and equipment.

The five official gigaprojects – Diriyah, Neom, the Red Sea Project, Qiddiya and Roshn – are free to employ their own procurement rules and processes, and each has taken a different approach to address its specific requirements. For example, Red Sea Global uses a construction management approach wherein it contracts directly with companies and suppliers that would normally work as subcontractors under the main contractors.

Similarly, Diriyah Company employs a strategy of bundling several smaller contract packages into a single large contract, as a means of consolidating work to ensure lower costs and maintain contractor interest.


Hear directly from the gigaproject owners at the biggest construction event – The Saudi Gigaprojects 2025 Summit, happening in Riyadh from 12-14 May 2025. Click here to know more


Demand signalling

The nature of Roshn’s mainly residential projects means that from the outset it knew it would need thousands of items with similar specifications, such as doors; glass panes; sanitaryware; and heating, ventilation and air-conditioning systems.

To secure this supply chain, early on the company identified local manufacturers of these products and reached long-term agreements with them for the delivery of required materials.

“Our first step was signing a lot of long-term partnership agreements through master purchase agreements where we could leverage preferential rates,” says McBride, speaking to MEED in late January.

“Ultimately, it's all about balance and risk – derisking the opportunities for the supply chain by telling them how many doors, for example, we're going to need each quarter for the next five to 10 years. It gives confidence to the manufacturers that they can start committing to.”

Roshn was the first of the gigaprojects to publicly signal its demand requirements. In 2021, it announced that it would require at least 5 million doors, 3.5 million air-conditioning units, 4.3 million windows, 80 million sq m of tiles and 6.5 million pieces of sanitaryware. These numbers have since changed, but they are indicative of the scale of the supply chain challenge.

Armed with the knowledge that Roshn is both supported by its parent, sovereign wealth vehicle the Public Investment Fund (PIF), and that it is a central element of Saudi Vision 2030, local manufacturers had the confidence to commit to investing in production capacity to meet its needs.

Significantly, most of these deals have been with manufacturers within the kingdom, thereby maximising the local content aspects. Just as importantly, Roshn has not had to make any fixed orders – so-called ‘take-or-pay agreements’ – with  suppliers, such is the latter’s faith in the developer.

“For the time being, we’ve not had to make any firm commitments,” says McBride. “We did look at it at one point, but our approach has always been to keep it as simple as possible by listening to the supply chain and seeing what they need. When we were speaking to them, it wasn’t their number one driver; they weren’t screaming at us saying, ‘We need you to give us a firm order’.

“Now, many people think a take-or-pay agreement is essential – where you commit to ordering [a certain quantity] of materials over a period of months or years and, if you don’t, you have to pay a penalty, thereby adding risk and complexity for the developer.

“What we were able to agree instead was that we'll be open and transparent with [the suppliers about] what we need. We said to ourselves, ‘Let's get a good price that works, whether we buy directly from the supplier or whether we include that supplier within our tenders with major contractors’. And we’ve seen great success with that approach, with multiple companies.”

The localisation push is supported by the design process. Wherever possible, the designs for Roshn’s projects incorporate and specify equipment and materials that are known to be manufactured locally.

There have been instances where specific, specialised materials and products are not produced in the kingdom, or not in the quantities required, such as marble and certain architectural facades.

Where this is the case, Roshn is keen to explore how it can help to build in-kingdom capacity. The developer has initiatives through which it looks to co-invest in production facilities that come with high capital requirements.

As McBride explains, Roshn is only one part of the huge and rapidly accelerating Saudi projects market ecosystem, and in helping to increase capacity, it is also putting itself in a position to help other developers with their supply chain needs.

A case in point is Roshn’s contract with China Harbour Engineering Company, which was awarded the $2bn deal in 2023 to build villas at Sedra and Warefa.  

Part of the contract requires the Chinese contractor to set up a precast manufacturing facility on site at Sedra. In this way, Roshn could not only ringfence the plant for its own needs, but when it no longer requires the output, other projects could benefit from its production capacity.

“The factory has a 15-year lifespan, so any additional capacity will be there for another 10 years after our requirements are met,” says McBride. “In Riyadh, we have Expo 2030, the new airport, the stadiums and many other projects that could draw on its output.”

There are some situations where even this is not enough, particularly when it comes to contracting expertise. One such case is Roshn’s mandate to develop a 45,000-seat stadium in the southwest of Riyadh as part of the kingdom’s Fifa World Cup 2034 plans. On such a complex, highly engineered project, Roshn has insisted that an international contractor teams up with a local company as a condition of tender participation.

This insistence is based on Roshn’s experience overseeing the construction of a football stadium in Dammam alongside co-developer, Saudi Aramco. The project, which is being built by a joint venture of Belgium’s Besix and the local Albawani, is proceeding at a rapid pace and progress has been relatively trouble-free.

McBride says: “If we have to go abroad, let’s go abroad. But make sure it’s done in a smart way and that we’re not just throwing money out of the kingdom.”

Early contractor involvement

On the issue of contracting, it is well known that the massive amount of work in Saudi Arabia is stretching contractors to the limit, pushing up prices and straining labour, engineering and equipment resources.

Roshn’s approach to this challenge has been to engage with contractors at the earliest possible stage of project planning, specifically at the design phase, through an early contractor involvement (ECI) procurement framework. In this way, the company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability.

“It's about signposting the demand by getting the contractor in early, where you can really influence the design, the buildability and the value-engineering opportunities,” says McBride. “Ideally, we bring them in as quickly as possible during the concept stages, when there's very little cost to changing things.

“The worst thing for a contractor is receiving a [request for proposal] cold. They have to … come back in four weeks and then be squeezed for a best price, whereas with ECI they can add value. They really appreciate that.”

When asked to quantify the cost benefits of such an approach, McBride is forthright: “It’s not even a case of doing the maths,” he says. “We have a great example of where it’s worked on our Aldanah project in Dammam. We selected the contract very early on and locked in the floor plans and facades that we wanted. We were then able to deliver a street of 10 show homes [that took] not much more than four months to design and construct.

“The saving, in terms of time, was massive; we probably halved the duration. I probably wouldn’t be exaggerating if I said it saved about a year.

“There are two ways you can follow your engineer,” he continues. “One: you can follow them early and make sure that the way you're looking to save costs is in areas that are not impacting the customer.

“Or two: the worst thing you can do is get to the end and you have a full structural design that could be over-engineered and you’re spending money in the wrong places.

“We don’t want to get to a point where we're trying to value-engineer by cutting things out that are important to customers,” McBride explains. “And that's what you avoid by having this early contractor involvement.”

The company is able to obtain contractor feedback during concept and design and subsequently lower construction risk by improving a project’s constructability

Unlike the other gigaprojects, Roshn has been in the favourable position of being able to raise some revenue by marketing and selling its properties off plan. While this has been beneficial from a development perspective, it has also meant that the developer must get its pricing and housing specifications right if it is to develop homes within an already-defined budget.

Having a contracting partner on board during the design and specification stage facilitates the conversation between the property sales team, which is informing on market requirements, and the builder, who can deliver within the designed cost and quality parameters.

This is in contrast to many real estate developments for which sales are completed before the construction estimates come in, potentially undermining the business case.

The step beyond ECI is for contractors and suppliers to partner with Roshn to inject equity into the projects by acting as co-developers. McBride points to several planned mid-rise towers at Marafy that could be a starting point for this.

Contractors financing projects or bringing in replacement equity has long been an ambition in the region, but builders have been reluctant to adopt this approach. Nonetheless, McBride is confident that it could happen, indicating that there has already been strong interest from the contracting community.

Cost inflation

Another major talking point in Saudi construction is the escalating costs caused by high inflation, logistical challenges and a tightening of contracting and skilled labour capacity.

In many cases, this has required the rescoping of projects, revisions to timelines and even the scrapping of elements. Neom is arguably the best example of this, as it has reprioritised The Line and is facing an estimated cost of $50bn for building each of its first three modules – far in excess of original estimates.

Roshn’s approach to the challenge is to be as open and transparent as possible with the contractor and supplier community. This has involved outlining a long-term pipeline of work that gives the supply chain confidence about its requirements, enabling them to fix in long-term pricing structures. In return, the developer expects prices to come in competitively.

“It’s no secret within the supply chain market that Roshn has quite aggressive price points,” says McBride, a former chartered surveyor who, prior to joining Roshn, worked as a quantity surveyor and cost-management director at consultants Faithful+Gould (now AtkinsRealis) and Rider Levett Bucknall.

“What we're trying to do is engage early, build trust with the contractors, let them see we’re a good client that's going to pay and have honest and fair contracting terms, and work together to try and solve issues post-contract.

“We don't mind if there's inflationary pressures because of commodity prices increasing. But what we're trying to avoid is inflationary prices through just the demand increasing.

“An innovative way that we've implemented this even on our lump-sum contracts – our traditional Redbook or older contracts – is that we have preferred supplier agreement clauses in them,” he adds.

“So, rather than a traditional bill of quantities (BoQ) that has a rate, a quantity, a total, within our rate section we have the material supply rate, the installation rate and then everything else, such as overhead profit. We protect the installation rate, so it's not a percentage of the material; it's a fixed SR100 a square metre to install, for example.

“One of the big frustrations for contractors is [that the supplier has] a material we think they're going to deliver. It's maybe not available, so they submit alternative materials. The client keeps rejecting it – it's not what they want – and it becomes a delay; it's painful.”

McBride gives the example of a pre-approved bathroom sink. Thanks to Roshn’s relationships with key long-term suppliers, the company is able to negotiate better rates for sanitaryware than would be available to a contractor on an ad hoc basis. If the developer’s rates for sinks are better than the BoQ, it splits the savings 50:50 with the contractor.

“The contractors are winning out of that exercise, we're winning out of it and, ultimately, the customers are winning out of it as well, because we’re passing on those savings,” says McBride.

Flexibility

The benefits to contractors and suppliers extend to payment terms. In today’s sellers’ market, vendors are effectively able to pick and choose the clients they want to work for. As a result, clients – including the gigaprojects – have had to introduce more flexible payment terms and develop market reputations for paying on time.

Roshn may lead the pack on this, with an average payment time from invoice to payment of just 13 days in 2024. A decade ago, this would have been unheard of, but it is now increasingly becoming the norm among the gigaprojects.

In addition, like its PIF peers, Roshn has done away with tender fees and tender bonds, viewing them as outdated means of enforcing vendor participation, especially given the tight liquidity and cashflow situation in the projects market in Saudi Arabia.

Will such flexibility ever extend to performance bonds? McBride is sceptical, pointing to the fact that Roshn’s strong relationship with local banks allows to it facilitate credit agreements between contractors and their lenders. Being a gigaproject developer supported by the PIF – and by tacit extension the state – also helps provide the underlining ease of mind for financers.

Nonetheless, Roshn also takes a proactive approach with advanced payments, enabling up to 20% of the total contract value at the initial stage of the project.

“We've been quite clever in how we do this,” says McBride. “We don't go and release 20% straight away. We’ll do 10% and then, when we’ve evidence that you’ve expended that 10% on mobilisation and site establishment, we’ll release the second 10% tranche.”

Subcontractors

One of the chief sticking points in the kingdom’s projects ecosystem in the past decade has been the capacity and capability of its subcontractors.

The payments crisis in 2017-20 forced many main and general contractors to reduce their permanent labour forces, plant and general resources. Wary of a repeat, most have retained their leaner structure and so have turned increasingly to subcontractors for their manpower and delivery requirements.

In theory, this makes sense, but in practice subcontractors in Saudi Arabia are themselves often overstretched in terms of both delivery capacity and labour availability. In turn, they frequently use their own subcontractors, which then also outsource, to the point that specific elements of a project may be completed by companies very far down the supply chain – with the quality issues that this implies.

Roshn’s solution is to ensure any subcontractor on site goes through a vetting process encompassing quality and financial checks, thereby ensuring it has full visibility on every company on site.

Increasingly, Roshn is dealing with suppliers directly, under supply-install contracts. This can create interfacing issues with the main contractors, however, which are ultimately responsible for the project’s delivery.

“We have to be quite careful on that,” McBride says. “We have to go through all the checks and balances during the prequalification process because if we are going to give a subcontractor to a contractor that we're saying is pre-vetted by Roshn, we could be opening the door to lots of claims from the main contractor against us. So, vetting for us is absolutely crucial.”

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow, so that they can start taking on smaller main contractor roles themselves.

“Not every construction package we award is in the billions of riyals,” says McBride. “Our thinking is to let the big tier-one contractors focus on the multibillion-riyal deals while we encourage the smaller ones to grow as part of our supplier development programme.”

To achieve this, the developer holds events and bootcamps with its vendors to discuss best practices on subjects including health and safety, variation procedures and how to submit good tender returns.

Roshn is also working with smaller suppliers and subcontractors to help them evolve and grow

Building information modelling

Vendor education also extends to the use of building information modelling (BIM) and other construction technologies.

BIM is mandatory on Roshn’s projects, as it is on the other gigaprojects. While use of the technology is standard across almost all main contractors in the region, its take-up among smaller companies in the supply chain has been slower, with firms pointing to the cost of its adoption and integration as a barrier, as well as the fact that some clients, particularly government ones, view it as providing limited benefit.

Roshn’s task in this area is made difficult because its projects are less complex from an engineering and construction perspective.

“We’re building villas; it’s completely different to building stadiums or airports,” McBride says. “Can these contractors build from [two-dimensional] drawings? Yes, of course they can. You're not going to convince a smaller contractor that all of these benefits will make it easier to build because they know how to build. They've been doing it for decades.

“But the savings are in making it easier to procure, savings in the repeatability, and in the change control. If you upskill yourself on a Roshn project, you are building your capability, which you can then [demonstrate] to other clients as proof you can go after bigger and more complex projects. It's something that the whole industry has to get behind.”

Indeed, there is much to learn from Roshn’s approach to delivering its infrastructure and building plans. While the comparatively straightforward nature of its projects means that its procurement strategies may not be suited to those gigaprojects with more iconic designs, for many other developers it is a case study in efficient processes that have proven effective in delivering work on time and to budget.

This is just as well given that Roshn is set to embark on the next stage of its journey, with its focus on the more complex Marafy city development in Jeddah and Roshn Stadium in Riyadh. However, the evidence suggests that from a procurement strategy perspective, it is well-positioned to also make this a success.



https://image.digitalinsightresearch.in/uploads/NewsArticle/13503828/main.gif
Edward James
Related Articles
  • Delivery unlocks gigaproject investment

    29 September 2026

     

    Register for MEED’s 14-day trial access 

    Completed infrastructure and open assets are making it easier to attract private developers and foreign investors to Saudi Arabia’s gigaprojects, said speakers at MEED’s Shaping Mega Projects conference in Riyadh on 28 September.

    Dale Chadwick, acting CEO of King Salman Park Foundation, said investor appetite had grown as construction advanced. The foundation has received 23 expressions of interest from private developers, and Chadwick said that number was increasing.

    “What the private sector is looking for in terms of investment is surety of what we’re doing,” he said. “As soon as a private developer comes in and sees what we’re doing, they’re blown away. The closer we get to completion, the greater the appetite.”

    He said interest from foreign direct investors was also rising, and that a deal the foundation expects to award soon involves foreign investment.

    The foundation times its private asset awards to follow infrastructure and landscaping works. “They don’t have to take the leap of faith that we are going to execute on our side of the equation,” said Chadwick. “They can see it.”

    Partnership model

    Mohamed Saad, president of DevCo at Diriyah Company, said investors wanted a relationship rather than a transaction.

    “The first thing they’re looking for is partners,” he said. "They’re looking for master developers who act as true partners to them.”

    Saad said master developers acted as the catalyst, investing in infrastructure and anchor assets before the private sector joins. He said investors also wanted healthy supply and demand, and a market able to absorb commercial assets in phases.

    He said Diriyah had prioritised delivery over publicity. “People want to see to believe,” said Saad. “We are delivering on the ground, and when people come and visit, they’re pleasantly surprised.”

    Chadwick said developers also wanted flexibility, with some seeking more height or a different mix of uses. “We ourselves have a plan, but in order to make that more attractive, we have to be prepared to make adjustments as well,” he said.

    Ben Edwards, group head of cost, commercial and procurement at Red Sea Global, said the operating track record of The Red Sea and Amaala was now its strongest pitch to investors.

    "We’ve gone past the field of dreams approach of ‘if you build it, they will come',” he said. "We’ve built it now. The tourists are coming.”

    Edwards said Red Sea Global was at various stages of negotiation on several joint venture opportunities for future projects.

    The developer’s utilities public-private partnership (PPP) at The Red Sea is fully operational. Its Amaala equivalent is in final testing and commissioning and is due to be operational before the end of the year. Edwards expects the model to spread.

    "I’m sure the PPP market will continue to expand into the different infrastructure sectors here, and then lead into other sectors, from schools to hospitals,” he said.

    He added that Red Sea Global’s environmental credentials were a selling point for investors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20084647/main.jpeg
    Colin Foreman
  • KBR seeks renewable energy contracts in Libya

    29 September 2026

     

    The US-headquartered technology and engineering company KBR is seeking renewable energy project contracts in Libya.

    Representatives from KBR met with Abdussalam Elansari, chairman of the Renewable Energy Authority of Libya, earlier this month to discuss project opportunities, sources said.

    The meeting with Elansari followed KBR’s opening of a new branch in Libya and its securing of several contract awards in the oil and gas sector.

    In March, KBR announced that it had been awarded a contract by Zallaf Exploration, Production & Refining of Oil & Gas Company to provide project management and technical services for the South Refinery Project in Libya’s southern city of Ubari.

    Under the terms of the contract, KBR will provide contract management, project management and supporting technical services throughout the engineering, procurement and construction (EPC) phases of the project, according to a company statement.

    The EPC work is expected to be executed over a 50-month period.

    KBR is also carrying out work to re-evaluate the front-end engineering and design (feed) for the project to develop Libya’s J6 North Gialo field.

    In January, KBR signed a memorandum of understanding (MoU) with the state-owned Libyan Post, Telecommunications & Information Technology Company.

    Under the MoU, KBR agreed to support efforts to develop and improve Libya’s communications infrastructure and enhance fifth-generation (5G) mobile networks in the country.

    KBR has previously provided engineering services for major national projects in Libya, but was forced to shut down its office in the country several times amid political instability and security issues.

    When the company was known as Brown & Root, it worked on the Great Man-Made River Project in Libya, which is widely recognised as the largest irrigation project in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20081880/main.jpg
    Wil Crisp
  • Giga developers absorb supply chain shocks

    29 September 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s gigaproject developers are rerouting shipments and absorbing higher freight costs as regional geopolitical tensions disrupt supply chains. Executives discussed the impact at MEED’s Shaping Mega Projects conference in Riyadh on 28 September.

    Mohamed Saad, president of DevCo at Diriyah Company, said supply chain disruption was one of several challenges facing the developer. He said it required the company to be adaptive and quick in its decision-making.

    He said the wider situation had also weighed on end-user demand. “The appetite to buy residential units or lease retail or commercial office spaces has softened,” he said. “We also see opportunity, and developers who believe in the future and invest and develop in these times will catch the opportunity.”

    Rerouted shipments

    Dale Chadwick, acting CEO of King Salman Park Foundation, said the park had been fortunate because much of its supply chain was already in place.

    Some bespoke construction materials sourced from India have been affected, forcing suppliers to change routes. The foundation has also been unable to import some trees from China, because extended delivery times meant they would spend too long at sea.

    “It is a genuine challenge, and it’s on a case-by-case basis,” said Chadwick. “We make the call, then we pivot and start trying to secure the material from elsewhere.”

    He said one alternative was sourcing from Europe through a different supply route into the kingdom’s west coast. Chadwick said the impact had so far been manageable, with no significant effect on the park linked to the geopolitical situation. He added that contractors were facing the same pressures and suggested some might be seeking higher margins as a result.

    Local content

    Ben Edwards, group head of cost, commercial and procurement at Red Sea Global, said the developer had been shielded by the stage its projects had reached. The high proportion of local content in its procurement had also helped.

    Red Sea Global set up a landscape nursery to bring plants in early and acclimatise them. Edwards said the nursery, the largest in the region, had doubled in size to about 200 hectares.

    Freight costs have still risen sharply. “Container prices have doubled, and you have to just face that,” he said. “Where you haven’t got any other route to bring things in, and you’ve got to pay double, and you need the stuff, then you have to be flexible and deal with it accordingly with the supply chain.”

    Edwards said the local supply chain had strengthened since the peak of gigaproject construction activity.

    “The capability was here in Saudi, but the capacity wasn’t necessarily here at the time that everybody needed it three or four years ago,” he said. “Everybody needed all the same stuff all at the same time.”

    He said support from the Ministry of Investment and government programmes to build supplier capability was starting to pay off. Supplier quality was improving as capacity grew.

    Saad said the contracting market was also maturing. A correction was allowing contractors to be more selective about the work they pursue.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20082381/main.jpg
    Colin Foreman
  • Sharakat receives bids for Riyadh East sewage treatment plant

    29 September 2026

    Saudi Arabia’s state water offtaker Sharakat has received bids for the contract to develop the $150m Riyadh East independent sewage treatment plant (ISTP).

    Bids were submitted on 28 September.

    The plant will have a treatment capacity of 200,000 cubic metres a day (cm/d) in its first phase, expanding to 500,000 cm/d in the second phase.

    Five consortiums made offers, including:

    • EtihadWE (UAE) / Metito (UAE) / Thrustboring Construction Company (TCC, Saudi Arabia)
    • GS Inima (Spain) / Alkhorayef (Saudi Arabia) 
    • Lamar (Bahrain) / China Harbour Engineering Company (CHEC)
    • Miahona (Saudi Arabia) / Marafiq  (Saudi Arabia) / Bin Omairah Holding (Saudi Arabia)
    • Suez (France) / Civil Works Company (Saudi Arabia) / Alwael (Saudi Arabia)

    In May, MEED exclusively reported that groups had begun to form for the project, which will be developed under a build‑own‑operate‑transfer model with a 25‑year concession term.

    It is understood that at least two other potential consortiums weighed up making an offer for the contract, but did not bid.

    In 2024, Sharakat prequalified 53 companies that could bid for the Riyadh East ISTP, part of seven planned ISTP projects it said it would procure between 2024 and 2026. The request for proposals was issued last October. 

    WSP is the technical adviser, and KPMG Middle East is the lead and financial adviser.

    The targeted commercial operation date for the facility is 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20066914/main.jpg
    Mark Dowdall
  • Egypt firm wins Al-Dabaa desalination O&M contract

    29 September 2026

    Elsewedy Utilities has been awarded a three-year operation and maintenance (O&M) contract for a seawater desalination plant in Al-Dabaa on Egypt’s north coast.

    The plant has a production capacity of 40,000 cubic metres a day (cm/d), and the contract runs for three years.

    The award reflects Egypt’s increased focus on involving local private sector companies in operating and maintaining existing seawater desalination plants.

    In March, Egypt’s Ministry of Housing, Utilities & Urban Communities directed that a number of existing desalination plants with capacities of more than 10,000 cm/d be offered to specialised local private sector companies for O&M. The plants include facilities in Al-Dabaa, Matrouh and El-Alamein, as well as sites in the Red Sea region and North and South Sinai.

    The government said the move is intended to improve operating efficiency, strengthen maintenance systems and make greater use of specialised technical expertise. The contract value was not disclosed.

    Elsewedy Utilities is the utilities and facilities management arm of Elsewedy Electric, with activities spanning engineering, procurement and construction, O&M and utility management.

    As MEED understands, the contract is separate from the South Med desalination project at Al-Dabaa, which is being developed for the Engineering Authority of the Armed Forces’ Water Management Department.

    Elsewedy Electric Infrastructure previously announced it is the main engineering, procurement and construction contractor for the planned 160,000-cubic-metre-a-day seawater reverse-osmosis plant.

    Cairo-headquartered Engineering Experience Group also won a design and engineering services contract for the project in June.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20066727/main41574303.jpg
    Mark Dowdall