Adnoc Gas awards $2.1bn gas infrastructure contracts

10 January 2025

 

Register for MEED’s 14-day trial access 

Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has awarded three contracts worth $2.1bn to build infrastructure that will facilitate gas feedstock for the upcoming liquefied natural gas (LNG) terminal in Abu Dhabi’s Ruwais.

A consortium of Egyptian contractors Engineering for the Petroleum & Process Industries (Enppi) and Petrojet won a $1.24bn contract for the engineering, procurement and construction (EPC) of an LNG pre-conditioning plant within Adnoc Gas’ Habshan-5 gas processing complex.

The LNG pre-conditioning plant is intended to have the capacity to supply 1.5 billion cubic feet a day (cf/d) of gas feedstock for the Ruwais LNG complex.

UK-headquartered Petrofac secured a $335m contract to develop new compression facilities at the Habshan gas processing complex. This contract constitutes package 5 of Adnoc Gas’ larger project to upgrade its sales gas pipeline network across the UAE, also known as Estidama.

China Petroleum Pipeline Engineering Company won a $514m contract for EPC works to build a transmission pipeline network to provide gas to the Ruwais LNG complex and to other Adnoc Gas customers in the Northern Emirates.

This contract constitutes package 8 of the Estidama megaproject. In November, MEED reported that China Petroleum Pipeline Engineering was the favourite to win Estidama package 8.

The selection of contractors for packages 5 and 8 concludes the contract award exercise for the estimated $3bn Estidama megaproject. Through the Estidama scheme, Adnoc Gas aims to extend the existing 3,200 kilometre (km) pipeline network to over 3,500km, enabling the transportation of higher volumes of natural gas to customers across the UAE.

Detailed scope of work

The new LNG pre-conditioning plant will treat gas processed at facilities being built as part of Adnoc Gas’ Maximise Ethane Recovery & Monetisation (Meram) project.

Adnoc Gas awarded a $3.6bn contract for Project Meram to a consortium of Abu Dhabi’s NMDC Energy and Spanish contractor Tecnicas Reunidas in August 2023.

The Meram project has dual objectives. The first goal is to increase ethane extraction by 35%-40% from Adnoc Gas’ existing onshore facilities in the Habshan gas processing complex by constructing new gas processing facilities. The second goal is to unlock further value from existing feedstock and deliver it to Ruwais via a 120km natural gas liquids (NGL) pipeline.

The new LNG pre-conditioning plant will be an intermediate gas treatment facility for gas originating at Meram facilities, with the contractors required to perform EPC of the following units:

  • High-pressure absorber and regenerator columns and internals
  • Internals for high-pressure absorber and regenerator
  • Molecular sieve adsorber
  • Air-cooled exchangers
  • Centrifugal compressor
  • Centrifugal horizontal pumps
  • Cooling water refrigeration
  • Instrument air compressor
  • Gas turbine generator
  • Steam turbine generator
  • Waste heat recovery boilers
  • Power transformers 132/33kV
  • Integrated control and safety system
  • Tie-ins with Meram units and existing Habshan-5 facilities
  • Associated civil works, including grading works, road works and fencing

Estidama package 5, won by Petrofac, broadly covers the upgrade of the Habshan gas processing complex, and includes the EPC of the following units:

  • Booster station
  • Variable frequency drive motor-driven compressors
  • New compressor trains
  • High-pressure gas discharge units
  • Fibre optic cables and other communication equipment
  • Control systems
  • Safe and security systems

Petrofac is currently involved with several key projects involving the Habshan gas processing complex. The London-listed contractor won the main EPC contract for Estidama package 2 in July 2023. The scope of work on the $720m contract involves building a new facility at the KP-30 location of the Habshan gas compressor plant and installing three variable-frequency drive motor-driven compressors.

Separately, Adnoc Gas awarded Petrofac a $615m EPC contract in October 2023 for the carbon dioxide (CO2) recovery project at the Habshan complex. The planned Habshan carbon capture, utilisation and storage (CCUS) facility will have the capacity to capture and permanently store 1.5 million tonnes a year (t/y) of CO2 within geological formations deep underground.

The scope of work on Estidama package 8, won by China Petroleum Pipeline Engineering, involves building a gas transport pipeline in two sections.

The first segment of the pipeline will be a 56-inch suction line that runs 26km from the LNG pre-conditioning plant at the Habshan-5 facility to the Habshan gas processing complex. The second section is a larger portion of the pipeline. The 52-inch, high-pressure discharge line will run 155km from the KP-30 station at the Habshan gas processing complex to the upcoming Ruwais LNG facility.

Ruwais LNG terminal project

The upcoming LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.

Adnoc awarded the full EPC contract to the consortium of Technip Energies, JGC Corporation and NMDC Energy and achieved the final investment decision for the Ruwais LNG terminal complex in June last year.

The complex will also feature process units, storage tanks and an export jetty for loading cargoes and LNG bunkering, as well as utilities, flare handling systems and associated buildings.

Separately, Adnoc has also signed agreements with international energy companies to divest a total stake of 40% in the Ruwais LNG project.

UK energy producer BP, Mitsui & Co, Shell and French energy producer TotalEnergies will each hold 10% stakes in the Ruwais LNG terminal project, with Adnoc retaining the majority 60% stake in the facility.

Adnoc Gas will acquire its parent’s 60% stake in the Ruwais LNG facility, at cost, in the second half of 2028, when first production from the complex is due.

Along with awarding EPC contracts for the LNG pre-conditioning plant, the new compression facilities at the Habshan complex and the gas feedstock transmission pipeline, Adnoc Gas announced that capital expenditure on the three packages does not form part of the costs previously outlined by the company for its intended acquisition of Adnoc Group’s majority stake in the Ruwais LNG project.

The capex on the three projects forms part of Adnoc Gas’ $15bn capex portfolio until 2029.

ALSO READ: New CEOs take charge at Adnoc gas business units

https://image.digitalinsightresearch.in/uploads/NewsArticle/13247811/main10281124.jpg
Indrajit Sen
Related Articles
  • Jordan’s Nepco obtains $70m finance for grid

    21 February 2025

    The European Bank for Reconstruction & Development (EBRD) and the EU have approved a €67.1m ($70.2m) financing package for Jordan's state-owned utility, National Electric Power Company (Nepco).

    The financing package consists of a sovereign-guaranteed EBRD loan of up to $56.5m and an EU investment grant of up to €12.4m.

    These funds will finance the construction of a new high-voltage electricity substation in northern Jordan to improve the grid’s capacity, enabling it to handle existing and new generation in the north of the country, said EBRD

    The new substation will not only improve the grid’s ability to handle additional generation capacity, but also facilitate cross-border interconnections, as well as reduce transmission losses by optimising power flows across the national grid.

    The project to be financed will include the construction of four new overhead transmission lines: two 400-kilovolt (kV) lines providing connections to the existing Samra and Amman West substations, and two 132kV lines connected to the Hasan Industrial and Jerash substations.

    These projects support Jordan's ambitious renewable energy targets for 2030.

    The financing will be complemented by a comprehensive technical cooperation package. An EU-funded technical cooperation grant of €2.2m will also be provided to appoint a project implementation consultant for Nepco.

    Nepco is the owner and operator of Jordan’s transmission system, as well as the single buyer of electricity.

    Since the start of its operations in Jordan in 2012, the EBRD has invested almost €2.3bn across 74 projects, providing more than €815m to projects in the country’s energy sector through 14 loans.

    In February 2023, Jordan's Water & Irrigation Ministry and the local firm Arab Towers Contracting Company signed an agreement worth €79.5m ($84.7m) for the design and implementation of a wastewater treatment plant in the Ghabawi region. EBRD provided a €41.3m loan while the EU agreed to provide a €30m grant for the project.

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13414961/main.jpg
    Jennifer Aguinaldo
  • Saudi Arabia capacity buildout enters busiest period

    21 February 2025

    Saudi Arabia has entered what could be the busiest period for power generation capacity buildout in its entire history.

    According to data from regional projects tracker MEED Projects and MEED, a total of 53GW of power generation capacity is under construction or about to start construction following the formal award of contracts or the selection of bidders.

    Generation and cogeneration plants powered by natural gas account for two-thirds, or 66.7%, of the total capacity under construction, with renewable plants, mainly solar, accounting for the rest.

    Solar and wind power plants, however, dominate the pre-execution pipeline, accounting for roughly 94% of the capacity that is currently under bid or prequalification.

    Inclusive of projects in the study and design phase, the total thermal and renewable generation capacity being planned and tendered in Saudi Arabia stood at around 80GW as of February 2025.

    The major capacity buildout is in line with the kingdom's liquid displacement programme as well as its target for renewable energy sources to account for half its electricity production by 2030.

    According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1 TWh, or about 36%, of the total, with natural gas accounting for 265TWh, or 63%, and renewables, 5.8TWh or 1%.

    CCGT plants

    The urgency of displacing its oil-fired fleets underpins the successive contract awards for combined-cycle gas turbine (CCGT) power generation plants, which are being developed as independent power projects (IPPs) or via engineering, procurement and construction (EPC) contracts.

    Roughly 47% of the 35.8GW of gas-fired capacity under construction is being built via an EPC or design and build model, mainly by the Saudi  Electricity Company (SEC), while the rest are being built using an IPP model.

    Of the total thermal capacity under construction, about 45% will be generated by greenfield power plants that are being built as an expansion to existing power generation facilities across the kingdom.

    Chinese contractors such as Sepco 3 and China Energy Engineering Corporation, among others, are constructing 10 of the 19 gas-fired power generation and cogeneration plants that are under execution in Saudi Arabia. An eleventh plant is being constructed by Sepco 3 in partnership with Doosan Enerbility, of South Korea. The 11 plants equate to a capacity of roughly 21GW.

    South Korean contractors, mainly Doosan and Samsung C&T are in four of the 19 projects.

    "I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source tells MEED, in reference to Tecnicas Reunidas, Orascom and Elsewedy, which have been selected to undertake the EPC contracts for several CCGT plants last year.

    The peak for new gas-fired contract awards may have passed, however.

    MEED Projects data indicate that four cogeneration plants with a combined capacity of around 1.5GW  are in the pre-execution stage. And, only at least two gas-fired IPP schemes - Shoaiba and Al-Shuqaiq - are currently under study, each with a planned capacity of 2.6GW.

    However, a "surprise"  new project, such as the 3GW expansion of the Qurayyah IPP, announced on 20 February, cannot be ruled out. 

    Renewables  

    A reverse trend could be seen for renewable solar power generation capacity.

    As of February 2025, nearly all renewable energy capacity under construction in Saudi Arabia is being developed as IPPs.

    Around 43% of these IPPs are publicly tendered by the principal buyer, Saudi Power Procurement Company (SPPC), while the rest are directly negotiated between the Saudi sovereign vehicle, Public Investment Fund (PIF), and the dominant local utility developer, Acwa Power.

    The pre-execution pipeline for solar and wind energy projects, which will be procured by SEC and gigaproject developer Neom, is staggering, especially given a directive by the Energy Ministry to procure up to 20GW of renewable energy capacity annually until 2030 subject to demand growth.

    "It is a massive pipeline," notes a Dubai-based senior transaction adviser.

    However, he also notes that a re-scoping process is under way especially for renewable energy projects designed to cater to Neom, the $500bn development in northwestern Saudi Arabia, which aims to be powered 100% by renewables by 2030.

    Issues related to land allocation may also become an issue if it has not yet, notes another industry expert.

    Deployment of additional renewable energy capacity will also require a major battery energy storage system buildout, which started last year, to ensure the flexibility of the electricity grid. 

    "The question is how much batteries they will need and how much batteries will be available to support that ambition," the consultant said.    

    Data centres

    In addition to the liquid displacement programme and the 50% renewable energy production target by 2030, Saudi Arabia has been seeing a major uptick in data centre construction projects in line with a plan to become a major artificial intelligence (AI) hub.

    Hyperscalers such as Amazon Web Services, Google and Microsoft plan to expand their digital or cloud infrastructure in Saudi Arabia in line with this strategy. These and other AI  players, as well as local firms such as DataVolt, Ezditek, Alfanar and the UAE-based Gulf Data Hub, among others, pledged around $15bn of investments in such infrastructure during the recently concluded Leap technology conference in Riyadh, with more investments expected to be announced over the coming months or years.

    These projects, assuming they all come to fruition, will significantly increase computing, cooling and overall electricity demand. The need to make these advanced data centres as sustainable as possible will also further incentivise the kingdom's national renewable energy programme.

     

     

       

     

     

      

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13414408/main.gif
    Jennifer Aguinaldo
  • Hyundai E&C wins $389m Saudi grid contracts

    21 February 2025

    South Korea’s Hyundai Engineering & Construction (E&C) has won two power transmission line contracts worth approximately $389m in Saudi Arabia.

    The transmission lines will be built in Saudi Arabia's Medina and Jeddah regions, the firm said.

    The 380-kilovolt (kV) Humaiji transmission network will extend 311 kilometres and transfer power from a solar power plant in Humaiji to a substation in the Medina area.

    The 380kV Kulais transmission network will extend 180 kilometres and transmit power from a solar facility planned for construction in the coastal Kulais area to an existing transmission network in Jeddah.

    The project owner is Saudi Electricity Company, which conducted a competitive bidding process among a selected number of engineering, procurement and construction (EPC) companies, said Hyundai E&C.

    In November, Hyundai E&C won a KRW1tn ($725m) contract to build a high-voltage direct current (HVDC) network project in Saudi Arabia.

    The contract forms part of a 1,089-kilometre (km), 500-kilovolt (kV) HVDC transmission line connecting Riyadh Power Plant 14 (PP14) to the Kudmi substation in southwest Saudi Arabia.

    The company signed the contract to build the transmission line's first package, which extends over 369km, with National Grid, the power transmission unit of state utility Saudi Electricity Company (SEC).

    The lump sum turnkey project is expected to be completed by January 2027.

    Photo credit: Hyundai E&C

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13413980/main.jpeg
    Jennifer Aguinaldo
  • Sojitz-backed Capella eyes Middle East PPPs

    20 February 2025

     

    Public-private partnership (PPP) projects across the Middle East will be a key focus for Sydney-headquartered infrastructure developer and investor Capella Capital, according to two sources familiar with the matter.

    "The Middle East … is one of the potential markets to expand the business portfolio of Capella," one of the sources said.

    MEED understands that the region is included in Capella's medium- to long-term growth strategy.

    This development follows the acquisition of the company by Japanese infrastructure investor Sojitz in January this year.

    Valued at AUD470m ($300m), the acquisition is targeted for completion in June this year.

    Sojitz says the acquisition is in line with its efforts to "strengthen its large-scale infrastructure development capability in the energy, social and transportation infrastructure fields" in Australia, as well as in global markets.

    It will also support Sojitz's transformation into an "integrated business model that manages projects from initial formation to asset management".

    Capella will likely follow the entry into the Middle East PPP market of fellow Australian infrastructure investor, Plenary Group.

    Abu Dhabi holding company ADQ acquired a 49% stake in Plenary in April 2024, including all shares owned at the time by the Canadian pension fund Caisse de Depot et Placement du Quebec.

    In a statement issued in September last year, ADQ said the two firms plan to establish a co-investment platform, which will focus on public and social infrastructure opportunities "in high-growth geographies including the GCC region, the Middle East and Central Asia".

    In August last year, the Abu Dhabi Investment Office (Adio) appointed a team of Plenary, Belgian firm Besix and the local Mazrui International for a contract to develop and operate a 3,250-bed student accommodation complex and associated facilities at Khalifa University in Abu Dhabi. 

    Plenary is also part of a consortium that is understood to be planning to bid for the first two packages of the $22bn Dubai Strategic Sewerage Tunnels project.  

    In April 2023, Saudi Arabia launched a pipeline of 200 PPP projects in 17 sectors. Adio is responsible for coordinating PPP projects in Abu Dhabi, while Oman's Finance Ministry oversees the sultanate's planned PPP projects. 

    Photo credit: Pixabay (for illustrative purposes only)


    READ THE FEBRUARY MEED BUSINESS REVIEW

    Trump unleashes tech opportunities; Doha achieves diplomatic prowess and economic resilience; GCC water developers eye uptick in award activity in 2025.

    Published on 1 February 2025 and distributed to senior decision-makers in the region and around the world, the February MEED Business Review includes:

    > WATER & WASTEWATER: Water projects require innovation
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13411316/main5649.jpg
    Jennifer Aguinaldo
  • SEC and Acwa Power sign Qurayyah IPP expansion deal

    20 February 2025

    Register for MEED’s 14-day trial access 

    Riyadh-based utility firm Saudi Electricity Company (SEC) and Acwa Power have signed a power-purchase agreement with the principal buyer, Saudi Power Procurement Company, for the expansion of the Qurayyah independent power project (IPP) in Saudi Arabia.

    The Qurayyah IPP expansion project will have a generation capacity of 3,010MW and is expected to be carbon capture-ready, the two firms said in separate bourse filings on 20 February.

    SEC and Acwa Power will each have an effective shareholding of 40% in the project, which is valued at SR13.4bn ($3.57bn).

    Hajj Abdullah Alireza & Company (Haaco) will own the remaining 20%. 

    The three firms will develop, finance, build, own and operate the combined-cycle gas turbine plant.

    The project also includes the development, financing, construction and transfer of a 380-kilovolt (kV) electrical substation.

    The project duration is 25 years from the plant commercial operation date.

    Acwa Power, South Korea's Samsung C&T, Mena Infrastructure Fund and SEC own Hajr Electricity Production Company, the development company behind the existing 3.9GW Qurayyah 1 & 2 IPP in Saudi Arabia.

    The Qurayyah 1 & 2 IPP reached commercial operations in 2015.

    The expansion of the Qurayyah IPP is not to be confused with a separate engineering, procurement and construction (EPC) project with the same name.

    Egyptian contractor Orascom is understood to be undertaking the EPC contract for the 3.6GW Qurayyah EPC project.

    MEED reported in September 2024 that Orascom had received limited notice to proceed on the project from SEC.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13411202/main4001.gif
    Jennifer Aguinaldo