Oman pursues utility and grid expansion
5 December 2024
Expanding renewable energy and water production capacity and interconnecting disparate grids have been key priorities for Oman’s main utility stakeholders, especially over the past two years.
These efforts support a stated objective for renewable energy to account for 30% of Oman’s electricity generation capacity by 2030 – or an intervening milestone of about 3,000MW by 2027 – while ceasing to procure new thermal capacity.
“As in every other GCC state, the role of renewables is enshrined in Oman’s overall energy production mix target,” notes a UAE-based infrastructure consultant.
In addition to the longer-term renewable energy target, the sultanate expects new wind and solar projects to contribute to almost 11% of electricity production by 2025, according to the state offtaker Nama Power & Water Procurement Company’s (Nama PWP) latest seven-year statement covering 2023-29.
The milestones appear manageable. While Oman’s operational renewable energy capacity, mainly from the Ibri 2 solar independent power project (IPP), is only around 500MW, a further 1,000MW is under construction through the Manah 1 and Manah 2 solar IPPs.
The tendering process is also under way for around 1,000MW of wind IPP schemes.
In September, Nama PWP invited firms to bid for a contract to develop and operate the first two wind farms it is procuring under an IPP framework.
Located in South Sharqiyah Governorate, the Jalan Bani Bu Ali wind IPP will cater to Oman’s Main Interconnection System (MIS). It will have a capacity of 91MW-105MW and a commercial operation target of Q1 2027.
The second scheme is the Dhofar wind IPP, catering to the smaller Dhofar Power System (DPS). It will have a capacity of 114MW-132MW and will be operational in Q2 2027.
Three other wind schemes will be tendered over the following months, bringing the total capacity of wind IPPs to be developed in Oman over the next two to three years to over 1,000MW.
Nama PWP is also expected to issue the request for proposals for the 500MW Ibri 3 solar IPP scheme shortly.
Expiring capacities
While Muscat has said it does not plan to procure further thermal power generation capacity in the foreseeable future, it successfully extended the contracts for several expiring thermal power generation and water desalination capacities earlier this year.
These agreements collectively secured over 1,500MW of electricity and 200,000 cubic metres a day (cm/d) of desalinated water for up to nine years.
The contract renewals follow the expiry or expected expiry of the power- or power and water-purchase agreements for the following plants:
- Barka 1 independent water and power project (IWPP): 427MW (installed power generation capacity) / 101,000 cm/d (desalination capacity)
- Barka 2 IWPP: 703MW / 120,000 cm/d
- Rusail IPP: 184MW
- Manah IPP: 179MW
According to Saudi utility developer Acwa Power, the Barka 1 plant’s power and water purchase agreement extension is valued at $356m.
It includes extending the operation of the power plant for eight years and nine months, starting from 1 June 2024, and the water desalination plant for three years from 1 September 2024. When it began operations in 2003, the facility contributed 6% of Oman’s electricity and 24% of its desalinated water.
Nama PWP said “efficient utilisation of gas consumption will continue to improve” over the 2023-29 planning horizon.
Peak demand forecast
Peak demand in the MIS is expected to grow at an average of approximately 3.4% a year over the seven-year planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022.
In the DPS, peak demand is anticipated to grow 5% a year, from 612MW in 2022 to 837MW in 2029.
Oman has been implementing key projects to improve the efficiency of its electricity grids, addressing growing peak demand and intermittent renewable power.
In 2023, Oman Electricity Transmission Company completed works on the $966m, 400-kilovolt (kV) first phase of the North-South Interconnection project – known as Rabt – enabling Oman’s MIS to connect with the Duqm Power System.
The project is expected to stimulate the development of the Special Economic Zone at Duqm (Sezad) and the development of renewable energy projects in the Al-Wusta Governorate. The next phase to expand the Rabt project is expected by 2026.
Oman’s second direct link to the GCC regional electricity grid is also planned to come onstream the same year.
The 400kV Oman Direct Link project will extend the Gulf Cooperation Council Interconnection Authority’s (GCCIA) 400kV transmission network to enable direct interconnection with Oman.
According to energy consultancy firm Energoprojeckt, which is advising the GCCIA on this project, a new 400kV double circuit overhead line connection, with a total route length of 528 kilometres, will be constructed from the existing 400kV GCCIA Silaa substation in the UAE to the existing 400/220kV Ibri substation in Oman.
Oman’s first link with the GCCIA became operational in November 2011. It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.
Water sector
The sultanate’s water sector has been similarly buoyant. Contract awards for desalination and treatment capacity and the construction of water transmission pipelines are approaching record highs.
According to MEED Projects data, close to $1bn-worth of contracts are in the bid evaluation stage, including the estimated $100m package for the wastewater network facilities on Masirah Island, as well as several water pipeline, desalination and dam projects across the sultanate.
Oman’s Barka 5 independent water project (IWP) reached commercial operations in August, its owner and operator, Madrid-headquartered GS Inima, announced. Oman’s eighth IWP scheme has a design capacity of 100,000 cm/d.
The project, which uses reverse osmosis technology, will serve 800,000 people in the sultanate’s most populated areas: Muscat, Dakhiliyah and Batinah.
GS Inima, in a consortium with local contractor Sogex and Saudi Arabia’s Aljomaih, won the contract to develop another IWP in Oman, the 300,000 cm/d Ghubrah 3 IWP, in 2020. The project is expected to reach financial close soon.
Peak water demand in the sultanate’s MIS is expected to increase by an average of 2% annually, from 1,172,000 cm/d in 2022 to 1,387,000 cm/d in 2029.
A higher growth rate of 5% annually is expected in the sultanate’s Sharqiyah zone, and 7% is projected in Dhofar.
Other upcoming projects
In addition to Nama PWP’s plans, state-backed Petroleum Development Oman (PDO) is procuring renewable energy capacity to support its target of 30% of its power capacity coming from renewable sources by 2026 and 50% by 2030.
PDO floated a tender for two 100MW wind projects in April 2023. It is understood that PDO is in discussions with Abu Dhabi Future Energy Company (Masdar) for the contract to develop the Riyah-1 and Riyah-2 wind projects.
PDO has also appointed a team comprising Beijing-headquartered Power Construction Corporation of China (PowerChina) and its subsidiary, Huadong Engineering Corporation (HDEC), to undertake the engineering, procurement and construction (EPC) work for the two wind projects.
PDO plans to develop its second solar photovoltaic project near Saih Nihayda, next to Qarn Alam airport, in the northern region of Oman. The project is expected to come onstream late next year, nearly five years after its first 100MW Amin solar project began operating.
Exclusive from Meed
-
Egypt approves Russian nuclear financing amendment
4 February 2025
-
Abu Dhabi plans estimated 10GW data centre capacity
4 February 2025
-
UAE data centre policy highlights AI-energy nexus
4 February 2025
-
UAE government eyes federal data centre policy
3 February 2025
-
Saudi Arabia invites bids for 2GW battery IPPs
3 February 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt approves Russian nuclear financing amendment
4 February 2025
The Egyptian House of Representatives has approved a report, previously ratified by the North African nation's Energy & Environment Committee, that amends the government financing agreement between Egypt and Russia over the El-Dabaa nuclear power plant in Matrouh.
The agreement secures a government export loan from Moscow to support the construction of Egypt’s first nuclear power plant.
According to a local media report, the decree was reviewed by a joint committee that included members of the Energy & Environment Committee, as well as representatives from the Planning & Budget, Economic Affairs and Foreign Relations Committees.
The amendments to the financing agreement aim to "align the loan's terms with the project's implementation schedule".
The report did not disclose the nature of the financing amendment that has been approved.
Financing details
Egypt and Russia signed the initial inter-governmental agreement for the North African state’s first nuclear facility in November 2015.
MEED understands that the existing agreement entails an 85:15 project financing split between Russia and Egypt.
The project is expected to cost between $25bn and $30bn.
According to industry sources, the funds Russia is providing are payable over 22 years in 43 semi-annual installments, with the first installment due on 15 October 2029.
MEED understands Egypt can repay the loan in US dollars or Egyptian pounds, whichever suits the Russian party better, and that "a very affordable" 3% annual interest rate applies.
The power plant will be equipped with four Russian-designed, 1,200MW VVER reactor units.
When complete, the El-Dabaa nuclear power plant is expected to generate more than 10% of electricity production in Egypt.
The plant’s first reactor is scheduled to be operational in 2026.
Russia’s State Atomic Energy Corporation (Rosatom), the project’s main contractor, announced that it started the production of electrical components in Saint Petersburg for a reactor vessel for the plant in June 2022.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13360633/main.jpg -
Abu Dhabi plans estimated 10GW data centre capacity
4 February 2025
Abu Dhabi is planning to invest in data centres with a total combined IT load capacity equivalent to an estimated 10,000MW.
According to industry sources, the locations that are being considered are in Abu Dhabi's Dhafra region, previously known as the Western or Al-Gharbia region, including one close to the Barakah nuclear power plant.
In addition to the nuclear power plant, which has a total nameplate capacity of 5,600MW, Abu Dhabi's second utility-scale solar photovoltaic (PV) independent power project is located in Al-Dhafra.
Abu Dhabi National Energy Company (Taqa) is also procuring an open-cycle gas turbine (OCGT) plant to be located in the region. The Al-Dhafra OCGT plant is being tendered on a fast-track basis and is expected to have an installed capacity of 1,000MW-1,100MW.
State utility offtaker Emirates Water & Electricity Company and Abu Dhabi Future Energy Company (Masdar) have yet to disclose the locations for the gigawatt-scale solar PV and battery energy storage system (bess) plants that they are planning to develop as part of the UAE's national net-zero target and artificial intelligence (AI) strategy.
The project comprises 5,200MW solar PV and 19 gigawatt-hour (GWh) bess plants that are expected to supply 1,000MW of round-the-clock renewable power.
Experts have advised colocating data hyperscale centres, particularly those designed for training AI large-language models that have an electrical output similar to small towns or cities, with power generation sources.
This helps bypass complex and time-consuming grid connection upgrades and approvals processes and minimises energy waste.
Data centres designed for inferencing AI models, however, need to be built close to load centres or cities for improved latency.
"Lots of data centre project activity in Abu Dhabi at the moment," said a senior technical consultant, who also cautions there might be duplications in terms of these "concept projects".
Karen Young, senior research scholar at Columbia University’s Centre on Global Energy Policy, also observes the uptick in project activity, as well as in policies directly related to AI and data centres in the UAE.
"It's a lot to keep track of, and the new doubt that we may be able to do supercomputing with less power and investment, and cheaper inputs, makes the race for energy infrastructure and data centre placement slightly more risky," she tells MEED.
Related read: DeepSeek complicates regional data centre choices
"All the same, the UAE has made a strategic decision to lead the space and it changes the global landscape of where this advances and which countries have advantages to control it."
GCC data centre market
Over $10.6bn-worth of data centres, some catering to hyperscalers such as Amazon Web Services and Microsoft, are planned to be developed and built in the GCC states, according to the latest available data from regional projects tracker MEED Projects.
This is a conservative estimate, given potential investments such as the $5bn planned between US asset investment firm KKR and the UAE-based Gulf Data Hub.
It also excludes spending by government entities to develop AI capabilities in defence, security, healthcare and energy.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13360347/main1606.jpg -
UAE data centre policy highlights AI-energy nexus
4 February 2025
Commentary
Jennifer Aguinaldo
Energy & technology editorThe UAE National Team for Reviewing the Impact of Data Centres on the Energy Sector held its inaugural meeting on 3 February.
The UAE Ministry of Energy & Infrastructure (MoEI)-attached entity was formed to assess the impact of data centres on the domestic energy sector and to work on developing a federal policy aimed at regulating the operation of local data centres.
Sharif Al-Olama, undersecretary for energy and petroleum affairs at the MoEI, said the formation of the national team is part of the state's strategic efforts towards digital transformation and enhancing sustainability in the energy sector.
This development follows significant initiatives aligned with the UAE's national artificial intelligence (AI) strategy.
For instance, Emirates Water & Electricity Company and Abu Dhabi Future Energy Company (Masdar) announced the $6bn "gigawatt-scale" solar photovoltaic (PV) and battery energy storage system (bess) project in Abu Dhabi in mid-January.
The project, comprising 5,200MW of solar PV and a 19 gigawatt-hour (GWh) bess plant, is expected to provide 1,000MW of round-the-clock, baseload renewable power.
The UAE leadership has said this project will help advance AI and other emerging technologies while contributing to its 2050 net-zero target.
Advanced AI models require the construction of hyperscale – large-capacity and low-latency – data centres, which consume large amounts of electricity, impacting consumption, supply, planning and carbon emissions.
A federal policy could help streamline the entire ecosystem and mobilise plans to ensure no single point of failure once all the planned data centres start operating.
This move comes a few months after the UAE cabinet approved the state's international AI policy in October, which focuses on advancement, cooperation, community, ethics, sustainability and security.
In addition to helping shape future standards and guidelines in AI diffusion, the UAE foreign AI policy advocates "transparency and built-in checkpoints within AI tools, enabling governments to enforce ethical standards and implement accountability measures".
Investors and data centre operators will be watching these evolving policies with great interest to ensure compliance, and to see what impact they might have on capital and operating expenses, if any.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13357411/main1654.jpg -
UAE government eyes federal data centre policy
3 February 2025
A UAE national team has been formed to assess the impact of data centres on the domestic energy sector and work on developing a federal policy aimed at regulating the operation of local data centres.
The UAE Ministry of Energy and Infrastructure (MoEI)-attached national team held its first meeting in Dubai, Emirates News Agency (Wam) reported on 3 February.
At its inaugural meeting, the National Team for Reviewing the Impact of Data Centres on the Energy Sector, explored the development of data centres in the UAE and their influence on the local energy sector.
The report added: "It also highlighted the challenges facing data centres, ways to make them more sustainable, and the importance of adopting global best practices to ensure efficient operation of these centres".
Related read: AI chip restriction may slow down GCC data centre boom
The team is tasked with a"nalysing and reviewing the impact of data centres on energy demand, evaluating the local market and projected economic return for this key sector, identifying all data centres in the country and classifying them according to specific standards".
The team will also conduct a geographical study of the distribution of current and future data centres to ensure optimal infrastructure distribution, perform benchmark comparisons to review global best practices in data centres, and work on developing a federal policy aimed at regulating the operation of local data centres.
Sharif Al-Olama, Undersecretary for Energy and Petroleum Affairs at MoEI and Saif Ghubash, assistant undersecretary for Petroleum, Gas, and Mineral Resources at MoEI participated in the meeting, along with key team members from various ministries including the Ministry of Industry and Advanced Technology, the Ministry of Climate Change and Environment, the Telecommunications and Digital Government Regulatory Authority, the Artificial Intelligence, Digital Economy, and Remote Work Applications Office, among others.
Related read: AI underpins 5GW Abu Dhabi solar project
During the meeting, Al-Olama underscored the importance of collaboration among member entities to achieve the team's objectives, including adopting innovative solutions to reduce energy consumption and enhancing the operational efficiency of data centres.
He added that the formation of the National Team is part of the country's strategic directions towards digital transformation and enhancing sustainability in the energy sector.
He emphasised the need to develop innovative solutions to ensure a balance between the demands of technological development and the sustainability of energy resources in alignment with national goals.
Al-Olama also highlighted the importance of establishing a comprehensive framework that includes analytical studies and clear recommendations based on accurate data, which will contribute to making strategic decisions capable of achieving the country's energy goals, particularly in clean and renewable energy.
Close to $2bn worth of data centre projects are under construction in the UAE, according to latest available MEED Projects data.
Over $10.6bn-worth of data centres, some catering to hyperscalers such as Amazon Web Services and Microsoft, are planned to be developed and built across the GCC states.
Photo credit: Wam
https://image.digitalinsightresearch.in/uploads/NewsArticle/13357025/main.jpg -
Saudi Arabia invites bids for 2GW battery IPPs
3 February 2025
Register for MEED's 14-day trial access
Principal buyer Saudi Power Procurement Company (SPPC) has invited prequalified firms to bid for the contracts to develop the first phase of independent battery energy storage system (bess) projects in Saudi Arabia.
The group one bess – also called independent storage provider (ISP) – projects will be developed using a build, own and operate (BOO) model.
They comprise the following schemes with a total combined capacity of 2,000MW, which equates to about four hours or 8,000 megawatt-hours (MWh) of storage:
- Al-Muwyah bess ISP: 500MW (Mecca)
- Haden bess ISP: 500MW (Mecca)
- Al-Khushaybi bess ISP: 500MW (Qassim)
- Al-Kahafa bess ISP: 500MW (Hail)
MEED understands a bidders conference is set for 17 February, to be followed by site visits.
The principal buyer expects to receive the letters of intention by April and the proposals by 2 June.
The following 21 companies have been prequalified to bid for the contracts as managing or technical partners:
- Abu Dhabi Future Energy Company (Masdar, UAE)
- Abu Dhabi National Energy Company (Taqa, UAE)
- Acwa Power (local)
- Akaysha Energy (Australia)
- China Energy Overseas Investment Company (CEECOIC, China)
- China Power Engineering Consulting Group International Engineering (China)
- China Southern Power Grid International (HK) Company (CSGIHK)
- Cox Energy (Spain)
- EDF (France)
- Envision Energy (China)
- FRV-X Renewable (Spain)
- International Power (Engie, France)
- Jera Nex (Japan)
- Jinko Power (Hong Kong)
- Korea Electric Power Corporation (Kepco, South Korea)
- Marubeni Corporation (Japan)
- Pro-Power Investment (China)
- Samsung C&T Corporation (South Korea)
- SPIC Huanghe Hydropower Development Company (China)
- TotalEnergies Renewables (France)
- X-Elio Energy
The following firms may bid as technical partners:
- Al-Gihaz Holding Company (local)
- Al-Jomaih Energy & Water Company (local)
- Alfanar Company (local)
- FAS Energy (local)
- GCL Intelligent Energy (Suzhou, China)
- Gulf Energy Development Public Company (Thailand)
- Nesma Renewable Energy (local)
- Posco International Corporation (South Korea)
- Power Construction Corporation of China (PowerChina)
- Saudi Electricity Company (local)
- Shell Overseas Investment (UK)
- Sumitomo Corporation (Japan)
The successful bidders will hold 100% equity in the special purpose vehicle (SPV) set up to develop and operate each ISP.
The SPVs will enter into a 15-year storage services agreement with the principal buyer.
According to SPPC, the energy storage programme will enable the kingdom’s energy mix to contain 50% renewable energy by 2030 while enhancing the reliability and resilience of the electric power system.
MEED reported in May last year that SPPC was several months away from seeking developers’ interest in the contract to develop and operate the 2,000MW first phase of an energy storage system catering to the kingdom’s electricity grid.
It is understood that SPPC plans to procure up to 10,000MW of bess capacity by 2030.
The planned bess facilities are to be built near demand centres. As more renewable energy enters the electricity production mix, they will boost the grid’s spinning reserves.
Bess comprises rechargeable batteries that can store and discharge energy from various sources when needed. It is one of the key solutions being considered to address the intermittency of renewable energy sources.
US/India-based Synergy Consulting is advising SPPC on the energy storage capacity procurement programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13356657/main4004.jpg