Dubai focuses on infrastructure
24 December 2024

It feels like Dubai has never had it so good. Economic growth remains robust, and as the outlook for other countries proves to be shaky, the emirate’s lifestyle proposition is attracting wealthy residents from around the world.
As the city grows, it is becoming increasingly apparent that its infrastructure is strained and needs upgrading. An examination of the construction contract awards data over the past 10 years suggests why. After reaching a peak in 2017, the value of construction contracts in Dubai slumped to a low of less than $10bn a year in 2020 and 2021 before recovering in 2022 and growing strongly in 2023.
Those new projects awarded during the recovery phase are still under construction and have not yet positively impacted Dubai’s infrastructure offering.
Dubai budget
As these pressures build, Dubai announced its budget for 2025 on 29 October 2024 with a 9% increase in government spending, and an extra $1.6bn for construction and infrastructure compared to the approved budget for 2024.
Of the AED86.26bn ($23.5bn) of planned spending, 46%, or AED39bn ($10.6bn), will be allocated for construction and infrastructure schemes. “These projects encompass roads, tunnels, bridges, transportation systems, sewage stations, parks, renewable energy facilities and the rainwater drainage network development plan,” the emirate’s finance department said in a statement.
“This also includes the recently announced Al-Maktoum airport development project and other initiatives supporting quality of life and promoting smart and sustainable transportation strategies in Dubai.”
The 2024 budget had AED33.2bn of spending allocated for construction and infrastructure.
Population boom
In the long term, the driver for infrastructure spending is population growth. The Dubai 2040 Urban Master Plan expects Dubai’s population to reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is forecast to rise from 4.5 million in 2020 to 7.8 million in 2040.
In the short term, increased construction spending will also help the emirate overcome some of its most pressing infrastructure challenges. Traffic has developed into a major issue in Dubai and, over the past year, the Roads & Transport Authority (RTA) has pressed ahead with a series of road projects aimed at alleviating congestion. The most recent road project to be announced is the AED696m upgrade to the Trade Centre roundabout.
In early November, the RTA outlined plans to tackle traffic with improved urban mobility and infrastructure throughout the emirate. The estimated AED16bn ($4.3bn) 2024-27 Main Roads Development Plan comprises 22 projects across Dubai’s road network. It includes the construction of new roads and bridges at several key locations across Dubai.
The most immediate is the Al-Mostaqbal Road project, which, according to the official statement, will be awarded by the end of 2024. The project includes the construction of bridges and tunnels totalling 6.2 kilometres (km), increasing the road capacity from 9,000 to 12,000 vehicles an hour.
The Latifa Bint Hamdan Street development is set to commence in 2025. This project covers 12.2km of road network from its intersection with Al-Khail Road to Emirates Road. The project also includes 8.1km of bridges and will add capacity for about 16,000 vehicles an hour in both directions.
The Meydan Road development project includes 10.6km of roads, 3.3km of bridges and three tunnels totalling 1.5km. The project is expected to add capacity for 22,000 vehicles an hour in both directions and reduce the travel time from Umm Suqeim Street to the extension of Meydan Street to just four minutes.
After reaching a peak in 2017, the value of construction contracts in Dubai slumped to a low of less than $10bn a year in 2020 and 2021 before recovering in 2022 and growing strongly in 2023
A project encompassing Umm Suqeim and Al-Qudra streets covers a 16km stretch from the Jumeirah Street intersection to Emirates Road. The project includes the development of four intersections, including 2.5km of bridges and 2km of tunnels. It will increase road capacity from 8,400 to 12,600 vehicles an hour.
The Al-Fay Street development project will extend from Al-Khail Road at its intersection with Sheikh Mohammed Bin Zayed Road, passing through Sheikh Zayed Bin Hamdan Al-Nahyan Street up to Emirates Road. It includes 12.9km of roads with five intersections and 13.5km of bridges. The project will add capacity for about 64,400 vehicles an hour.
The Al-Safa Street development project will stretch from Sheikh Zayed Road to Al-Wasl Road. The project includes the construction of 2.1km of tunnels, including a two-lane tunnel providing direct access from Al-Safa Street to the City Walk residential development, as well as 650 metres of bridges. The project will increase the road capacity from 6,800 to 9,400 vehicles an hour.
The RTA also plans to expand the Dubai Tram network and is carrying out a study on deploying trackless tram systems at eight locations across Dubai. The self-driving tram system will operate on virtual tracks, using camera-guided painted lines on dedicated lanes. The electricity-powered system will have three carriages with a capacity of 300 passengers and an operational speed of 25 to 60 kilometres an hour.
Other plans include extending Dubai’s dedicated bus and taxi lanes to 20km and expanding the cycle track network.
A new metro line is also planned. In October, contracting consortiums submitted bids for the contract to complete a new Blue Line. Revised offers were submitted in late November, with the lowest-priced base offer coming in at AED19.8bn. The project was given a budget of AED18bn when approved by the government in late 2023.
Airport plans
Another infrastructure concern is maintaining Dubai’s status as a global aviation hub. Dubai International airport is operating at close to capacity, and with no room to add to its two existing runways, a major new airport project is planned at Al-Maktoum International airport. Designs for that project, valued at $35bn, were approved by the government in April and all operations at Dubai International are scheduled to move there within 10 years. Tendering for major construction contracts is expected to start in 2025.
Drainage is also a concern, with widespread flooding in April this year exposing the shortcomings of the emirate’s infrastructure. In June, the government approved a AED30bn project known as Tasreef, which will enhance the capacity of Dubai’s rainwater drainage system by 700%, covering all areas of the emirate.
The sewage system will also be upgraded with the $22bn Dubai Strategic Sewerage Tunnels project, which will be delivered as a public-private partnership.
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg