Lowest bidder changes for Dubai Metro Blue Line
22 November 2024
Register for MEED's 14-day trial access
The team of Beijing-based China State Construction Engineering Corporation (CSCEC) and France’s Alstom has emerged as the low bidder for the Blue Line extension to the Dubai Metro network after revised bids were submitted on 21 November.
The team submitted an offer of AED19.8bn after the project client, Dubai’s Roads & Transport Authority (RTA), asked bidders to submit proposals with alternatives to reduce the price.
The consortium’s price is nearly 18% lower than its original base offer of AED24.1bn submitted on 8 October.
The second-lowest price on 21 November was the AED20.3bn bid submitted by a consortium of India’s Larsen & Toubro, China’s Powerchina, the local Wade Adams and Hitachi.
The third-lowest bid was an offer of AED20.6bn submitted by a consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).
The RTA had received another round of updated offers a week earlier on 14 November. That time the Limak/Mapa/CRCC team submitted the lowest bid with a price of AED21.7bn.
For the first round of revised offers on 7 November, the group of China Tiesiju Civil Engineering Group (CTCE), Egypt’s Arab Contractors, the local Binladin Contracting Group and Spain’s CAF submitted the lowest-priced revised base offer of AED22.2bn.
The CTCE/Arab Contractors/Binladin/CAF group submitted the lowest base offer when the bids were first submitted on 6 October.
The design-and-build contractor for the Blue Line will be responsible for all civil works, electromechanical works, rolling stock and rail systems. After completing the project, the contractor will assist with maintenance and operations for an initial three-year period.
The Blue Line will connect the existing Red and Green lines. It will have a total length of 30 kilometres (km), 15.5km underground and 14.5km above ground.
The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.
The scope of the contract also includes the supply of 28 driverless trains, the construction of a depot to accommodate up to 60 trains and the construction of all associated roads, facilities and utility diversion works.
The detailed scope of work for the project includes:
- Civil works, including detailed design and construction of architectural and structural components (including viaducts, tunnels and stations)
- Design and execution of electromechanical works
- Design, procurement and delivery of operation and control systems for rail, stations and facilities
- Design, manufacturing and supply of rolling stock
UAE Vice President, Prime Minister and Ruler of Dubai, Sheikh Mohammed Bin Rashid Al-Maktoum, approved the Blue Line extension project last year. In a post on social media network X, formerly Twitter, he said the project will cost AED18bn ($4.9bn) and will have a length of 30km, half of which will be underground.
He added that the extensions will transport 320,000 passengers a day and serve a population of about 1 million people living in areas such as Festival City, International City, Rashidiya, Warqa, Mirdif, Silicon Oasis and Academic City.
Exclusive from Meed
-
Saudi drilling firm raises acquisition offer for Dubai rival
16 September 2025
-
Oman tenders Rusayl power cable project
16 September 2025
-
QatarEnergy awards contract for 2GW Dukhan solar plant
16 September 2025
-
Saudi firm awards $121m of housing construction contracts
16 September 2025
-
Oman LNG shortlists bidders for fourth liquefaction train
16 September 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Saudi drilling firm raises acquisition offer for Dubai rival
16 September 2025
Saudi Arabia-based ADES International Holding has increased its offer to buy Dubai-based, Oslo-listed rival Shelf Drilling to 18.50 Norwegian Krone ($1.88) per share, representing a 6% increase in the acquisition’s enterprise value.
The offer was revised from an earlier deal of $1.42 per share or a total of $379.33m.
ADES International Holding, a subsidiary of ADES Holding Company, signed a transaction agreement to acquire all issued and outstanding shares of Shelf Drilling through a cash merger, with ADES International Cayman (BidCo) also participating in the proposed merger.
According to a joint statement, irrevocable commitments have now been provided by additional shareholders, including China Merchants, Anchorage Capital Group and Magallanes Value Investors, which, combined with ADES’ 17.9% stake in Shelf Drilling, represent 53.4% of the outstanding shares in the company.
ADES International Holding raised its offer for Shelf Drilling after reassessing the company’s current market performance and revising its estimated annual cost synergies upwards by $10m, bringing the total to $50m-$60m.
All other terms of the merger remain unchanged, along with the transaction timetable, with closing expected to occur in the last quarter of the year.
Shelf Drilling is incorporated under the laws of the Cayman Islands, with its corporate headquarters in Dubai.
In April this year, ADES International Holding secured a 10-year extension for one of its standard offshore jack-up rigs from Saudi Aramco, valued at approximately $290m.
The contract for the offshore jack-up marks the re-entry of ADES International Holding into the Saudi offshore oil and gas market. The rig was among six jack-ups whose charters were suspended by Aramco last April.
ADES International Holding has secured deployments for three of those jack-ups in Qatar, Thailand and Egypt, while the fourth was recently redeployed to Thailand.
ADES International Holding also said it has increased its footprint since the start of 2025 by securing an offshore drilling job off the coast of Nigeria, marking its entry into West Africa.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14676037/main0952.jpg -
Oman tenders Rusayl power cable project
16 September 2025
State-owned Oman Electricity Transmission Company (OETC) has opened bidding for the construction of the cable connection from the Rusayl power plant (GT-5 & GT-6) to the Rusayl industrial grid station.
The tender is open to local companies with tender board registration and valid commercial registration, the authority said.
Bids must be submitted electronically, with hard copies of the bid bond and other documents delivered to OETC’s head office in Muscat.
The last date to obtain documents is 23 September, with bids due by 7 October.
The new cable tender forms part of OETC’s strategy to expand transmission in line with industrial growth. The Rusayl power plant, located near Muscat, is one of Oman’s key natural gas-fired generation facilities and supplies electricity to the Main Interconnected System (MIS), the country’s largest grid.
The adjoining Rusayl Industrial City is a major manufacturing hub hosting companies across chemicals, textiles, electrical materials and food production, which has driven steady growth in power demand.
OETC is undertaking several major transmission projects to reinforce the MIS. These include the construction of new 132kV grid stations, network reinforcements around Muscat and the Masirah Island interconnection, which is valued at about RO72m ($187m).
Local firm Bahwan Engineering won the main contract for this project and started construction earlier this year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14675720/main.jpg -
QatarEnergy awards contract for 2GW Dukhan solar plant
16 September 2025
State-owned petroleum firm QatarEnergy has signed an agreement with South Korea’s Samsung C&T to build a 2,000MW solar power plant in Dukhan, about 80 kilometres west of Doha.
The plant will double Qatar’s solar generation capacity, supplying up to 30% of Qatar’s total peak electricity demand once complete. It will use a solar tracker system and inverters, capable of operating in high temperatures, to maximise efficiency.
The project will be delivered in two phases and is expected to be fully operational by mid-2029.
The first phase of the Dukhan solar plant will deliver 1,000MW of power to the Kahramaa grid by the end of 2028.
The agreement was signed by Saad Sherida Al-Kaabi, minister of state for energy affairs and QatarEnergy CEO, and Sechul Oh, president and CEO of Samsung C&T.
Senior officials from Kahramaa and executives from both companies also attended the ceremony.
Under QatarEnergy’s Sustainability Strategy, the country plans to generate more than 4,000MW of renewable energy by 2030.
Qatar’s first utility-scale solar photovoltaic (PV) facility, the 800MW Al-Kharsaah solar independent power producer project, has been operational since 2022.
In August 2022, Samsung C&T won contracts for two other solar PV plants with a total combined capacity of 875MW.
One of the solar plants, which has a capacity of 458MW, is located in Ras Laffan. The other plant is located in Mesaieed and will have a capacity of 417MW.
Construction work on both projects was completed earlier this year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14674775/main.jpg -
Saudi firm awards $121m of housing construction contracts
16 September 2025
Saudi Arabian real estate developer Al-Majdiah has awarded construction contracts worth SR454m ($121m) for housing projects in Riyadh and Jeddah.
The contracts were awarded to the local firm Tatweej Contracting.
The two projects are part of Al-Majdiah’s portfolio in collaboration with the state-backed National Housing Company (NHC).
In an official statement published on the Saudi stock exchange Tadawul, Al-Majdiah said the contract value for the Adeem Al-Fursan project in Riyadh is SR298m ($80m).
The project comprises the construction of 540 villas and townhouses.
The Al-Fursan development in northeast Riyadh spans over 35 million square metres (sq m) and includes over 50,000 residential units.
The contract value for the Khayala 1 project in Jeddah is SR155m ($41m). The project includes the construction of 528 residential units.
The Khayala development is located in north Jeddah and spans nearly 1.6 million sq m. It includes 3,680 residential units.
The contracts have a scheduled completion period of 36 months.
UK-based analytics firm GlobalData expects the construction industry in Saudi Arabia to grow by 4% in real terms in 2025, before recording an annual average growth of 5.4% from 2026 to 2029.
The industry’s output in 2025 will be supported by allocations as part of the kingdom’s 2025 budget, which includes a total expenditure of SR1.3tn ($342.7bn) for 2025.
The industry’s output over the remainder of the forecast period will be supported by investments in transport, electricity, housing and water infrastructure projects.
The residential construction sector is expected to grow by 3.8% in real terms in 2025 before recording an annual average growth rate of 6.4% over the remainder of the forecast period, supported by public and private sector investments in the residential sector to address the national housing deficit.
https://image.digitalinsightresearch.in/uploads/NewsArticle/14674464/main.jpg -
Oman LNG shortlists bidders for fourth liquefaction train
16 September 2025
Register for MEED’s 14-day trial access
Oman LNG has shortlisted contractors to bid for engineering, procurement and construction (EPC) works for a new processing train at its Qalhat liquefied natural gas (LNG) production complex in Sur.
The LNG train will be the fourth at the Qalhat complex, located in the sultanate’s South Al-Sharqiyah governorate, Oman LNG announced last July. The new train will have an output capacity of 3.8 million tonnes a year (t/y) and is expected to be commissioned in 2029, raising Oman LNG’s total production capacity to 15.2 million t/y.
According to sources, Oman LNG has issued the main EPC tender for the fourth LNG train project and invited the following contractors to submit bids:
- Chiyoda (Japan) / Samsung C&T (South Korea)
- JGC Corporation (Japan)
- Saipem (Italy) / Daewoo Engineering & Construction (South Korea)
MEED previously reported that Oman LNG hosted site visits in June for prequalified contractors, according to sources.
Oman LNG has performed the preliminary engineering study for the planned fourth LNG train. It awarded US-headquartered KBR a contract to execute front-end engineering and design (feed) works on the project in November.
Separately, in June, Oman LNG awarded Japan-based Kanadevia Corporation a contract to perform pre-feed work for a pilot methanation plant, and a detailed concept study for future commercial scaling of the facility.
The proposed facility is expected to produce 18,000 normal cubic metres of e-methane an hour.
The pilot plant will comprise three components: a seawater desalination unit, equipment for producing hydrogen via water electrolysis and a methanation system that combines hydrogen with captured carbon dioxide to produce e-methane.
The agreement follows a memorandum of understanding that Oman and Japan signed in March 2024, covering collaboration in hydrogen, fuel ammonia and carbon recycling.
Oman LNG operations
Oman LNG is a joint venture of the sultanate’s Ministry of Energy & Minerals, which holds the majority 51% stake, and foreign stakeholders.
The remaining 49% is held by UK-based Shell (30%); France’s TotalEnergies (5.54%); South Korea’s Korea LNG (5%); Japan’s Mitsubishi Corporation (2.77%); Japan’s Mitsui & Company (2.77%); Thailand’s PTTEP, following the acquisition of Portuguese firm Partex (2%); and Japan’s Itochu Corporation (0.92%).
Oman LNG presently operates three trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Following debottlenecking, total production capacity increased to approximately 11.4 million t/y.
Oman LNG secured $2bn-worth of project financing in 1997 to set up its first LNG export terminal in the sultanate, the Qalhat LNG terminal, which was commissioned in 2000.
On 1 September 2013, Qalhat LNG was integrated with Oman LNG to form a single entity.
The terminal exports gas produced by state oil and gas producer Petroleum Development Oman from its central Oman gas field complex. Oman LNG’s customers are mainly based in Asia, although the company has been expanding its client base outside the continent in recent months.
In April, Oman LNG announced the start of turnaround activities at the third LNG processing train, which has an output capacity of 3.3 million t/y. The third train commenced operations in 2006 and primarily processes gas produced at the Saih Nihayda field in central Oman.
ALSO READ: TotalEnergies studies expansion of Marsa LNG project in Oman
https://image.digitalinsightresearch.in/uploads/NewsArticle/14674434/main0940.jpg