UAE construction consolidates

10 October 2024

 

With an abundance of tower cranes on the horizon, labour buses and ready-mix concrete trucks clogging streets, it is evident that construction in the UAE is in the midst of yet another boom. 

While that may appear to be business as usual for a market that has become known around the world for delivering daring projects, behind the scenes, there have been sweeping changes that will affect how the market operates for the coming decades. 

In Dubai and Abu Dhabi, major property developers that the government owns or controls have been reshuffled and consolidated. At the same time, the government has taken control of major contracting companies to help it deliver on its project ambitions. 

In Dubai, the most significant move came in March this year when Sheikh Mohammed Bin Rashid Al-Maktoum, the Prime Minister and Ruler of Dubai, announced the incorporation of local real estate bodies Nakheel and Meydan into Dubai Holding Group. Under the directive, the board of directors of both Nakheel and Meydan will be abolished. 

The consolidated Dubai Holding Real Estate (DHRE) entity is a major player in Dubai’s construction market. By 4 October 2024, the company and its subsidiaries accounted for 9% of construction contract awards in Dubai. Importantly, the percentage share has been increasing over time. The entities – although not merged at the time – represented 6.5% of contract awards in 2019.

The largest contract signed by a DHRE entity this year was the $490m contract to construct the 75-storey Como Residences tower on the Palm Jumeirah awarded to local contractor Alec by Nakheel.

Master developer

While the combined entity will remain important for contract awards, its significance is even greater when its role as a master developer is considered. Dubai Holding had a large land bank, and the addition of Nakheel, which also has a vast portfolio of lands to develop, has created an entity that will shape the future development of Dubai for the coming decades.

One of the Nakheel projects that will move forward in the next few years is the development of Palm Jebel Ali. In late August, Nakheel awarded a $220m contract to complete the reclamation works for the artificial island to Belgium’s Jan de Nul.

Abu Dhabi activity

Abu Dhabi has also been consolidating its real estate companies. In September, Aldar Properties and Mubadala Investment Company signed a partnership agreement to establish several joint ventures to own and manage assets in Abu Dhabi.

The partnership will be owned 60:40 by Aldar and Mubadala, respectively. It includes a $2.45bn retail platform, $816bn-worth of real estate assets in Masdar City, two undeveloped islands off Saadiyat Island and Yas Island, and an industrial logistics park.

Earlier, in February this year, Q Holding completed a transaction with ADQ Real Estate and Hospitality IHC Capital Holding to acquire control over 100% of the share capital for companies including Modon Properties and Abu Dhabi National Exhibitions Company (Adnec). The merged company was rebranded as Modon Holding and is an ADQ portfolio company.

Abu Dhabi has a long track record of mergers and acquisitions with its government-related property development companies. In 2013, it merged Aldar properties with Sorouh Real Estate, two of the emirate’s largest property developers at the time. 

Like in Dubai, while the entities that make up these combined development bodies have been responsible for a significant share of contract awards in Abu Dhabi and will continue to do so in the future, their real importance is shown when considering their role as master developers. These consolidated players have vast land banks to develop and will help shape property development in the capital.

Fewer customers

For contractors, the consolidation of leading real estate players reduces the number of potential customers active in the market. Further complicating the matter is the growing importance of government-controlled contracting entities, which some contractors fear will mean fewer opportunities for privately owned contracting companies. 

In Dubai, the Investment Corporation of Dubai owns Alec. The contractor has won contracts for several key projects in recent years, including the recently awarded Como Tower. It has also worked extensively at Dubai International airport over the past 15 years. It is widely expected to play a leading role in the construction of the recently reinvigorated $35bn Al-Maktoum International airport project. 

The contracting landscape is more complex in Abu Dhabi. In early October, ADQ acquired a 49% stake in Alpha Dhabi Construction Holding, the construction subsidiary of local investment company Alpha Dhabi Holding (ADH). In 2022, ADH increased its stake in Aldar Properties and became the single largest shareholder, then becoming the real estate developer’s parent company. ADQ also has NMDC as a portfolio company. NMDC is a dredging and marine works contractor with capabilities in the construction and energy sectors. 

These contracting companies already command a dominant position in the market, and their common ownership structures with Abu Dhabi’s leading project clients will effectively guarantee that this trend will continue into the future. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12687275/main.gif
Colin Foreman
Related Articles
  • Dubai Municipality seeks Tasreef partner

    18 October 2024

    Dubai Municipality has issued a tender notice for a delivery partner to develop and implement a model tailored to the needs of the Tasreef programme, Dubai's planned AED30bn ($8.16bn) rainwater drainage network project.

    MEED understands the request for proposals targets technical and engineering advisory companies.

    Dubai Municipality expects to receive bids by 7 November, Fahad Al-Awadhi, director of drainage system and recycled water projects department, Dubai Municipality, said in a recent social media post.

    According to Al-Awadhi, the Tasreef  programme consists of three streamlines to enhance the effectiveness of Dubai's stormwater system:

    • Improvement of infiltration and sustainable drainage systems (Suds) and AI applications
    • Upgrade of stormwater systems in Deira, Bur Dubai and Jebel Ali
    • Proposed stormwater tunnels in Deira and Bur Dubai, as well as link tunnels in Jebel Ali

    In addition, the Tasreef programme will address storm event management, including raising awareness about storm impacts, implementing proactive risk control measures, developing marketing and procurement strategies, and establishing communication plans. 

    Al-Awadhi added: "The proposed stormwater tunnels, links and terminal pump stations aim to enhance the stormwater network’s capacity by 700% to handle up to 65 millimetres of rainfall per day. This program represents the largest rainwater collection project in a single system within the region."

    An early study is under way for Tasreef, which Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, approved in June, MEED reported in August

    A source familiar with the project said that Dubai Municipality is inclined to consider a public-private partnership (PPP) procurement model for the project.

    Sheikh Mohammed's approval of Tasreef came two months after a storm in April inundated Dubai, causing widespread flooding and damage to infrastructure and property in certain areas.

    The project will raise the emirate-wide drainage network’s capacity to more than 20 million cubic metres of water a day. It is envisaged to meet Dubai's needs for the next 100 years.

    The project is a continuation of drainage projects launched by Dubai in 2019, covering the Expo Dubai area, Al-Maktoum International Airport City and Jebel Ali.

    The rainwater drainage capacity through tunnels will reach 20 million cubic metres a day, with a flow capacity of 230 cubic metres a second.

    According to data from regional projects tracker MEED Projects, the Dubai Municipality Deep Tunnel Storm Water System (DTSWS) was first announced in 2014.

    It has several components, and the first two packages covering Jebel Ali were awarded between 2017 and 2018 and completed in 2022.

    The remaining packages of the master plan were on hold before the government's announcement on 24 June.

    The DTSWS project is separate from the Dubai Strategic Sewage Tunnels project, which is being developed under a PPP contracting model.  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12753886/main.jpg
    Jennifer Aguinaldo
  • Saudi Arabia picks Ras Mohaisen preferred bidder

    18 October 2024

    A team comprising the local firms Acwa Power, Haji Abdullah Alireza & Partners Company and AlKifah Holding has emerged as the preferred bidder for a contract to develop the Ras Mohaisen independent water project (IWP) in Saudi Arabia.

    The state water offtaker received two bids for the contract in April this year.

    The only other company that submitted a proposal for the contract, Spain’s Acciona, is the reserved bidder, according to Saudi Water Partnership Company (SWPC).

    The Ras Mohaisen IWP will have the capacity to treat 300,000 cubic metres of seawater a day (cm/d) using reverse osmosis technology.

    It will also include storage tanks with a capacity of 600,000 cubic metres, equivalent to two operating days, and an electrical substation.

    The project is expected to reach commercial operation by the second quarter of 2028.

    It is initially expected that the SWRO plant will reach commercial operation by the third quarter of 2026.

    Ras Mohaisen is about 300 kilometres south of Mecca, on the Red Sea coast in Saudi Arabia’s Western Region.

    SWPC has appointed Netherlands-headquartered KPMG as the financial adviser, with UK-based Eversheds Sutherland acting as the legal adviser for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12753083/main.gif
    Jennifer Aguinaldo
  • Chinese and Saudi partners set up Hithium Manat

    17 October 2024

    Register for MEED's 14-day trial access 

    Chinese energy storage solutions firm Hithium Energy Storage Technology Company (Hithium) and the local Nabilah AlTunisi have formed a joint venture that will manufacture battery energy storage systems (bess) in Saudi Arabia.

    The joint venture is called Hithium Manat. The planned manufacturing facility has an annual production capacity target of 5 gigawatt-hours (GWh), according to an official statement.

    Hithium launched energy storage solutions designed for the region's harsh environment during a solar and storage conference held in Riyadh.

    According to Hithium, "These systems feature advanced sandstorm protection and robust high and low-temperature designs, supporting ultra-long discharge cycles of 12+ hours."

    It added that the new product line is "customised to meet the unique demands of the Middle East and Africa region".

    Nabilah AlTunisi is the founder and owner of Hithium Manat's local partner.

    "This strategic alliance will not only provide access to world-class energy storage technology but also generate local employment opportunities, stimulate technological innovation and actively contribute to realising the kingdom's Vision 2030 objectives," AlTunisi said.

    Battery energy storage market

    In August, National Grid Saudi Arabia, a subsidiary of state utility Saudi Electricity Company, awarded the engineering, procurement and construction (EPC) contracts for three energy storage systems to Riyadh-based investment group Algihaz Holding. The estimated $800m projects are located in Najran, Madaya and Khamis Mushait.

    National Grid also recently tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW across the kingdom.

    The planned facilities, each with a capacity of 500MW or roughly 2,000 megawatt-hours, are located in or within proximity of the following key cities and load centres:

    • Riyadh
    • Qaisumah
    • Dawadmi
    • Al-Jouf
    • Rabigh

    Every utility in the region is procuring or planning to procure bess capacity in light of growing intermittent renewable power in their grids. 

    The overall capacity of deployed bess globally is expected to reach 127GW by 2027, up from an estimated cumulative deployment of 36.7GW at the end of 2023, a GlobalData report issued in June said.

    The report cited Chinese companies BYD and CATL and South Korean companies LG Energy Solutions and Samsung SDI among the top battery technology providers globally.

    Related read: Battery storage gains foothold

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742375/main.jpg
    Jennifer Aguinaldo
  • Kahramaa invites Ras Laffan substation bids

    17 October 2024

    Qatar state utility General Electricity & Water Corporation (Kahramaa) has tendered a contract to upgrade the Ras Laffan C substation.

    The scope of work covers the upgrade of existing 220-kilovolt (kV) and 400kV substations and the addition of 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.

    Kahramaa issued the tender on 15 October and expects to receive bids by 28 November.

    The project bid bond is valued at QR1.5m ($410,000).

    Separately, Kahramaa invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.

    Kahramaa expects to receive bids for this contract, with a bid bond of QR3m, by 14 November.

    Kahramaa is expanding its power generation capacity. Negotiations are under way with the sole bidder led by Japan's Sumitomo Corporation for a contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day.

    Earlier this month, Qatar Electricity & Water Company announced plans to develop a 500MW peak power unit in Qatar's Ras Abu Fontas area.

    Construction is also under way for two solar farms with a total combined capacity of 875MW in Mesaieed and Ras Laffan.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742343/main.jpg
    Jennifer Aguinaldo
  • Neom starts Tabuk highway prequalifications

    17 October 2024

     

    Saudi Arabian gigaproject developer Neom expects firms to submit their prequalification applications for a project to build a mountain road near Tabuk later this month.

    The 11.5-kilometre (km) Tabuk mountain road project comprises a 4km tunnel and 7.5km dualisation of an existing road, according to an industry source.

    Neom expects to receive statements of qualifications from interested engineering, procurement and construction contractors by 29 October.

    The tender proceedings for Neom's transport infrastructure projects are gathering momentum.

    Neom received expressions of interest for a contract to build a coastal highway and infrastructure project catering to the Magna development on the Gulf of Aqaba on 15 October.

    The project, called Magna Infrastructure Packages, is split into three. Package one is 13km, package two is 42km and package three is 41km. The packages cater to the development’s north, central and south areas.

    The design-and-build project covers utilities for water, power, mobility, sewer, buildings and highways, in addition to the coastal highway. The project is expected to be completed by 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12738632/main.gif
    Jennifer Aguinaldo