Transmission and distribution sector heads for record year
3 October 2024
The GCC region’s power transmission and distribution (T&D) sector is set to experience its best year in terms of the value of awarded contracts.
Based on data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.
This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.
It also exceeds by 31% the total value of awarded contracts in 2021, which registered a record-high of $10.5bn in the 10 years starting in 2014.
Project activity within the T&D sector is expected to remain buoyant over the next few years, with roughly $35.9bn-worth of planned and unawarded contracts.
Of these, some $8.5bn are in the bid evaluation stage as of early October, with a further $6.5bn under tendering.
Some $12bn of projects are in the front-end engineering and design (feed) phase.
Energy diversification
Ambitious national energy diversification and net-zero targets across the region, which traditionally relied almost entirely on thermal power plants, will spur significant investments in T&D infrastructure in the future.
According to experts, the ongoing expansion of electricity generation capacity across the region, particularly from renewable energy sources, requires a more robust, integrated and stable electricity grid.
This is in addition to the projected increase in electricity demand as most states expand their downstream and petrochemical sectors, develop new communities and megaprojects in remote regions, and build more data centres to support smart cities, and internet-of-things (IoT) and artificial intelligence (AI) applications.
The region’s largest economy, Saudi Arabia, for instance, aims for renewable energy to account for 50% of its electricity generation capacity by 2030.
Operational renewable installed capacity in the kingdom jumped from roughly 300MW in 2020 to 3,500MW this year, with a further 16,000MW currently under construction or about to start construction, and gigawatts more under tender.
Crucially, the kingdom’s energy minister confirmed earlier this year that the kingdom has plans to procure up to 20,000MW of renewable capacity every year, subject to demand.
Saudi Arabia is also ramping up its procurement programme for new gas-fired power plants, in line with a plan to decommission fleets running on liquid fuel and at the same time secure baseload as more renewable energy enters the grid.
There is also a marked increase in terms of T&D packages or contracts interconnecting the kingdom’s various regions from central Riyadh to the eastern, northern and southern provinces.
It comes as no surprise that the kingdom accounted for 72% of the $13.8bn-worth of T&D contracts awarded in the GCC region in the first three quarters of 2024.
Oman, which awarded T&D contracts with the same value as the UAE between January and September this year, has also been working to integrate its smaller electricity grids with the sultanate’s main electricity grid to boost electricity supply in its smaller, remote regions.
Unlike the noticeable peaks and throughs in T&D capital expense in other GCC states, the UAE’s spending has remained pretty consistent since 2014, averaging roughly $1.4bn annually. The exemption was in 2021 when a team comprising South Korea’s Kepco, Japan’s Kyushu Electric Power Company (Kyuden) International and France’s EDF won the contract to develop Abu Dhabi’s first high-voltage, direct current (HVDC) subsea transmission system.
It is worth mentioning that the completion of the four units of Abu Dhabi’s 5,600MW Barakah nuclear power plant this year and the expected completion of Dubai’s first hydropower plant in Hatta mean the UAE will have the most diverse energy sources for electricity generation among its peers.
Power links
The goal to expand electricity trade within the GCC member states and with other countries such as Egypt, Jordan and Iraq is another key driver for T&D investments.
Work is under way to increase the capacity of the GCC regional grid and enable its member-states to procure backup or emergency capacity when the need arises. Kuwait availed of this in May when it purchased 500MW from the GCC grid in anticipation of its inability to meet peak demand in the summer months.
An HVDC network linking Saudi Arabia and Egypt is under construction, which will allow bidirectional electricity trade as well as access to the wider European and African markets.
A second GCC link with Oman and a first link with Jordan are also planned. Another HVDC transmission project linking Neom in the northern tip of the Red Sea to Yanbu, stretching 605 kilometres, is under way.
It turns out that the need to invest in T&D infrastructure to support electricity generation capacity buildout, following years of underinvestment, is a global phenomenon.
Juan Diego Zuluaga, Suncolombia CEO, told the ongoing World Green Energy Summit in Dubai that there is a major mismatch between the buildout of transmission lines and electricity generation capacity.
Experts like Zuluaga think that failing to invest in T&D can potentially lead to issues such as curtailment or wastage in renewable power, particularly in the absence of suitable energy storage systems or efficient interconnections or electricity links.
Utility companies are under pressure not only to expand their transmission capacities and coverage but to make these infrastructure and facilities more efficient, too.
New technologies, most of them driven by IoT or AI, for instance, can be used to improve demand and supply management and forecasting, leading to improved grid performance.
“In this region, in particular, consumers expect 24x7 electricity supply. In fact, it is a given,” notes a senior executive with a European technology company. “The hope is for that to continue in the future.”
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.