EPC teams start forming for $22bn Dubai tunnels

24 September 2024

Register for MEED's 14-day trial access 

Some prequalified engineering, procurement and construction (EPC) companies for the contracts to develop and operate various packages of the $22bn Dubai Strategic Sewerage Tunnels (DSST) project have started forming teams in anticipation of the next stage of the tendering process.    

In August, Dubai Municipality prequalified 21 companies and consortiums that can bid for three packages known as J1, J2 and W, and 19 for a fourth package known as J3, of the six-package project.

Some companies are in the process of finalising their partners, while at least one has said it does not intend to tap a partner.

While the country of origin is expected to play a role in the formation of teams, it is expected that the complementarity of the companies' expertise and resources will be crucial in the selection process.  

The client and its advisers have opted to prequalify EPC contractors ahead of investors in a departure from the classic public-private partnership (PPP) procurement process.

"The idea is to issue the technical information pack to the prequalified EPC contractors before the prequalification process for investors starts, allowing EPC contractors time to undertake the design process," a source familiar with the project recently told MEED.

He added: "These designs should be ready once Dubai Municipality completes the prequalification process for investors, saving roughly three months compared to the usual route, where the prequalification processes for developers and EPC contractors are done simultaneously."

The staggered prequalification process is expected to help ensure the request for proposals process takes about six months rather than the typical nine months.

Six packages

Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered as PPP packages with concession periods lasting between 25 and 35 years.

The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres, and the links will extend 10 kilometres (km). 

The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.

W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.

J3, the fourth package, comprises 129km of links.

J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.

J3 will be procured under a design-build-finance model with a concession period of 25-35 years. Once completed, Dubai Municipality will operate them, unlike the first three packages, which are planned to be operated and maintained by the winning PPP contractors.

J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.

The project’s remaining two packages entail the expansion and upgrade of the Jebel Ali and Warsan sewage treatment plants (STPs), and will be procured in a process separate from the four DSST-DLT components.

Prequalified EPC contractors  

The prequalified EPC companies for packages J1, J2 and W are:

  • Acciona Construccion (Spain) – Dubai branch
  • Besix Construct (Belgium)
  • China Harbour Engineering (China)
  • China Railway Group (China)
  • China State Construction Engineering Corporation (China)
  • Daewoo Engineering & Construction (South Korea) 
  • Dogus Insaat VE Ticaret Anonim Sirketi (Turkiye) – Abu Dhabi
  • FCC Construcccion (Spain)
  • Archirodon Construction (Overseas) Company (Greece) / BESSAC (France)
  • China Civil Engineering Construction Corporation – Dubai Branch / Shanghai Tunnel Engineering Company (STEC) / China Railway 14th Bureau Group Corporation 
  • Gulermak Agir Sanayi Insaat (Turkiye) / DETech Contracting (local)
  • National Marine Dredging Company (local) / Afcons Infrastructure (India) / ITD Cementation India 
  • The Arab Contractors (Osman Ahmed Osman & Company, Egypt) / Darwish Engineering Emirates (local) / AqualiaMACE Contracting Operation & General Maintenance (local)
  • Larsen & Toubro (India)
  • Porr (Austria)
  • Power Construction Corporation of China (China) – Dubai branch
  • Samsung C&T Corporation (South Korea) – Dubai Branch
  • SK Ecoplant (South Korea) 
  • Strabag Dubai (Austria)
  • The Petroleum Projects & Technical Consultation Company (Petrojet) – Egypt
  • Webuild  (Italy)

EPC companies that have been prequalified for package J3 are:

  • Acciona Construccion (Spain) – Dubai branch
  • Alghanim International General Trading & Contracting (Kuwait) 
  • China Railway Group (China)
  • China State Construction Engineering Corporation (China)
  • Daewoo Engineering & Construction (South Korea)
  • DETech Contracting
  • Archirodon Construction (Overseas) Company (Greece) / BESSAC (France)
  • China Civil Engineering Construction Corporation (China) – Dubai branch / Shanghai Tunnel Engineering Company (STEC) / China Railway 14th Bureau Group Corporation 
  • Gulermak Agir Sanayi Insaat (Turkiye) / DETech Contracting (local) 
  • International Foundation Group (IFG, local) / General Construction Company (local)
  • Nael Construction & Contracting (UAE) / Concord for Engineering & Contracting (Egypt) – Dubai branch
  • National Marine Dredging Company (local) / Afcons Infrastructure (India) / ITD Cementation India 
  • Mapa Insaat Ve Ticaret (Turkiye)
  • Mohammed Abdulmohsin Al-Kharafi & Sons (Kuwait)
  • Porr (Austria)
  • Power Construction Corporation of China – Dubai branch
  • Strabag (Austria)
  • Tecton Engineering & Construction (local)
  • The Petroleum Projects & Technical Consultation Company – Petrojet (Egypt)
Market-sounding

Dubai Municipality is expected to hold a market-sounding event for investors, MEED reported in early September .

The event is set to take place during the first week of October, a few weeks before interested investors submit their statements of qualifications (SOQ) for the projects' various packages.

MEED previously reported that the client had extended the SOQ submission deadline from 5 September to 21 October.

 Gravity system project

The DSST project aims to convert Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.

Dubai currently has two major sewerage catchments. The first in Deira is Warsan, where the Warsan STP treats the flow.

The second catchment is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.

According to a source close to the project, the DSST will replace 120 pump stations, saving approximately 100 gigawatt-hours of electricity annually. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12590337/main0016.jpg
Jennifer Aguinaldo
Related Articles
  • UAE firm acquires majority stake in African power producer

    31 August 2026

    Abu Dhabi-based ePointZero has announced a deal to acquire a 90% stake in pan-African independent power producer Azura Power Holdings.

    The transaction will give the subsidiary of UAE investment group 2PointZero control of 752MW of operating power generation capacity across Nigeria, Senegal and Mozambique.

    The company will acquire the respective stakes held by existing shareholders Actis and Africa50 through an acquisition vehicle established with Amaya Capital, an Africa-focused investment firm based in London.

    Amaya Capital founded Azuro Power in 2010 and will retain a 10% minority stake in the company, which also has a development pipeline of more than 1.5GW of planned power projects.

    The pipeline includes expansions at existing sites, as well as new gas and renewable energy projects and battery energy storage systems.

    Azuro Power’s operating portfolio comprises the 461MW Azura-Edo power plant in Nigeria, the 116MW Tobene power plant in Senegal and the 175MW Central Termica de Ressano Garcia plant in Mozambique. The company’s operating assets generate around 10% of each country’s grid baseload power, the statement said.

    The company’s projects have received financing and support from development finance institutions including the World Bank, British International Investment, German Investment & Development Company, the US International Development Finance Corporation, the Dutch entrepreneurial development bank, the International Finance Corporation, the Multilateral Investment Guarantee Agency and France’s Proparco.

    The deal, subject to regulatory approvals and other customary closing conditions, marks ePointZero’s entry into African power generation and follows the acquisition of a 20% stake in Egypt’s Elsewedy Electric in 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19171095/main.jpg
    Mark Dowdall
  • Contract award nears for Saudi Landbridge Riyadh section

    31 August 2026

     

    Saudi Arabia Railways (SAR) is preparing to award the main construction contract for the design-and-build of the Riyadh Rail Link, a new north-to-south railway line across the capital.

    MEED understands that the commercial proposals were opened two weeks ago, with a decision expected imminently.

    SAR began the post-tender clarifications with bidders in July, as MEED reported.

    The bidders include:

    • China Civil Engineering Construction Corporation / Al-Ayuni Investment & Contracting (China/local)
    • Nesma & Partners / China Harbour Engineering Company (local/China)
    • Al-Rashid Trading & Contracting / IC Ictas Construction / Saipem (local/Turkiye/Spain)
    • Saudi Binladin Group (local)

    In June, MEED exclusively reported that contractors submitted their commercial proposals on the 30th of that month.

    The scope includes a 35-kilometre double-track line connecting SAR’s North-South Railway to the Eastern Railway network.

    Issued on 29 January, the tender also covers the procurement, construction and installation of associated infrastructure, including viaducts, civil works, utility diversions/installations, signalling systems and other related works.

    Once delivered, the Riyadh Rail Link is expected to become a key component of the Saudi Landbridge railway.

    In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and that the project would instead be delivered in several phases under a different procurement model.

    Negotiations have been under way between Saudi Arabia and China-backed investors interested in developing the scheme through a public-private partnership (PPP). Al-Malik put the project cost at about SR100bn ($26.6bn).

    Overall, it comprises more than 1,500km of new track. A core element is a 900km railway between Riyadh and Jeddah, providing the capital with direct freight access to King Abdullah Port on the Red Sea.

    Other key elements include upgrading the existing Riyadh-Dammam line, a bypass around the capital known as the Riyadh Link, and a connection between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. First announced in 2004, it was put on hold in 2010 before being revived a year later. Rights-of-way issues, route alignment and the high cost have been among the main stumbling blocks.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19161887/main.gif
    Yasir Iqbal
  • Prequalification begins for Dammam suburb boulevard PPP

    31 August 2026

    Saudi Arabia’s Ministry of Municipalities & Housing, in collaboration with Ashraq Development Company and the National Centre for Privatisation & PPP, has issued a request for qualification (RFQ) notice for the development of the King Fahd suburb boulevard project in Dammam.

    The notice was issued on 27 August, with a submission deadline of 22 October.

    The public-private partnership (PPP) project will be delivered using a design, build, finance, operate, maintain and transfer model, with a 43-year contract term.

    The project is located in Al-Bayda Governorate and features a 4 kilometre (km) mixed-use zone along a central boulevard, forming part of a larger 7.3km corridor.

    The project will be developed in two phases and span about 1 million square metres.

    According to a statement: “The private sector partner will be responsible for developing and operating the boulevard, which includes leisure and recreational facilities, public parks, entertainment venues, retail outlets, office spaces, hospitality zones, pedestrian walkways and road networks.”

    The project is the latest addition to the growing number of PPP projects in the kingdom. 

    In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.

    Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.

    In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19160560/main.jpg
    Yasir Iqbal
  • Contractors submit bids for Kuwait power transmission works

    31 August 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has received bids for two tenders covering power transmission works at the South Saad Al-Abdullah residential development.

    The first tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the third phase of the development. 

    According to sources, five contractors submitted bids on 26 August. The local Sayed Hamid Behbehani & Sons made the lowest offer of $104.2m.

    The bids include:

    • Sayed Hamid Behbehani & Sons: $104.2m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.5m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    The second PAHW tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the fourth phase of the project. 

    According to sources, five contractors also submitted bids on 26 August, with A-Ahleia Switchgear making the lowest offer of $103.3m.

    The bids include:

    • Al-Ahleia Switchgear: $103.3m (Kuwait)
    • Industrial Electrical Projects (IEP): $111.7m (Kuwait)
    • Larsen & Toubro: $114m (India)
    • Oman National Engineering & Investment: $118.3m (Oman)
    • National Contracting Company: $126m (Saudi Arabia)

    Both projects were initially tendered in May. As reported by MEED, PAHW previously issued addendums for both substation tenders, revising the qualification requirements for bidders.

    According to the revised requirements, contractors must be approved by Kuwait’s Ministry of Electricity, Water & Renewable Energy and have experience supplying and installing at least 10 132kV substations in Kuwait.

    The addendums also introduced requirements related to transformer and gas-insulated switchgear manufacturing approvals, as well as operational performance records for installed equipment.

    Sabah Al-Ahmad residential city

    Meanwhile, bids remain under evaluation for two 132kV underground cable tenders for the South Sabah Al-Ahmad residential development, tendered by PAHW in May.

    The first cable tender covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts in the project’s fourth phase. 

    MEED previously reported that Egytech Cables, a subsidiary of Egypt’s Elsewedy Electric, was the lowest bidder with an offer of $42.37m.

    The second cable tender covers the supply, extension and maintenance of 132kV underground cables linked to substations serving the N5, N6, N8 and N10 districts in the project’s third phase. 

    Egytech Cables submitted the lowest offer of $39.95m. TBEA Shandong Luneng Taishan Cable submitted a bid of $41.89m, along with Riyadh Cables ($42.05m) and The Contractor General Trading & Contracting ($44.97m).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19151780/main.jpg
    Mark Dowdall
  • Eni plans to drill 230 oil and gas wells in Egypt

    31 August 2026

    Italy’s Eni is planning to drill 230 new oil and gas wells in Egypt, according to a statement from the country’s Ministry of Petroleum & Mineral Resources.

    Eni’s chief executive, Claudio Descalzi, discussed his plans for exploration and development in Egypt on 25 August during a meeting with Egypt’s Prime Minister Mostafa Madbouly and the Minister of Petroleum and Mineral Resources Karim Badawi.

    During the meeting, Descalzi said that the company has plans to drill 30 exploration wells in addition to 200 development wells.

    Descalzi said his company plans to intensify its exploration and development programmes, especially in the Mediterranean and Western Sahara regions, to increase production of natural gas and crude oil.

    He said that his company plans to use the latest seismic imaging and artificial intelligence technologies as a key part of its exploration and development plans.

    In a separate statement, Eni also said that it is working with UK-headquartered BP and state-owned Egyptian General Petroleum Corporation (EGPC) to reach a final investment decision (FID) for a project to develop the major gas discovery of Denise West in Egypt’s Temsah concession.

    Eni made the discovery in February and says it holds about 2 trillion cubic feet of gas and 130,000 barrels of condensate.

    It is targeting first gas in less than two years and expects to reach FID “in the next few months”, according to its statement.

    Eni’s total investments in Egypt have reached a value of $8.5bn, according to the statement from Egypt’s Ministry of Petroleum & Mineral Resources.

    During the meeting on 25 August, Descalzi also stressed the importance of linking Cyprus’ Cronos gas field to Egyptian export infrastructure.

    In July, Eni reached the FID to develop the Cronos project in deep waters offshore Cyprus, targeting the first Cypriot gas to market in 2028.

    Production is expected to reach a plateau of 500 million standard cubic feet a day.

    In October last year, Egypt and Cyprus signed provisional agreements to connect Cyprus’ Cronos gas field to Egypt’s gas infrastructure.

    The agreements were signed by parties including Egypt’s Ministry of Petroleum and Mineral Resources, Eni, and the French oil and gas company TotalEnergies.

    Connecting the Cronos field to Egypt is expected to involve the tendering of a major subsea pipeline project.

    This will allow gas to be transported and processed in existing Zohr facilities in Egypt, then transferred and liquefied at the Damietta LNG plant for export as LNG to international markets, primarily Europe.

    At the meeting on 25 August, Descalzi said the planned project to connect the Cronos field to Egypt will be considered a model for regional cooperation in the gas sector and will enhance Egypt’s status as a regional gas hub.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19079059/main.jpg
    Wil Crisp