Saipem wins $4bn Qatar offshore gas project contract
16 September 2024
Register for MEED's 14-day trial access
QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, has awarded Italian contractor Saipem an estimated $4bn engineering, procurement, construction and installation (EPCI) contract as part of the second phase of its North Field Production Sustainability (NFPS) project.
Saipem has won combined packages COMP3A and COMP3B of the NFPS project’s second phase, it said in a statement on 16 September.
The scope of work on the combined packages encompasses EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.
The aim of the second phase of the NFPS project is to support QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme.
The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.
This is the second contract win for Saipem in the NFPS project’s second phase, which consists of four main EPCI packages.
Prior to winning combined packages COMP3A and COMP3B, QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities.
The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.
The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.
NFPS first phase
Saipem is executing the main EPCI works on the entire first phase of the NFPS project, which consists of two packages.
Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.
QatarEnergy LNG, formerly Qatargas, awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.
Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.
The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.
In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.
QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.
Saipem’s scope of work on the package, known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.
Saipem has performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.
Saipem expects to complete work on both packages of the first phase of the NFPS project by the end of 2024.
Exclusive from Meed
-
-
Drone strikes Kuwait International airport1 April 2026
-
Saudi Arabia’s Sadara halts chemical production1 April 2026
-
-
BP advances Egypt offshore gas plans1 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Contractors submit Al-Maktoum airport superstructure bids1 April 2026

Dubai Aviation Engineering Projects (DAEP) received proposals on 31 March from contractors for three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.
MEED understands that the selected contractor will undertake superstructure works on three packages:
- West Terminal and concourse one
- Concourse two
- Concourse three
Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.
According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.
It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.
In August last year, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport.
The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
Construction progress
Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.
Construction on the project’s first phase is expected to be completed by 2032.
The government approved the updated designs and timelines for its largest construction project in April 2024.
In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
The statement added that the project will create housing demand for 1 million people around the airport.
In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.
Project history
The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.
An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.
Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16215664/main.jpg -
Drone strikes Kuwait International airport1 April 2026
Register for MEED’s 14-day trial access
Kuwait International airport was hit by further drone attacks on Wednesday, with strikes on fuel tanks sparking a major fire.
Kuwait’s state news agency Kuna said the attack caused significant damage to fuel tanks belonging to Kuwait Aviation Fuelling Company. No casualties were reported.
This was the second reported incident at the airport in recent days. Local media reported that the airport was attacked on 28 March by multiple drones, causing significant damage to its radar system.
The airport is currently undergoing expansion works that are expected to be completed by 2027, as MEED reported previously.
Project execution of the second terminal began in 2017, with the completion date pushed back from the original 2022 target.
The second terminal project consists of three packages.
These are:
- Package 1: Main works – $4,329m
- Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
- Package 3: Aircraft parking, runways and service buildings – $950m
Turkiye’s Limak Holding is executing the main works.
The terminal building was designed by Foster+Partners and Gulf Consult.
Spanish firm Ineco is providing the project management services for the new terminal building and the airfield.
The scope of the main package includes the new terminal building, a building for cooling and electricity supply facilities, and a building for the water supply and the future Automatic People Mover (APM) connection to the satellite building.
The terminal building will be three times the size of the original building and will have 36 boarding gates.
The building will cover more than 700,000 square metres and have five floors, one of which will be underground.
It will have the capacity, at maximum service level, for 25 million passengers a year once the first phase has been completed and up to 50 million passengers after further phases are completed.
The second package of works includes a new car park with approximately 5,000 parking spaces, connected to the new passenger terminal.
It also includes all new access roads to the airport and landscaping.
The scope of the third package comprises the main platform, new taxiways and several tunnels, including one under the platform between the terminal building and the future cargo area of the airport.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16216797/main.png -
Saudi Arabia’s Sadara halts chemical production1 April 2026
Register for MEED’s 14-day trial access
Sadara Chemical Company (Sadara), the Saudi Aramco-Dow Chemical joint venture producing petrochemicals and specialty chemicals, has announced a temporary shutdown of production, citing ongoing supply chain disruptions.
Sadara operates a sprawling chemical production complex in Jubail in Saudi Arabia’s Eastern Province, with a total output capacity of more than 3 million metric tonnes a year. Aramco and Dow established the Sadara petrochemicals complex – estimated to have cost $13bn – in 2016.
The suspension was announced in a filing on the Saudi Exchange (Tadawul) by Sadara Basic Services, which issues sukuk, or Islamic bonds, for its parent. “The shutdown was successfully completed in accordance with Sadara’s high safety standards and in a manner that safeguards operations and reduces risk,” the entity said in its filing on 31 March.
“Sadara cannot provide, at the present time, an estimate for the return to production, as this is contingent on domestic and international factors,” it said, adding the shutdown is expected to impact this year’s financial results.
The month-long war between Israel, the US and Iran has spread across the Middle East, disrupting energy supplies and threatening the global economy, as Tehran has responded to US and Israeli attacks by targeting regional energy and industrial infrastructure, as well as shipping.
ALSO READ: Sultan Al-Jaber calls Strait of Hormuz blockade “economic terrorism”
Separately, Sadara, in another Tadawul filing on 31 March, announced a net loss of SR5,793bn ($1.54bn) for the full year 2025, a further decline of about 40% compared to 2024. The company’s revenue in 2025 fell by about 15% year-on-year to $2.63bn.
The chemicals producer attributed the deepening of its losses in 2025 to a reduction in sales volumes, “which resulted from unplanned operational events and extended maintenance activities that temporarily impacted production availability”.
Sadara also pinned its augmented losses to “margin compression, and higher fixed costs associated with unplanned operational events and extended maintenance activities.
“In addition, the company experienced lower average selling prices across certain portfolio lines, which further contributed to the overall decrease in revenue,” Sadara said in the disclosure.
In addition, “the net loss for 2025 increased compared to 2024, mainly due to an accounting adjustment related to a debt modification that had a favourable impact on the prior year’s results,” the company added.
ALSO READ: Sabic registers $6.87bn net loss in 2025
https://image.digitalinsightresearch.in/uploads/NewsArticle/16215635/main2446.jpg -
AD Ports earmarks $667m for port infrastructure in 20261 April 2026
Register for MEED’s 14-day trial access
Abu Dhabi’s AD Ports Group plans to invest AED2.45bn ($667m) in port infrastructure development in 2026, according to its 2025 annual report.
It has also earmarked AED1.3bn ($345m) in capital expenditure for the development of liquefied petroleum gas (LPG) and liquefied natural gas (LNG) storage terminals in 2026-28.
The group said 2025 was a year of record revenue and profits. It posted revenue of AED20.77bn and net profit of AED2.07bn, up 20% and 16%, respectively, from 2024.
Its ports, economic cities and free zones, and maritime and shipping clusters were the key drivers of growth.
AD Ports Group also acquired long-term, profit-generating assets through stakes in container terminal operators in Egypt and Syria.
The company launched an asset monetisation programme in Q3 2025 to deleverage and optimise its balance sheet over the medium term.
The programme targets debt reduction and is intended to enable the recycling of AED4.6bn ($1.3bn) of capital in 2025 into higher-return projects aligned with its core business.
Separately, AD Ports Group said operations across its clusters continue as normal amid current regional developments.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16215273/main.jpg -
BP advances Egypt offshore gas plans1 April 2026
London-headquartered BP is making progress on its campaign to drill five wells in Egypt’s portion of the Mediterranean, according to a statement from the North African country’s oil and gas ministry.
The Fayoum 4 well is scheduled to start production in July, with an estimated output of around 100 million cubic feet of gas a day, according to the ministry.
It said it expected the well to bolster domestic supply during the summer, helping meet demand from power stations and reducing Egypt’s import bill.
BP is planning to invest about $1.5bn in exploration and field development in Egypt during the 2026/27 fiscal year.
Karim Badawi, minister of petroleum and mineral resources, said that intensifying drilling for new wells is a top priority for the ministry, both to unlock fresh exploration opportunities and to increase output from existing fields.
Egypt is currently a net importer of natural gas, and due to this, its economy is expected to be severely impacted by the recent spike in global gas prices as a result of the US and Israel’s war with Iran.
MEED’s March 2026 report on Egypt includes:
> COMMENT: Egypt’s crisis mode gives way to cautious revival
> GOVERNMENT: Egypt adapts its foreign policy approach
> ECONOMY & BANKING: Egypt nears return to economic stability
> OIL & GAS: Egypt’s oil and gas sector shows bright spots
> POWER & WATER: Egypt utility contracts hit $5bn decade peak
> CONSTRUCTION: Coastal destinations are a boon to Egyptian constructionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16212519/main.jpg