Region advances LNG projects with pace

30 August 2024

 

Global liquefied natural gas (LNG) liquefaction capacity is expected to more than double by 2028, potentially increasing from 473 million tonnes a year (t/y) in 2023 to 968 million t/y in 2028 through new build and expansion projects, according to a recent report by GlobalData.

North America dominates globally among the regions, in terms of new build and expansion liquefaction capacity growth, contributing around 54% of the total global capacity additions or 268 million t/y by 2028, GlobalData says in the report. 

The Middle East comes in at second position, followed by the Former Soviet Union, with capacity additions of 78 million t/y and 71 million t/y, respectively. 

Since the start of this decade, there has been a sharp increase in investments in the Middle East and North Africa (Mena), and particularly in the Gulf region, in projects to expand LNG production. Capital expenditure close to $45bn has been made by Mena hydrocarbon producers in the past 10 years on various LNG projects, mainly for output capacity building, MEED Projects data shows. Almost three-fourths of that spending took place in the past four years, and predominantly in the GCC.

A desire to cater to the steady growth expected in global LNG demand and dominate the global supply market is fuelling the wave of investments into large-scale production capacity expansions and terminal construction by Gulf players.

Qatar guns for top spot

Qatar has been jostling with the US and Australia for the status of being the largest LNG provider to the world for many years now. The three countries have all clinched the top spot, only to be unseated by another the very next month.

However, when its mammoth North Field LNG expansion programme begins to come online later this decade, Qatar will be able to consolidate its position as the world’s largest producer and exporter of LNG in the long term.

State enterprise QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028. Engineering, procurement and construction (EPC) works on the two projects are making steady progress.

QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by 2025. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

QatarEnergy awarded the $10bn main EPC contract for the North Field South LNG project, covering two large LNG processing trains, to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company (CCC) in May last year.

When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

Qatar is, however, not stopping at that. QatarEnergy, in February, announced a third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project derives its name from the western zone of Qatar’s North Field offshore gas reserve, from where it will draw feedstock for LNG production.

Oman moves up the ladder

Oman has been supplying LNG to customers, mainly in Asia, for many years now. Majority state-owned Oman LNG operates three gas liquefaction trains at its site in Qalhat, with a nameplate capacity of 10.4 million t/y. Due to debottlenecking, the company’s complex now has a production capacity of about 11.4 million t/y.

As recently as late July, the Omani government announced that Oman LNG will build a new train at its Qalhat LNG production complex in Sur, located in the sultanate’s South Al-Sharqiyah governorate. Oman LNG will perform the preliminary engineering study for the planned LNG train.

The LNG train will have an output capacity of 3.8 million t/y. When commissioned in 2029, it will increase Oman LNG’s total production capacity to 15.2 million t/y.

Aside from Oman LNG, France’s TotalEnergies has now committed itself to becoming a major LNG supplier in the sultanate. In partnership with state energy holding conglomerate OQ, TotalEnergies achieved final investment decision earlier this year for a major LNG bunkering and export terminal in Oman’s northern city of Sohar.

TotalEnergies leads a joint venture named Marsa LNG, which is the Sohar LNG terminal project developer. Marsa LNG was formed in December 2021 through an agreement between TotalEnergies and the sultanate’s state energy holding company OQ. The partners own 80% and 20% stakes, respectively.

Marsa LNG intends to develop an integrated facility consisting of upstream units that will draw natural gas feedstock from TotalEnergies’ hydrocarbon concessions in the sultanate, particularly from Blocks 10 and 11; an LNG bunkering terminal and storage units located in Sohar port; and a solar photovoltaic plant to power the LNG terminal.

The Marsa LNG terminal will have a single train with the capacity to process about 1 million t/y of natural gas into LNG. The bunkering terminal will mainly supply LNG as a marine fuel to vessels. Marsa LNG has picked France-based Technip Energies to perform EPC works on the estimated $1bn LNG terminal project.

Adnoc gives shape to ambitions

Abu Dhabi National Oil Company (Adnoc) has been a relatively smaller LNG producer in comparison to its GCC peers. Adnoc Group subsidiary, Adnoc Gas, operates three large gas processing trains on Das Island. At its Das Island terminal, Adnoc Gas has an LNG liquefaction and export capacity of about 6 million t/y. The first and second trains were commissioned in the 1970s and have a combined output capacity of 2.9 million t/y. The third train came into operation in the mid-1990s, with a capacity of 3.2 million t/y.

Adnoc Gas’ LNG production and export capability, however, will receive a major fillip when a new greenfield terminal it has committed to developing in Ruwais, Abu Dhabi, comes online before the end of this decade. The planned LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.

Adnoc awarded the full EPC contract and achieved the final investment decision for the LNG terminal complex in June. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy was awarded the EPC contract, worth $5.5bn.

Jordan takes a step forward

Jordan imports more than 90% of its oil, gas and refined product needs and therefore has a strong economic case for developing projects to boost its domestic hydrocarbon infrastructure, particularly for gas.

The country recently took a key step forward when Aqaba Development Corporation awarded the main EPC contract in August for a project to develop the Sheikh Sabah Al-Ahmad Al-Jaber Al-Sabah LNG onshore regasification facility at the port of Aqaba.

The contract was won by a consortium of Singapore-based AG&P and South Korea’s Gas Entec, along with their local partner, Jordan’s Issa Haddadin.

In a statement, Gas Entec said that the facility will have the capacity to process 720 million cubic feet a day of natural gas. 

“Jordan relies heavily on natural gas for its power and industrial needs, but faces challenges with supply reliability,” Gas Entec said.

“The new LNG terminal will provide Jordan with the flexibility to access LNG from various global suppliers, ensuring a stable and secure energy source.”

Global LNG demand set for steady growth

https://image.digitalinsightresearch.in/uploads/NewsArticle/12432924/main.gif
Indrajit Sen
Related Articles
  • Consultant wins Dubai Al-Maktoum airport metro link

    11 September 2026

     

    Register for MEED’s 14-day trial access 

    US-based engineering firm Aecom has won a design contract for the Route 2020 extension, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Dubai’s Roads & Transport Authority (RTA) awarded the contract.

    The extension will run about 3 kilometres (km) and include two stations.

    MEED understands the invitation to bid was issued in January, with a submission deadline in mid-March.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    The RTA also selected Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4, in October last year, as MEED reported.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19571676/main.jpg
    Yasir Iqbal
  • Saudi Arabia sets October deadline for Mecca metro design

    11 September 2026

     

    The Royal Commission for Makkah City & Holy Sites (RCMC) has set a deadline of 14 October for a contract covering the initial design studies for its long-planned metro network in the holy city.

    The scope includes reviewing existing studies, preparing a concept design, conducting land acquisition studies, developing an integration concept for future phases and other related studies.

    The notice was issued in May, with an initial submission deadline of 5 August, as MEED reported.

    In September last year, RCMC invited contractors to attend an early market engagement meeting for the project.

    In an explanatory document inviting companies to attend the event, the RCMC’s General Transport Centre said it was seeking to gauge market interest in the multibillion-dollar project and obtain feedback on its proposed procurement approach.

    MEED exclusively reported in June last year that the project was restarting. Current plans envisage a four-line network, named lines A-D, with 89 stations and three depots, to be implemented over three phases between 2032 and 2045.

    Project scope

    Stage 1 focuses on lines B and C, involving 2.4 kilometres of tunnelling under the Masar project and integration with the existing Mashaer line.

    The network will run just over 62km and comprise 31 stations, 21 of which will be underground, including three iconic stations. A total of 19.5km will run through tunnels, while 41.2km will be elevated, with the remainder at grade.

    The 66 required trainsets are projected to provide a daily passenger capacity of about 450,000, equating to annual ridership of 171 million.

    The 84.7km-long second phase, due to be operational by 2038, will extend the two lines towards the outskirts of Mecca and includes construction of the initial inner and central segments of lines A and D.

    Comprising 61.1km elevated and 18.6km underground, Phase 2 is planned to add 45 stations serving the two new lines, as well as two depots and a potential interconnection with the planned Saudi Landbridge. The 59 trainsets for Phase 2 will increase the network’s projected total annual passenger capacity to more than 500 million.

    Phase 3 covers the elevated 36km extension of lines A and D and involves procurement of a further 72 trainsets, increasing the network’s ultimate passenger capacity to 1.2 million daily and 642 million annually by completion in 2045.

    Associated development

    The metro plan also envisages several transit-oriented developments (TODs) at different points on the route. These will typically comprise commercial, residential and retail elements to maximise the investment case.

    The client’s proposed procurement approach involves three distinct packages: civil and systems works, TODs, and operations and maintenance.

    The initial concept calls for some of the project to be delivered on a public-private partnership (PPP) basis, wherein the private sector, through special purpose vehicles, will part-finance, build, operate and then transfer commercially viable elements of the scheme.

    The then-called Mecca Mass Rail Transit Company (MMRTC) first launched the metro project in 2013; however, the scheme has faltered for more than a decade due to funding issues, land acquisition challenges and scope changes.

    The relaunch of the procurement process raises hopes that the project will now come to fruition, although it is likely to be at least 18 months before any definitive works start.

    Mecca is home to Saudi Arabia’s first metro, the nine-station, 18km-long Mashaer line, which opened in 2010. It operates only seven days a year during Hajj, but carries more than 2 million pilgrims during that time.

    Some 30 million pilgrims visit the city each year, with this number set to grow. A known, quantifiable and growing demand base will help facilitate the use of a PPP mechanism if the framework is adopted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19569659/main.jpg
    Yasir Iqbal
  • Consortiums submit bids for Sadara cogeneration plant

    11 September 2026

     

    Register for MEED’s 14-day trial access 

    At least three consortiums have submitted bids for the contract to develop and operate a cogeneration steam and power plant catering to the Sadara petrochemicals complex in Saudi Arabia.

    The planned independent steam and power plant (ISPP) project will have a capacity for 400MW-450MW of combined-cycle electricity generation and 550-700 tonnes an hour of steam.

    According to sources, bids were submitted for the contract at the end of August.

    The consortium bidders include: 

    • Abu Dhabi National Energy Company (Taqa) / Samsung C&T (South Korea)
    • Al-Jomaih Energy & Water (Saudi Arabia) / Albawani (Saudi Arabia) / Sepco 3 (China)
    • Acwa (Saudi Arabia), Korea Electric Power Corporation (Kepco) / Doosan Enerbility (South Korea)

    Sadara Chemical Company (Sadara) is the project client. It is the downstream joint venture of Saudi Aramco and US-headquartered Dow Chemical.

    The estimated $500m project includes construction of a power plant, substations, a seawater intake system and associated switchyards and switchgear.

    The project will also include gas turbines and a back-pressure steam turbine, as well as facilities for steam production.

    In 2024, MEED exclusively reported that Sadara had prequalified potential bidders for the project. It is understood that the request for proposals was issued towards the end of last year.

    The first units at the $20bn Sadara petrochemicals complex in Jubail began production in 2016, and the complex became operational in 2017.

    The Sadara complex is designed to produce more than 3 million tonnes a year (t/y) of chemicals and performance plastics, including polyurethanes, propylene oxide, propylene glycol, elastomers, polyethylene, glycol ethers and amines.

    Construction is also continuing on the Najim cogeneration facility, which will supply the Amiral petrochemicals complex with up to 475MW of power and approximately 452 tonnes an hour of steam.

    Previously known as the Amiral cogeneration independent steam and power plant, the project is being developed by a team comprising Abu Dhabi National Energy Company (Taqa) and Japanese power generation company Jera.

    South Korean contractor Samsung C&T is the engineering, procurement and construction contractor for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19567716/main.jpg
    Mark Dowdall
  • UAE plans 150km Boring Company tunnel network

    11 September 2026

    The UAE plans to build more than 150 kilometres of underground tunnel with US tunnelling firm The Boring Company, in a programme backed by a $3bn funding round the UAE led.

    The Series D round values the Boring Company at $23bn, about four times the $5.7bn it was worth after a 2022 funding round. The UAE and affiliated investment entities led the round, which will accelerate a partnership to deploy underground infrastructure across the UAE, the firm said.

    The 150km target marks a substantial expansion of the company’s footprint in the country, extending work already committed through the Dubai Loop project. It contrasts sharply with what has been contracted so far. The Boring Company has signed a construction contract with Dubai’s Roads & Transport Authority (RTA) for the pilot phase of Dubai Loop, covering a 6.4km route and four stations linking Dubai International Financial Centre (DIFC) and Dubai Mall. The pilot is expected to cost about AED565m ($154m), with tunnelling due to begin in the second half of this year.

    The 150km figure therefore represents an ambition for the wider partnership rather than a contracted volume, with the bulk of the network yet to be tendered, designed or awarded. No timeframe has been attached to the target.

    A second Dubai Loop phase will connect Dubai World Trade Centre and DIFC with Business Bay, extending the tunnels to 22km across 19 stations. The total cost across both phases is expected to be about AED2bn ($545m), with completion scheduled within three years. The pilot route is projected to carry about 13,000 passengers a day, rising to about 30,000 a day across the full route.

    Other investors in the round include Human Capital, Vy Capital, Valor Equity Partners, Sequoia Capital, Andreessen Horowitz, Temasek, Shamal Holding and Baron Capital. The proceeds will also fund hiring, the scaling of the company’s Loop transit systems in the US cities of Las Vegas and Nashville, and further development of its Prufrock tunnel-boring machines, which it says can operate in both soft ground and hard rock.

    The RTA and the Boring Company signed a memorandum of understanding in February last year to explore developing the Dubai Loop, and the construction contract followed in February this year. In May, US engineering firm Parsons was appointed as programme manager for the pilot phase, with a scope covering independent design verification, permitting and multidisciplinary design reviews.

    The appointment comes amid a broader shift towards underground construction across the Gulf, as metro, sewerage and highway works in the UAE, Saudi Arabia and Qatar increasingly default to tunnelling.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19567623/main.jpg
    Yasir Iqbal
  • Heisco wins $359m oil contract in Kuwait

    11 September 2026

    Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) has been awarded a contract worth KD111.05m ($359m) to develop storage tanks for Kuwait’s Jurassic Light Oil (JLO) export facilities, according to a stock market filing.

    The scope of the contract includes civil, mechanical, electrical and instrumentation works, as well as engineering, procurement and construction (EPC) services for the tanks.

    The contract was awarded by India’s Larsen & Toubro (L&T), the main contractor for a broader project to develop JLO storage and export facilities in Kuwait, as well as upgrade Kuwait Oil Company’s (KOC’s) existing export network.

    The $979.2m main contract for this broader project was awarded to L&T on 15 July.

    The contract for Heisco’s scope of work has a time period of 42 months, according to its stock market filing.

    Oil crisis

    Kuwait’s oil and gas sector is currently in crisis due to the regional war that started after the US and Israel attacked Iran on 28 February.

    The war has severely disrupted exports through the Strait of Hormuz, which Kuwait relies on in order to ship crude exports.

    It has also disrupted imports of equipment and materials for projects, raising project costs.

    Sheikh Nawaf Saud Al-Sabah, deputy chairman and CEO of Kuwait Petroleum Corporation (KPC), the country’s national oil company, has described the current conflict as the biggest oil crisis the country has faced since Iraq’s 1990 invasion.

    Despite the significant reduction in crude exports, Kuwait’s state-owned oil companies have continued to tender some projects.

    Export facilities

    The scope of work under the contract awarded to L&T in July includes the EPC of six new crude oil storage tanks, each with an operating capacity of 618,000 barrels, along with associated facilities, the Mumbai-headquartered company said on 29 July.

    The project also involves “the installation of new pipelines and comprehensive upgrades to Kuwait’s existing crude loading and export network, to seamlessly accommodate increased production and enhance the country’s crude handling capabilities”, the Bombay Stock Exchange-listed company said.

    L&T also said that the contract will be executed on a lump-sum turnkey basis.

    Only two companies submitted bids for the contract in October last year:

    • L&T (India): KD303.5m ($988m)
    • Petrofac (UK): KD310.6m ($1.01bn)

    Following bid submission, KPC discussed the potential cancellation of the tender due to bids coming in significantly over budget and Petrofac becoming ineligible to win contracts in Kuwait.

    The contractor was temporarily barred from participating in tenders in Kuwait’s oil and gas sector in December last year.

    Petrofac received the ban after the company announced it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa region.

    Despite discussions about cancelling the tender, KPC ultimately decided to proceed with the award process because it considered the project a high priority.

    One source previously told MEED: “Around the same time, projects worth around $8bn were cancelled because of bids coming in over budget, but this one has gone ahead because KPC sees it as an essential project.”

    The project was originally tendered in November 2024, with a bid deadline of 1 December the same year. The bid deadline was extended several times before bids were ultimately submitted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19556019/main.png
    Wil Crisp