Working towards a common energy-transition goal
28 November 2022
Published in partnership with

In the end, it went right to the wire. Just as it looked like the UN’s 27th Conference of the Parties (Cop27) would conclude without an accord, the weary delegates announced that they had reached a landmark agreement on setting up a fund to help compensate poorer nations for the economic and social destruction caused by climate change.
The statement, two days after the Sharm el-Sheikh summit’s original 18 November end date, was a culmination of some 30 years of negotiations between developed economies and developing nations. The latter had long argued that the damage they have experienced from global warming should be paid for by richer countries responsible for the crisis in the first place.
Although far from perfect, the global ‘loss and damage’ fund was hailed as an important and symbolic step towards hitting the agreed target of limiting global temperature increases to 1.5C above pre-industrial levels by 2030. It also marked the continuing engagement and collaboration by governments across the globe.
“We rose to the occasion,” said Egypt’s Minister of Foreign Affairs and president of Cop27 Sameh Shoukry.
“We worked around the clock, day and night, but united in working for one gain, one higher purpose, one common goal. In the end, we delivered. We listened to the calls of anguish and despair.”
Private sector involvement
While Cop27 has been and will continue to be a policy-setting mechanism negotiated at the highest level, companies played a critical role during the conference.
Firms representing a broad range of sectors, including Vodafone, Microsoft, Boston Consulting Group and Bloomberg, partnered with the event, and many more participated in the main conference and exhibition areas.
Ultimately, governments understand that the private sector will lead the drive towards net zero. Without corporates worldwide investing in clean energy projects and technology, there is little hope that targets will be reached.
Five consistency points
A key supporter of Cop27 was Siemens Energy. Sharing its expertise through panels covering subjects as varied as the Mediterranean’s North-South Energy Partnership, improving power access in Africa by unlocking its green hydrogen potential, and overcoming the challenges of decarbonisation, the energy technology company played a pivotal role in discussions and thought leadership.
It also participated in the world leader’s summit at a roundtable discussing green hydrogen, reinforcing its positioning of energy transition at the heart of its strategy.
Before the Sharm el-Sheikh conference, Siemens Energy president and CEO Christian Bruch outlined five points of consistency that his company considers to be unifying elements in the decarbonisation drive.
The first is the acceleration of renewables. Replacing conventional power generation systems with solar, wind, hydro and other forms of renewable energy is essential to reduce greenhouse emissions.
Despite a considerable increase in the overall share of renewables in the past three years on the back of ever-lowering costs and more efficient technology, more must still be done.
For example, the US needs to triple its share of renewable energy as a proportion of the energy mix by 2050 for the energy transition to succeed. The Asia-Pacific region, meanwhile, will have to increase this figure fourfold.
Regional targets
In the Middle East, every country has now set ambitious targets to increase renewable energy. The likes of Saudi Arabia, Morocco and the UAE are aiming for renewables to account for up to 50 per cent of total production by 2030. To reach these objectives, almost all new power generation projects come in the form of renewables.
However, the impact of greener electricity production could be somewhat offset by continuing demand growth caused by an increasing global population and economic growth.
In this context, the second point is the requirement for improved energy conservation measures, such as policies to incentivise the electrification of industry and transport.
Regionally, the industrial electrification of energy-intensive industries is an optimal opportunity to reduce harmful emissions by harnessing electric boilers and/or electricity-based fuels. Future large-scale blue and green hydrogen production will also have a role to play in industrial processes.
Siemens Energy’s third point of consistency is improving electrical efficiency. The increase in renewable energy capacity and the growth in power capacity, in general, require significant investment in transmission and distribution networks.
This is particularly important in areas such as sub-Saharan Africa, where almost 25 per cent of the population has little to no access to electricity.
The fourth point covers the requirement to use existing conventional power infrastructure to help bridge the gap between the fossil-fuelled economies of today and the net zero of tomorrow.
Progress cannot be made in one step alone and requires a gradual transition. In the meantime, existing thermal plants can employ measures such as combined-cycle technology and carbon capture to make them as efficient and environmentally friendly as possible.
The energy transition is the biggest investment programme since the dawn of industrialisation. If governments, business and society work together, energy transition is a massive opportunity
Christian Bruch, Siemens Energy president and CEO
Mineral production
Finally, to achieve all of this, it is necessary to improve supply chains and increase the production of necessary minerals and rare earth metals required in net-zero technologies, such as lithium, nickel, cobalt and chromium.
Bruch gives the example of a typical electric car, which requires six times more mineral inputs than one powered by an internal combustion engine. He also cites onshore wind plants, which need nine times more than a gas-fired power plant.
If mineral production is not increased and geographically diversified, there is a risk of future supply bottlenecks.
In the Middle East, a good illustration of this is the potential future supply gap for electrolyser systems, and the anodes and cathodes typically made from metals such as zinc, nickel and lithium.
MEED estimates that about 75GW of electrolyser production capacity will be required by 2030 to meet the demand for the raft of planned green hydrogen plants in the region alone, compared with a total global output capacity of just 8GW today.
Industrial decarbonisation alliance
All five consistency points make salient arguments. However, they can only be achieved with close cooperation between the private and public sectors. While the former can spearhead and implement the decarbonisation drive, the latter can provide the regulations and incentives to encourage these initiatives.
The newly formed Alliance for Industry Decarbonization initiated by Siemens Energy and coordinated and facilitated by the Abu Dhabi-based International Renewable Energy Agency (IRENA) is an example of greater collaboration between the public and private sectors.
The 28-member alliance – which encompasses a range of global energy, renewable, consulting and manufacturing companies – met for the first time during Cop27 to outline its joint vision and implementation plan. Its strategy focuses on six pillars and enablers that tie into the points of consistency: renewables, green hydrogen, bioenergy with carbon capture, utilisation and storage (CCUS), heat process optimisation, human capital and finance.
Only through this kind of stakeholder dialogue can the immense and existential challenges posed by global warming be overcome. Governments or companies acting in isolation will only achieve so much on their own. The points of consistency must be considered as a whole and in unison if the world’s climate objectives are to succeed.
As Bruch says: “The energy transition is the biggest investment programme since the dawn of industrialisation. If governments, business and society work together, energy transition is a massive opportunity. There is no excuse for waiting any longer.”
Related reads:
- New alliance forged to accelerate net-zero ambitions
- The journey towards net zero
- Solving Europe’s energy challenge
- Africa’s energy trilemma
- Region primed for global green hydrogen leadership
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg