Working towards a common energy-transition goal

28 November 2022

Published in partnership with

In the end, it went right to the wire. Just as it looked like the UN’s 27th Conference of the Parties (Cop27) would conclude without an accord, the weary delegates announced that they had reached a landmark agreement on setting up a fund to help compensate poorer nations for the economic and social destruction caused by climate change. 

The statement, two days after the Sharm el-Sheikh summit’s original 18 November end date, was a culmination of some 30 years of negotiations between developed economies and developing nations. The latter had long argued that the damage they have experienced from global warming should be paid for by richer countries responsible for the crisis in the first place.

Although far from perfect, the global ‘loss and damage’ fund was hailed as an important and symbolic step towards hitting the agreed target of limiting global temperature increases to 1.5C above pre-industrial levels by 2030. It also marked the continuing engagement and collaboration by governments across the globe.

“We rose to the occasion,” said Egypt’s Minister of Foreign Affairs and president of Cop27 Sameh Shoukry. 

“We worked around the clock, day and night, but united in working for one gain, one higher purpose, one common goal. In the end, we delivered. We listened to the calls of anguish and despair.”

Private sector involvement

While Cop27 has been and will continue to be a policy-setting mechanism negotiated at the highest level, companies played a critical role during the conference. 

Firms representing a broad range of sectors, including Vodafone, Microsoft, Boston Consulting Group and Bloomberg, partnered with the event, and many more participated in the main conference and exhibition areas. 

Ultimately, governments understand that the private sector will lead the drive towards net zero. Without corporates worldwide investing in clean energy projects and technology, there is little hope that targets will be reached.

Five consistency points

A key supporter of Cop27 was Siemens Energy. Sharing its expertise through panels covering subjects as varied as the Mediterranean’s North-South Energy Partnership, improving power access in Africa by unlocking its green hydrogen potential, and overcoming the challenges of decarbonisation, the energy technology company played a pivotal role in discussions and thought leadership.

It also participated in the world leader’s summit at a roundtable discussing green hydrogen, reinforcing its positioning of energy transition at the heart of its strategy. 

Before the Sharm el-Sheikh conference, Siemens Energy president and CEO Christian Bruch outlined five points of consistency that his company considers to be unifying elements in the decarbonisation drive.

The first is the acceleration of renewables. Replacing conventional power generation systems with solar, wind, hydro and other forms of renewable energy is essential to reduce greenhouse emissions.

Despite a considerable increase in the overall share of renewables in the past three years on the back of ever-lowering costs and more efficient technology, more must still be done.

For example, the US needs to triple its share of renewable energy as a proportion of the energy mix by 2050 for the energy transition to succeed. The Asia-Pacific region, meanwhile, will have to increase this figure fourfold. 

Regional targets

In the Middle East, every country has now set ambitious targets to increase renewable energy. The likes of Saudi Arabia, Morocco and the UAE are aiming for renewables to account for up to 50 per cent of total production by 2030. To reach these objectives, almost all new power generation projects come in the form of renewables.

However, the impact of greener electricity production could be somewhat offset by continuing demand growth caused by an increasing global population and economic growth. 

In this context, the second point is the requirement for improved energy conservation measures, such as policies to incentivise the electrification of industry and transport. 

Regionally, the industrial electrification of energy-intensive industries is an optimal opportunity to reduce harmful emissions by harnessing electric boilers and/or electricity-based fuels. Future large-scale blue and green hydrogen production will also have a role to play in industrial processes.

Siemens Energy’s third point of consistency is improving electrical efficiency. The increase in renewable energy capacity and the growth in power capacity, in general, require significant investment in transmission and distribution networks. 

This is particularly important in areas such as sub-Saharan Africa, where almost 25 per cent of the population has little to no access to electricity. 

The fourth point covers the requirement to use existing conventional power infrastructure to help bridge the gap between the fossil-fuelled economies of today and the net zero of tomorrow. 

Progress cannot be made in one step alone and requires a gradual transition. In the meantime, existing thermal plants can employ measures such as combined-cycle technology and carbon capture to make them as efficient and environmentally friendly as possible.

The energy transition is the biggest investment programme since the dawn of industrialisation. If governments, business and society work together, energy transition is a massive opportunity

Christian Bruch, Siemens Energy president and CEO

Mineral production

Finally, to achieve all of this, it is necessary to improve supply chains and increase the production of necessary minerals and rare earth metals required in net-zero technologies, such as lithium, nickel, cobalt and chromium. 

Bruch gives the example of a typical electric car, which requires six times more mineral inputs than one powered by an internal combustion engine. He also cites onshore wind plants, which need nine times more than a gas-fired power plant. 

If mineral production is not increased and geographically diversified, there is a risk of future supply bottlenecks.

In the Middle East, a good illustration of this is the potential future supply gap for electrolyser systems, and the anodes and cathodes typically made from metals such as zinc, nickel and lithium. 

MEED estimates that about 75GW of electrolyser production capacity will be required by 2030 to meet the demand for the raft of planned green hydrogen plants in the region alone, compared with a total global output capacity of just 8GW today.

Industrial decarbonisation alliance

All five consistency points make salient arguments. However, they can only be achieved with close cooperation between the private and public sectors. While the former can spearhead and implement the decarbonisation drive, the latter can provide the regulations and incentives to encourage these initiatives. 

The newly formed Alliance for Industry Decarbonization initiated by Siemens Energy and coordinated and facilitated by the Abu Dhabi-based International Renewable Energy Agency (IRENA) is an example of greater collaboration between the public and private sectors. 

The 28-member alliance – which encompasses a range of global energy, renewable, consulting and manufacturing companies – met for the first time during Cop27 to outline its joint vision and implementation plan. Its strategy focuses on six pillars and enablers that tie into the points of consistency: renewables, green hydrogen, bioenergy with carbon capture, utilisation and storage (CCUS), heat process optimisation, human capital and finance.

Only through this kind of stakeholder dialogue can the immense and existential challenges posed by global warming be overcome. Governments or companies acting in isolation will only achieve so much on their own. The points of consistency must be considered as a whole and in unison if the world’s climate objectives are to succeed.

As Bruch says: “The energy transition is the biggest investment programme since the dawn of industrialisation. If governments, business and society work together, energy transition is a massive opportunity. There is no excuse for waiting any longer.”

Related reads:

Click here to visit Siemens Energy 
https://image.digitalinsightresearch.in/uploads/NewsArticle/10387284/main.gif
MEED Editorial
Related Articles
  • Amazon data centre hit highlights sector vulnerabilities

    2 March 2026

     

    Amid ongoing Iranian missile and drone attacks on GCC states, US cloud provider Amazon Web Services (AWS) has reported service outages following separate incidents at two of its UAE data centres.

    “At around 4.30AM PST [16.30 UAE time on 1 March], one of our Availability Zones (mec1-az2) was impacted by objects that struck the data centre, creating sparks and fire,” AWS said in an operational update on 1 March.

    At 10.46 UAE time on 2 March, the company announced a further update, saying that another of its three UAE Availability Zones had gone down.

    “We can confirm that a localised power issue has affected another Availability Zone in the ME-CENTRAL-1 Region (mec1-az3),” it said in the latest update. “Customers are also experiencing increased EC2 APIs and instance launch errors for the remaining zone (mec1-az1). At this point, it is not possible to launch new instances in the region, although existing instances should not be affected in mec1-az1.

    “Other AWS services, such as DynamoDB and S3, are also experiencing significant error rates and latencies. We are actively working to restore power and connectivity, at which time we will begin to work to recover affected resources. As of this time, we expect recovery is multiple hours away.”

    Regional footprint

    The company, part of the US’ giant Amazon group, is one of the world’s largest data centre and cloud operators. It operates three data centres in the UAE – one in Dubai and two in Abu Dhabi – and provides critical IT services to government and private sector operations and systems.

    Its Availability Zones consist of infrastructure in separate geographic locations, spaced far enough apart to significantly reduce the risk of a single event affecting customers’ business continuity, yet near enough to provide low latency for high-availability applications that use multiple zones.

    The targeting of the two data centres – and potentially others if the conflict continues – highlights the strategic importance of these types of facilities. The AWS attacks are believed to be the first time a data centre has been targeted in a conflict and are likely to drive a reconfiguration of future campus designs to account for similar risks.

    Such changes could include increased redundancies – particularly in power provision – enhanced structural resilience, and potentially a reconsideration of the location and clustering of data centre facilities.

    WATCH: Ed James explores the rapidly evolving GCC data centres market

    Historically, data centres in the region were largely smaller enterprise facilities dedicated to storage services for organisations such as banks. Their locations were often confidential and in areas that were difficult to target, making them harder to disrupt.

    However, the emergence of large in-region hyperscale data centres – with IT loads of 200MW or more and larger physical footprints – may necessitate a rethink of how such infrastructure is delivered, not just in the GCC but worldwide.

    According to MEED Projects data, there are believed to be about 185 data centres in the region, each with an estimated capex investment value of more than $10m, of which about 99 are either planned or under construction.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823937/main.gif
    Edward James
  • Contractor wins Oman water network contract

    2 March 2026

    Egypt’s Hassan Allam Construction has won an engineering, procurement and construction (EPC) contract for a water transmission network project from Al-Jardaa to Mihlaih (Sawt) in Oman’s North Al-Sharqiyah Governorate.

    The contract was awarded by Oman Water & Wastewater Services Company (OWWSC).

    The scope includes 76 kilometres of transmission lines and nearly 600km of distribution networks.

    The project also covers seven high-capacity reservoirs, two pumping stations and seven solar-powered systems.

    Hassan Allam Construction won a separate contract with OWWSC in August 2025 to build and supervise the construction of a large-scale water supply and wastewater system in Al-Amerat, Muscat.

    The Al-Amerat Catchment 10 water supply, sewer system and treated effluent networks project covers the construction of a 64km gravity sewer network.

    Last month, MEED exclusively revealed that China’s Hunan Installation Overseas Engineering had won an EPC contract to build water supply and sewage networks in Muscat. 

    The contract was awarded by state utility Nama Water Services (NWS).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823693/main.jpg
    Mark Dowdall
  • RTA opens bridge as part of Trade Centre road project

    2 March 2026

    Dubai’s Roads & Transport Authority (RTA) has opened a key bridge as part of the World Trade Centre roundabout project.

    Extending 1 kilometre (km) from Sheikh Zayed Road to Sheikh Khalifa Bin Zayed Street towards Deira, the bridge has a capacity of 3,000 vehicles an hour.

    It comprises two lanes, reducing journey time from six minutes to one minute.

    In a statement, the RTA said overall project construction progress has reached 60%.

    The project’s main construction works are being undertaken by the local firm Wade Adams, which was awarded a AED696m ($189m) contract to upgrade the Trade Centre roundabout in October 2024.

    The project will enhance connections between Sheikh Zayed Road and five main streets: Sheikh Khalifa Bin Zayed Street, Sheikh Rashid Street, 2nd December Street, Zabeel Palace Street and Al-Mustaqbal Street.

    The project’s scope covers the construction of five bridges spanning a total length of 5km. 

    In addition to the recently opened bridge, two other two-lane bridges will extend 2km and will connect Sheikh Rashid Street with 2nd December Street, with a capacity of 6,000 vehicles an hour.

    The fourth and fifth two-lane bridges will span 2km from Al-Majles Street to 2nd December Street and will connect Al-Mustaqbal Street with 2nd December Street, with a capacity of 6,000 vehicles an hour.

    The scope also covers converting the existing roundabout into a surface intersection to improve the flow of traffic inbound from Sheikh Zayed Road to 2nd December Street and of southbound traffic from Al-Mustaqbal Street to Sheikh Zayed Road.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823684/main.png
    Yasir Iqbal
  • Riyadh selects three teams for King Salman airport ECI

    2 March 2026

     

    Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has selected three groups for the construction of Terminal 6 at King Salman International airport (KSIA) in Riyadh.

    KSIADC, which is backed by Saudi sovereign wealth vehicle, the Public Investment Fund, will deliver the project on an early contractor involvement (ECI) basis.

    The selected groups include:

    • UCC / CCC (Qatar/Greece)
    • Al-Gihaz Holding / TAV / WeBuild (local/Turkiye/Italy)
    • PowerChina / MBL (China/local)

    MEED understands that the ECI timeframe will be around six months.

    The ECI process requires selected contractors to submit methodologies for the project and a design proposal. One team will then be selected for the construction.

    In November last year, MEED exclusively reported that KSIADC was targeting mid-2026 to award the contract for the construction of Terminal 6 at KSIA in Riyadh.

    In July last year, MEED exclusively reported that several contractor consortiums had submitted proposals for a contract to develop the first phase of Terminal 6 and the Iconic Terminal at KSIA.

    MEED reported in May last year that US firm Bechtel Corporation had been appointed as the delivery partner for the terminals at KSIA.

    According to local media reports, KSIADC’s acting CEO, Marco Mejia, said the project developer had completed the project’s masterplan.

    The reports added that Terminal 6 will boost the airport’s capacity by 40 million passengers.

    The project is expected to be delivered before the start of the Expo 2030 Riyadh event.

    Project scale

    The project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.

    If the project is completed on time in 2030, it will become the world’s largest operating airport in terms of passenger capacity, according to UK analytics firm GlobalData.

    The airport aims to accommodate up to 120 million passengers by 2030 and 185 million by 2050. The goal for cargo is to process 3.5 million tonnes a year by 2050.

    Saudi Arabia plans to invest $100bn in its aviation sector. Riyadh’s Saudi Aviation Strategy, announced by the General Authority of Civil Aviation, aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.

    It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15823432/main.jpg
    Yasir Iqbal
  • Petrofac cuts staff in Libya and puts oil project on hold

    2 March 2026

     

    The financially troubled engineering company Petrofac has cut its staff in Libya and stopped work on a key oil project in the country, according to industry sources.

    Between 15 and 20 Libyan members of staff have been released by the company, and work on a project to develop the Erawin oil field has been paused, sources said.

    Petrofac secured a contract with Zallaf Libya Oil & Gas Exploration & Production Company to deliver its Erawin field development project phase 1 early production facilities (EPF) in September 2021.

    The project’s scope of work encompassed surface equipment, including well pads and flowlines, at the Erawin oil field.

    It also included a pipeline to transport crude oil approximately 100 kilometres (km) to the El-Sharara oil field, along with a control room, substation and telecom system located there.

    In a statement to MEED, Petrofac said:

    “Petrofac has not exited Libya. Our Tripoli office remains operational and we continue to maintain an active presence in the country.

    “Regarding the Erawin project, the pipeline infrastructure was completed and has been in operation for more than a year.

    “A small number of remaining activities were paused while we continue discussions with the client on the project’s final scope and close‑out arrangements.

    “Petrofac has not abandoned the project, nor have we shut down our operations in Libya.”

    Commenting on the cut to employee numbers in Libya, the company said:

    “Recent workforce adjustments reflect the normal lifecycle of a project.”

    The company added: “Libya remains an important market for Petrofac, and we remain committed to supporting the development of the country’s energy sector.

    “As discussions with the client are ongoing, we are not in a position to comment further at this time.”

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s National Oil Corporation.

    It awarded the Erawin EPF contract to Petrofac using the engineering, procurement, construction and commissioning (EPCC) contract model.

    In a statement in 2021, Petrofac said the contract was valued at over $100m, but did not give a precise figure.

    The regional project-tracking service MEED Projects has estimated that the contract was worth $440m.

    Petrofac problems

    On 27 October last year, Petrofac announced that it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa (Mena) region.

    At the time, the total value of projects awarded to Petrofac and under construction in the region was $5.83bn, according to information recorded by MEED Projects.

    Petrofac also had bids under evaluation for 15 projects in the region worth a total of $19.28bn.

    Since then, key parts of the business have been sold off, and many of the company’s staff have been made redundant.

    The redundancies included around 180 employees who were issued termination notices in October last year.

    In December, the US-based company CB&I announced it had entered into a deal to buy Petrofac’s asset solutions business in the first quarter of 2026.

    In January this year, the proposed company voluntary arrangement (CVA) related to the sale of its Asset Solutions business was approved.

    Erawin exports

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the EPF project in 2019.

    The Erawin field development project is located about 800km south of Tripoli and 100km southwest of the El-Sharara field.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15821861/main.jpg
    Wil Crisp