Iraq electricity sector makes slow progress
9 May 2024
Latest news from Iraq's power and water sectors:
> Iraq plans new Baiji power plant
> Decision imminent on Iraq waste-to-energy project
> Iraq discusses nuclear projects with global watchdog
> Siemens Energy and SLB sign Iraq flare gas-to-power deal
> PowerChina in talks for Basra desalination plant
> US seeks firms for Baghdad power plant package
> Iraq plans green hydrogen project at refinery
> Iraq approves long-term grid expansion

In late March, Iraq’s Electricity Ministry struck a five-year gas supply deal with National Iranian Gas Company for up to 50 million cubic metres a day (cm/d), contingent on the needs of Iraqi power stations, in exchange for oil and gasoline.
The deal offers a lifeline to Iraq’s deteriorating electricity sector and replaces an existing agreement whereby contractual volumes were theoretically set at 70 million cm/d for summer and 45 million cm/d for winter.
The two countries signed the deal following nearly three months of longer-than-usual power outages in Iraq, and after Baghdad settled part of the multibillion-dollar debt it owes Iran. The power cuts occurred due to a drastic reduction in Irani gas supply, which dipped to 10 million cm/d and wiped out 4GW from Iraq’s grid.
The deal is a compromise for both countries. It allows Iraq some breathing space to implement projects to reduce its dependence on Iran’s gas exports – a long-running and elusive objective among Iraq’s policymakers and its allies in the GCC states and the US.
The crisis should prompt Iraq to push ahead with projects to boost domestic gas production and build solar power plants, according to the Electricity Ministry.
Supply and demand mismatch
There has been a persistent mismatch between supply and demand in Iraq’s electricity sector, with peak demand during the summer months outstripping available capacity by a sizeable margin.
In recent years, the deficit has returned during the winter when heating requirements rise.
With a few exceptions, however, the procurement process or negotiations for additional generation capacity have been proceeding slowly, leaving a gap that is typically addressed by diesel generators.
Iraq aspires to build 12,000MW of solar capacity by the end of the decade, which is nearly half its known available capacity today.
The Electricity Ministry has signed deals with several companies to develop sizeable solar photovoltaic (PV) capacity over the past two to three years in line with this objective. Yet, despite regular pronouncements that the construction phase for these projects is about to start, none have reached final investment decisions (FIDs) or the construction phase so far.
The Electricity Ministry remains the dominant client for these projects, although the National Investment Commission (NIC) has been an active participant, particularly in bilateral or public-private partnership projects.
For example, the UAE’s Masdar signed a deal to develop 2GW of solar capacity in Iraq with the NIC. The commission is also procuring a contract to develop the country’s first waste-to-energy (WTE) project in coordination with the Municipality of Baghdad, the Electricity Ministry and the Environment Ministry.
Located in the Al Nahrawan area of Baghdad Governorate, the planned WTE project will have the capacity to treat 3,000 tonnes of waste a day and generate nearly 80 megawatt-hours (MWh) of electricity.
Other companies that have committed to develop solar PV projects in Iraq include Power China, which has pledged to develop solar PV projects with a combined total capacity of 2GW, and France’s Total Energies, which has committed to build a 1,000MW solar farm in Artawi.
The solar project in Artawi is a small part of a $27bn package that TotalEnergies is developing in partnership with QatarEnergy. The package involves the development of a common seawater supply project and oil and gas fields in Iraq.
Awarded projects
As earlier cited, there are some exceptions to the endemic start-stop mode for Iraq’s power generation and distribution projects.
For example, Germany’s Siemens Energy and the US-based GE have ongoing projects that include retrofitting or upgrading existing gas turbine power stations or building new substations as part of agreements to help rebuild Iraq and support its goal of reducing carbon emissions.
Earlier this month, the Electricity Ministry signed a preliminary agreement with Germany’s Siemens Energy and US firm SLB, formerly Schlumberger, to explore the development of a power generation plant using flare gas.
According to Siemens Energy Middle East managing director Dietmar Siersdorfer, the planned flare gas-to-power project in southern Iraq will help reduce carbon dioxide emissions and capture value from gas that would otherwise be wasted.
The planned flare gas-to-power plant could have a generation capacity of up to 2,000MW.
In January this year, China-based Oriental International is understood to have signed a contract to convert a single-cycle unit at the Baghdad South power plant complex into a combined-cycle power plant.
In April, the Electricity Ministry awarded another Chinese company, China Machinery Engineering Corporation (CMEC), a second year of operation and maintenance contracts for the Salah Al Din gas-fired power plant.
CMEC was awarded the estimated $1bn contract to build the power plant in northern Iraq in 2011. After a series of delays and challenges, including the Isis uprising, the two 630MW capacity units began operating last year.
In December last year, Siemens Energy also signed a contract to deliver five high-voltage substations on a turnkey basis in Iraq. The 400-kilovolt substations, each with a capacity of 1,500MW, will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.
Similarly, the US’s preoccupation with helping wean Iraq off Iran’s gas and electricity imports has spurred projects to interconnect Iraq’s grid with its neighbour Saudi Arabia through the GCC grid and Jordan.
In October last year, the governor of Saudi Arabia’s Eastern Province, Prince Saud Bin Naif Bin Abdulaziz, inaugurated the GCC grid's Iraq connection, which had been under development for several years. The 295-kilometre power transmission network will have a total transmission capacity of 1,800MW, with an initial phase expected to supply 500MW of electricity to Iraq.
Future projects
In February this year, Electricity Ministry spokesperson Ahmed Mousa said the government had approved funds for the long-term plans to expand the country’s power transmission and distribution network with Siemens Energy’s help.
Mousa said the ministry “received funds for long-term plans to develop the electricity sector in 2023 … the three-year budget approved in 2023 also includes funds this year and in 2025”.
In early May, it was reported that the Electricity Ministry held discussions with Qatar’s UCC Holding to develop a 2,100MW gas-fired power plant in Baiji. The plant will replace a power station that was damaged during the war.
It is unclear if the project is part of a previous agreement between UCC Holding and NIC to develop two power plants with a capacity of 2,400MW in Iraq.
A new 2,000MW gas-fired power plant is also being proposed in Basra, which is expected to receive gas from the nearby West Qurna 1 and West Qurna 2 oil fields.
As it is, several projects are waiting for final approvals, such as the gas-fired 2,800MW Khairat independent power producer, which has yet to reach FID over two years after the contract was awarded.
Going nuclear
Project delays and indecision in Iraq do not appear to narrow down the options for future power generation expansion.
In March, it was reported that senior Iraq and International Atomic Energy Agency (IAEA) officials had discussed Iraq’s plans for a possible nuclear energy programme, including small modular reactors.
According to the nuclear watchdog, discussions included maintaining strict adherence to non-proliferation norms.
IAEA director general Rafael Mariano Grossi said his agency has committed to supporting the foundations of what should be an entirely peaceful programme in Iraq.
Iraq, for its part, is considering nuclear energy to enable greater energy security and for water desalination projects as part of the country’s plans for a more sustainable future.
Exclusive from Meed
-
Tabreed finishes the year on a high17 December 2025
-
Kuwait Oil Company seeks higher project budgets17 December 2025
-
Morocco awards $185m Guercif-Nador road contracts17 December 2025
-
Egypt plans $5.7bn oil and gas exploration campaign17 December 2025
-
Saudi Arabia to award Abha airport expansion by March17 December 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Tabreed finishes the year on a high17 December 2025

Tabreed is consolidating its position as a leading regional district cooling provider following a series of major transactions and new concessions that will reshape its portfolio in the UAE and beyond.
In 2025, the company completed the AED3.87bn ($1bn) acquisition of PAL Cooling Holding (PCH) in consortium with CVC DIF, and finalised the long-term district cooling concession for Palm Jebel Ali in Dubai as part of a joint venture (JV) with Dubai Holding Investments.
The PCH deal will eventually add about 600,000 refrigeration tons (RT) of capacity across eight long-term concessions in Abu Dhabi, raising Tabreed’s total connected capacity by 13% to 1.55 million RT. The AED1.5bn Palm Jebel Ali JV will ultimately deliver a further 250,000RT.
Speaking to MEED, Tabreed CEO Khalid Al-Marzooqi outlined how the company is integrating the newly acquired brownfield assets, developing greenfield projects and advancing a new generation of sustainable cooling solutions, including geothermal energy for data centres.
Tabreed’s recent milestones span both greenfield and brownfield investments, each requiring a different approach, says Al-Marzooqi.
Greenfield projects, such as Palm Jebel Ali, remain Tabreed’s preferred route for new capacity, he adds. “The beauty of a greenfield is that you can optimise it the way you want. You build it as you want.”
For new plants, Tabreed designs the civil structure to accommodate long-term capacity, while phasing in mechanical equipment in line with demand. By contrast, the acquisition of PCH is a large-scale brownfield integration, bringing in a portfolio of existing and future plants and networks, mainly on Abu Dhabi’s main island and Reem Island.
The immediate focus is on integration and driving network synergies. “That’s the beauty of district cooling. If you achieve the synergies, the benefits literally double up and triple up as well,” Al-Marzooqi says.
By interconnecting plants, Tabreed can avoid building for peak capacity at each individual site and instead leverage shared spare capacity across the network.
Growth strategy
Acquiring a competitor in Abu Dhabi is part of a strategy to sustain growth in a sector where many contracts follow build-own-operate-transfer or similarly time-bound models.
Organic growth via new concessions and inorganic growth via acquisitions are both seen as key to maintaining and expanding the asset base.
Tabreed’s portfolio remains weighted towards the UAE, with the home market accounting for the bulk of its business.
Beyond the UAE, Tabreed has built a regional presence, with a partially owned business in Saudi Arabia, where it sees significant growth potential as district cooling is integrated into gigaprojects and major urban developments; a wholly owned operation in Bahrain; and a majority stake in Tabreed Oman, a market that Al-Marzooqi says is expanding well.
Despite the energy and lifecycle cost benefits of district cooling, Al-Marzooqi says tariff subsidies on conventional, building-level cooling are a barrier to adoption in parts of the UAE.
“The killer for us is subsidy,” he says, explaining that artificially low tariffs for individual customers make it harder for district cooling to compete on price in Abu Dhabi compared to Dubai.
He says that policy support and regulatory mandates are needed, particularly as existing buildings approach the end of life for their standalone cooling systems. At that point, compulsory connection to district cooling could lock in significant energy savings and emissions reductions at city scale.
Raising Abu Dhabi’s district cooling penetration from about 15% towards Dubai’s estimated 30% remains a key concern and strategic objective.
In Abu Dhabi, Tabreed has developed … the Middle East’s first geothermal-powered district cooling plant
Geothermal breakthrough
Alongside portfolio growth, Tabreed is investing in new technologies to decarbonise cooling, with a focus on large campuses, major developments and, increasingly, data centres.
At Masdar City in Abu Dhabi, Tabreed has developed what Al-Marzooqi describes as the Middle East’s first geothermal-powered district cooling plant.
“We have started off by building the region’s first geothermal plant, to prove the concept of using geothermal energy to provide cooling,” he says.
The pilot plant is already achieving efficiency levels in the range of 0.5-0.6 kilowatts per ton (kW/ton) of cooling, better than Tabreed’s typical district cooling benchmark of about 0.85kW/ton. Conventional, standalone cooling systems generally consume about twice as much energy per ton.
“This is proof that if you really want to pursue a sustainable cooling solution for data centres in this area, this is the one,” he says.
Data centres are emerging as a priority growth segment for Tabreed. The facilities have high, continuous cooling loads and increasingly stringent decarbonisation requirements, making them a natural fit with both district cooling and geothermal systems.
Al-Marzooqi says geothermal cooling is a “godsend solution” for data centres, combining 24/7 availability with the potential for near-zero operational emissions.
For hyperscale and colocation data centre operators facing mounting pressure to reduce their carbon footprint, geothermal district cooling could offer a differentiated, long-term solution in the Gulf region, particularly where grid power is still largely fossil-fuel based.
Tabreed’s technology agenda is not limited to low-carbon generation. The utility is in the second phase of connecting its plants to a centralised digital control centre, enabling remote operation and optimisation.
The long-term goal is for the majority of plants to be unmanned, with operations centrally monitored and controlled. This integrated view of the network will enable the application of artificial intelligence and advanced analytics to fine-tune performance, optimise energy use and predict maintenance requirements.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15266676/main.gif -
Kuwait Oil Company seeks higher project budgets17 December 2025

Contractors in Kuwait expect to have answers by the end of the year on whether budgets for several key upstream projects in the oil and gas sector will be increased, according to industry sources.
State-owned upstream operator Kuwait Oil Company (KOC) is seeking approvals for at least three upstream projects, for which bids came in significantly over budget.
The first project, with a low bid of $2.47bn, involves the development of two facilities: Separation Gathering Centre 1 (SGC-1) and Water Injection Plant 1 (WIP-1).
The second project, with a low bid of $2.48bn, focuses on developing SGC‑3 and WIP‑3.
The third project, which involves developing effluent water disposal plants for injector wells, had a low bid of $1.3bn.
For KOC to increase the budgets for all three projects, approvals will be required from Kuwait Petroleum Corporation (KPC) and the country’s Ministry of Finance.
Already cancelled
One Kuwaiti oil project tender that received bids significantly above budget has already been cancelled.
On 7 October, MEED reported that the tender for the SGC-2 oil project – focused on the installation of a separation gathering centre – was cancelled by Kuwait’s Central Agency for Public Tenders.
Earlier this year, UK-based Petrofac had submitted a bid more than double the project’s proposed budget.
Petrofac’s bid was KD422.45m ($1.37bn), while the provisional budget stood at KD207m ($670.2m).
This contract is expected to be retendered, but there is significant uncertainty about when a new invitation to bid will be issued and how the scope may change.
Earlier in December, MEED reported that KOC was discussing whether to retender the contract using a different contract model.
Initially, the project was tendered using the engineering, procurement and construction (EPC) contract model.
Discussions are ongoing on whether it will be relaunched under a build-own-operate (BOO) contract model.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15263996/main.png -
Morocco awards $185m Guercif-Nador road contracts17 December 2025

Morocco’s Ministry of Equipment, Transport, Logistics & Water has awarded three contracts totalling MD1.7bn ($185m) for building three lots of the 40-kilometre (km) section two of the Guercif to Nador highway between Saka and Driouch.
The contracts were awarded to local firms.
Casablanca-based Groupe Mojazine won a $64m contract for lot one, which covers the construction of 14km of highway.
The other two contracts covering construction works on lots two and three were awarded to the local firm Bioui Travaux.
The contract value for lot two is over $56m and covers the 12km highway section. The lot three contract is worth about $69m and covers 40km of highway construction.
The 104km Guercif to Nador highway is being implemented in three sections. Prequalification for section two from Saka to Driouch was completed in June, as MEED reported.
The estimated $700m project, partly funded by the African Development Bank, is part of the kingdom’s plans to upgrade its public infrastructure in preparation for co-hosting the 2030 Fifa World Cup alongside Portugal and Spain. The programme includes the expansion of over 1,000km of highways.
In May, Societe Nationale des Autoroutes du Maroc awarded MD5bn ($540m) of contracts for nine packages covering construction works on the Rabat-Casablanca continental expressway.
Morocco’s construction and infrastructure sector is gearing up for billions of dollars in projects as the North African nation continues to award contracts for building infrastructure for the 2030 Fifa World Cup.
Morocco has made a strong head start in ensuring that the necessary infrastructure is ready for the tournament.
According to data from regional project tracker MEED Projects, 2024 was the best year in the past decade for construction and transport contract awards in Morocco, with contracts worth over $3.6bn signed with local construction firms and international companies from South Korea, China, France and Spain.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15266606/main.jpg -
Egypt plans $5.7bn oil and gas exploration campaign17 December 2025
Egypt plans to drill 480 exploratory wells, with total investment estimated at $5.7bn, over the next five years, according to Karim Badawi, the country’s minister of petroleum and mineral resources.
Speaking at a conference in Cairo, Badawi said that Egypt’s oil and gas sector was stabilising after a period of decline.
He said that his ministry was targeting an increase in gas production for the first time in four years.
The government is also aiming for self-sufficiency in crude oil production within five years, he said.
Egypt is aiming to boost crude production by introducing investment incentive packages and utilising new production technologies.
Badawi highlighted specific capital commitments from international partners to develop oil and gas resources over the next five years. These included Italian company Eni’s commitment to invest $8bn, as well as London-headquartered BP’s plan to invest $5bn.
He also highlighted Arcius Energy’s plan to invest $3.7bn. Arcius Energy is a joint venture of BP and Adnoc’s XRG.
The $5.7bn exploration programme includes 101 wells scheduled for drilling in 2026.
Badawi said that seismic survey operations would expand to cover 100,000 square kilometres in the Western Desert and 95,000 square kilometres in the Eastern Mediterranean using Ocean Bottom Node (OBN) technology.
Renewable energy strategy
Addressing the national energy strategy, Badawi said the government aims to increase the share of renewable energy in electricity generation to 42% by 2030.
He said this would enable natural gas to be redirected to value-added industries, such as petrochemicals and fertilisers, to boost exports.
On the transition to green energy, the minister cited plans to reduce reliance on traditional fuels and open investment in sustainable aviation fuel (SAF), green ammonia and bioethanol.
Efficiency measures in the sector have already reduced carbon emissions by 1.4 million tonnes, he said.
Recently, Egypt announced a $200m deal with Qatar to produce aviation fuel from used cooking oil.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15264077/main0508.jpg -
Saudi Arabia to award Abha airport expansion by March17 December 2025
Register for MEED’s 14-day trial access
Saudi Arabia’s Civil Aviation Holding Company (Matarat) and the National Centre for Privatisation & PPP (NCP) are expected to award the contract to develop and operate a new passenger terminal building and related facilities at Abha International airport by March next year.
The announcement was made by Abdulaziz Al-Duailej, president of the General Authority of Civil Aviation (Gaca), at the Supply Chain and Logistics Conference 2025 in Riyadh on Tuesday.
The companies prequalified to bid for the contract are:
- GMR Airports (India)
- Mada TAV: Mada International Holding (local) / TAV Airports Holding
- Touwalk Alliance: Skilled Engineers Contracting (local) / Limak Insaat (Turkiye) / Incheon International Airport Corporation (South Korea) / Dar Al-Handasah Consultants (Shair & Partners, Lebanon) / Obermeyer Middle East (Germany/Abu Dhabi)
- VI Asyad DAA: Vision International Investment Company (local) / Asyad Holding (local) / DAA International (Ireland)
Located in Asir Province, the first phase of the Abha International airport public-private partnership (PPP) project will expand the terminal area from 10,500 square metres (sq m) to 65,000 sq m.
In early March this year, the clients held one-on-one meetings with prospective bidders in Riyadh, as reported by MEED.
The contract scope includes a new rapid-exit taxiway on the existing runway, a new apron to serve the new terminal, access roads to the new terminal building and a new car park area.
Additionally, the scope includes support facilities, such as an electrical substation expansion and a new sewage treatment plant.
Construction is scheduled for completion in 2028.
The project will be developed under a build-transfer-operate (BTO) model and involves designing, financing, constructing and operating a greenfield terminal.
This will be the kingdom’s third airport PPP project, following the Hajj terminal at Jeddah’s King Abdulaziz International airport and the $1.2bn Prince Mohammed Bin Abdulaziz International airport in Medina.
Higher capacity
According to Matarat, Abha airport’s capacity will increase to accommodate over 13 million passengers annually—a 10-fold rise from its current 1.5 million capacity.
Once completed, the airport will handle more than 90,000 flights a year, up from 30,000.
The new terminal is also expected to feature 20 gates and 41 check-in counters, including seven new self-service check-in kiosks.
The BTO contract duration is 30 years.
The existing terminal, which served 4.4 million passengers in 2019, will be closed once the new terminal becomes operational.
Matarat’s transaction advisory team for the project comprises UK-headquartered Deloitte as financial adviser, ALG as technical adviser and London-based Ashurst as legal adviser.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15264715/main.jpg