Iraq electricity sector makes slow progress
9 May 2024
Latest news from Iraq's power and water sectors:
> Iraq plans new Baiji power plant
> Decision imminent on Iraq waste-to-energy project
> Iraq discusses nuclear projects with global watchdog
> Siemens Energy and SLB sign Iraq flare gas-to-power deal
> PowerChina in talks for Basra desalination plant
> US seeks firms for Baghdad power plant package
> Iraq plans green hydrogen project at refinery
> Iraq approves long-term grid expansion

In late March, Iraq’s Electricity Ministry struck a five-year gas supply deal with National Iranian Gas Company for up to 50 million cubic metres a day (cm/d), contingent on the needs of Iraqi power stations, in exchange for oil and gasoline.
The deal offers a lifeline to Iraq’s deteriorating electricity sector and replaces an existing agreement whereby contractual volumes were theoretically set at 70 million cm/d for summer and 45 million cm/d for winter.
The two countries signed the deal following nearly three months of longer-than-usual power outages in Iraq, and after Baghdad settled part of the multibillion-dollar debt it owes Iran. The power cuts occurred due to a drastic reduction in Irani gas supply, which dipped to 10 million cm/d and wiped out 4GW from Iraq’s grid.
The deal is a compromise for both countries. It allows Iraq some breathing space to implement projects to reduce its dependence on Iran’s gas exports – a long-running and elusive objective among Iraq’s policymakers and its allies in the GCC states and the US.
The crisis should prompt Iraq to push ahead with projects to boost domestic gas production and build solar power plants, according to the Electricity Ministry.
Supply and demand mismatch
There has been a persistent mismatch between supply and demand in Iraq’s electricity sector, with peak demand during the summer months outstripping available capacity by a sizeable margin.
In recent years, the deficit has returned during the winter when heating requirements rise.
With a few exceptions, however, the procurement process or negotiations for additional generation capacity have been proceeding slowly, leaving a gap that is typically addressed by diesel generators.
Iraq aspires to build 12,000MW of solar capacity by the end of the decade, which is nearly half its known available capacity today.
The Electricity Ministry has signed deals with several companies to develop sizeable solar photovoltaic (PV) capacity over the past two to three years in line with this objective. Yet, despite regular pronouncements that the construction phase for these projects is about to start, none have reached final investment decisions (FIDs) or the construction phase so far.
The Electricity Ministry remains the dominant client for these projects, although the National Investment Commission (NIC) has been an active participant, particularly in bilateral or public-private partnership projects.
For example, the UAE’s Masdar signed a deal to develop 2GW of solar capacity in Iraq with the NIC. The commission is also procuring a contract to develop the country’s first waste-to-energy (WTE) project in coordination with the Municipality of Baghdad, the Electricity Ministry and the Environment Ministry.
Located in the Al Nahrawan area of Baghdad Governorate, the planned WTE project will have the capacity to treat 3,000 tonnes of waste a day and generate nearly 80 megawatt-hours (MWh) of electricity.
Other companies that have committed to develop solar PV projects in Iraq include Power China, which has pledged to develop solar PV projects with a combined total capacity of 2GW, and France’s Total Energies, which has committed to build a 1,000MW solar farm in Artawi.
The solar project in Artawi is a small part of a $27bn package that TotalEnergies is developing in partnership with QatarEnergy. The package involves the development of a common seawater supply project and oil and gas fields in Iraq.
Awarded projects
As earlier cited, there are some exceptions to the endemic start-stop mode for Iraq’s power generation and distribution projects.
For example, Germany’s Siemens Energy and the US-based GE have ongoing projects that include retrofitting or upgrading existing gas turbine power stations or building new substations as part of agreements to help rebuild Iraq and support its goal of reducing carbon emissions.
Earlier this month, the Electricity Ministry signed a preliminary agreement with Germany’s Siemens Energy and US firm SLB, formerly Schlumberger, to explore the development of a power generation plant using flare gas.
According to Siemens Energy Middle East managing director Dietmar Siersdorfer, the planned flare gas-to-power project in southern Iraq will help reduce carbon dioxide emissions and capture value from gas that would otherwise be wasted.
The planned flare gas-to-power plant could have a generation capacity of up to 2,000MW.
In January this year, China-based Oriental International is understood to have signed a contract to convert a single-cycle unit at the Baghdad South power plant complex into a combined-cycle power plant.
In April, the Electricity Ministry awarded another Chinese company, China Machinery Engineering Corporation (CMEC), a second year of operation and maintenance contracts for the Salah Al Din gas-fired power plant.
CMEC was awarded the estimated $1bn contract to build the power plant in northern Iraq in 2011. After a series of delays and challenges, including the Isis uprising, the two 630MW capacity units began operating last year.
In December last year, Siemens Energy also signed a contract to deliver five high-voltage substations on a turnkey basis in Iraq. The 400-kilovolt substations, each with a capacity of 1,500MW, will be installed in Baghdad, Diyala, Najaf, Karbala and Basra.
Similarly, the US’s preoccupation with helping wean Iraq off Iran’s gas and electricity imports has spurred projects to interconnect Iraq’s grid with its neighbour Saudi Arabia through the GCC grid and Jordan.
In October last year, the governor of Saudi Arabia’s Eastern Province, Prince Saud Bin Naif Bin Abdulaziz, inaugurated the GCC grid's Iraq connection, which had been under development for several years. The 295-kilometre power transmission network will have a total transmission capacity of 1,800MW, with an initial phase expected to supply 500MW of electricity to Iraq.
Future projects
In February this year, Electricity Ministry spokesperson Ahmed Mousa said the government had approved funds for the long-term plans to expand the country’s power transmission and distribution network with Siemens Energy’s help.
Mousa said the ministry “received funds for long-term plans to develop the electricity sector in 2023 … the three-year budget approved in 2023 also includes funds this year and in 2025”.
In early May, it was reported that the Electricity Ministry held discussions with Qatar’s UCC Holding to develop a 2,100MW gas-fired power plant in Baiji. The plant will replace a power station that was damaged during the war.
It is unclear if the project is part of a previous agreement between UCC Holding and NIC to develop two power plants with a capacity of 2,400MW in Iraq.
A new 2,000MW gas-fired power plant is also being proposed in Basra, which is expected to receive gas from the nearby West Qurna 1 and West Qurna 2 oil fields.
As it is, several projects are waiting for final approvals, such as the gas-fired 2,800MW Khairat independent power producer, which has yet to reach FID over two years after the contract was awarded.
Going nuclear
Project delays and indecision in Iraq do not appear to narrow down the options for future power generation expansion.
In March, it was reported that senior Iraq and International Atomic Energy Agency (IAEA) officials had discussed Iraq’s plans for a possible nuclear energy programme, including small modular reactors.
According to the nuclear watchdog, discussions included maintaining strict adherence to non-proliferation norms.
IAEA director general Rafael Mariano Grossi said his agency has committed to supporting the foundations of what should be an entirely peaceful programme in Iraq.
Iraq, for its part, is considering nuclear energy to enable greater energy security and for water desalination projects as part of the country’s plans for a more sustainable future.
Exclusive from Meed
-
Dubai evaluates Tasreef drainage bids24 November 2026
-
Muscat financial centre opens for business24 November 2026
-
Mecca university tenders water infrastructure projects24 November 2026
-
Oman’s OQT formalises Pakistan fuel supply agreement24 November 2026
-
Contractors bid for Aramco-backed logistics hub24 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai evaluates Tasreef drainage bids24 November 2026

Up to eight stormwater and drainage projects under the next phase of Dubai Municipality’s AED30bn ($8.2bn) Tasreef programme have moved into the bid evaluation stage in recent weeks as procurement activity continues to drive the wider water infrastructure sector.
The projects cover major stormwater drainage networks, pumping stations, storage tanks and sewerage infrastructure. They include schemes serving Dubai South, Abu Hail, the area surrounding Dubai International airport, Dubailand and Al-Awir.
According to regional project tracker MEED Projects, the eight tenders have an estimated combined value of at least $800m. The tenders cover the following projects:
- DS-316-C1: Drainage networks serving Hind 4
- TF-24-C1: Connections to the stormwater network in Dubailand
- TF-25-C1: Stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman
- TF-07-C1: Strategic stormwater drainage network between Sheikh Mohammed bin Zayed Road and Emirates Road
- TF-21-C1: Stormwater system upgrade and rehabilitation in Abu Hail
- TF-30-C1: Stormwater storage tanks serving the Dubai International airport area
- TF-06-C2: Stormwater drainage system connecting Al-Maktoum International airport and Dubai South
- DS317-C1: Sewerage and stormwater infrastructure in New Al-Awir 1st
According to sources, local firms Nael Construction & Contracting, Al-Nasr Contracting and Arifco Building Contracting are among those that submitted bids for the Dubailand stormwater network project (TF-24-C1) in October. The bidders for this tender do not include the local DeTech Contracting, which won the estimated $350m engineering, procurement and construction contract for a package on Al-Wasl Road (TF-15-C1), earlier this year.
On 29 October, DeTech, Mohammed Abdulmohsin Al-Kharafi & Sons and Green Oasis General Contracting Company were among those that submitted bids for TF-07-C1, sources told MEED.
It is undersood that both DeTech and Kharafi also submitted offers on 12 November for a contract to upgrade and rehabilitate the stormwater system in Abu Hail (TF-21-C1). The Abu Hail project comprises a stormwater pumping station with a total discharge capacity of 26 cubic metres a second. The wider project involves a major stormwater gravity drainage network, including large-diameter pipelines, and is estimated to cost up to $163m.
Meanwhile, the the municipality is preparing to receive bids for a further scheme (TF-06-C1) on 26 November, involving the construction of a stormwater pond connecting Al-Maktoum airport and Dubai South. Al-Nasr Contracting and Green Oasis are among those preparing to bid, sources said.
In October, the municipality confirmed it had awarded four contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.
The projects will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. The works include constructing and extending main stormwater drainage lines with diameters of up to 3 metres.
The Tasreef programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21756439/main.jpg -
Muscat financial centre opens for business24 November 2026
The International Financial Centre of Oman (IFC Oman) has opened its headquarters at Al-Mouj Business Park in Muscat and registered its first 13 companies.
Sayyid Theyazin bin Haitham Al-Said, Oman's Deputy Prime Minister for Economic Affairs and chairman of IFC Oman, opened the headquarters on 23 November. The ceremony also marked the official start of company registration, which allows local and international businesses to set up within the centre's jurisdiction.
The first 13 companies received their certificates of incorporation at the event. The centre was set up by Royal Decree No. 8/2026 in January, so the move from setting up a legal framework to taking in businesses has taken 10 months.
Registration follows royal decrees that put in place IFC Oman's operating law, regulatory law and courts law. Five core regulations sit alongside them and cover operations, companies, partnerships, foundations and interpretation. Together they set the rules for setting up and running a business in the centre, including corporate governance, regulatory obligations and dispute resolution.
Businesses can apply through a new digital registry platform. A separate regulatory framework for financial services is still being drafted, and licensing for those activities is expected to start in early 2027.
Finance Minister Sultan bin Salim Al-Habsi, who is vice-chairman of IFC Oman, said the decision by 13 companies to join from the start "reflects the strength of the business and investment environment the centre offers".
"We will maintain this momentum as we complete the regulatory framework ahead of the start of financial services licensing early next year," he said.
Sayyid Theyazin said the framework "lays the foundation for a stable and competitive business environment" and will strengthen Oman's appeal to international investors and financial institutions.
He also chaired a board meeting. It reviewed progress on finishing the centre's legal, regulatory and operational infrastructure and set priorities for attracting companies and investment.
IFC Oman aims to connect the national economy more closely to international capital and to support growth in financial and professional services, in line with the Oman Vision 2040 economic diversification programme.
The centre goes up against established regional financial hubs, including Dubai International Financial Centre, Abu Dhabi Global Market and Qatar Financial Centre.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21756636/main5305.gif -
Mecca university tenders water infrastructure projects24 November 2026
Mecca-based Umm Al-Qura University has issued two tenders for wastewater and water storage infrastructure at its student campus in the Al-Abidiyah district.
The first tender covers the second phase of the university’s main water storage scheme. The project involves building seven tanks with a combined capacity of 14,700 cubic metres.
The scope includes three ground-level tanks with a total capacity of 7,500 cubic metres and four elevated tanks with a combined capacity of 7,200 cubic metres.
It also includes a 2.1-kilometre backup water supply pipeline with a diameter of 400 millimetres, as well as pumping stations, inlet and outlet pipework, valves and water control systems.
The second tender covers the construction of a wastewater treatment plant with a capacity of 4,000 cubic metres a day at the university’s student campus. The contract duration is listed as two years.
The projects will expand the campus’s water infrastructure, adding storage capacity and wastewater treatment facilities to support its operational requirements.
Both tenders were issued in November. Bids for the water storage tanks and wastewater plant are due by 14 December and 13 December, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21752745/main.jpg -
Oman’s OQT formalises Pakistan fuel supply agreement24 November 2026
Oman's state-owned commodity trader OQT has signed a petroleum products supply agreement with Pakistan State Oil (PSO), the South Asian country's national oil marketing company.
The deal was signed on 8 October and formally marked at a ceremony in Muscat on 22 November. It was made under the Oman-Pakistan intergovernmental framework and gives OQT a structured arrangement for supplying petroleum products to PSO.
The two companies have yet to disclose the agreement's value, volumes or duration.
The agreement builds on an existing trading relationship. OQT says it has supplied more than 1 million tonnes of gasoline to PSO in 2026.
OQT also supplies Pakistan's liquefied petroleum gas (LPG) market, selling to both state-owned and private buyers. The company expects its LPG deliveries to Pakistan to pass 120,000 tonnes by the end of the year.
"This agreement gives us a stronger framework to build on that relationship, combining OQT's international trading capabilities with PSO's position in the Pakistani market," said OQT chief executive Wail Al-Jamali.
PSO chief executive Jawwad Ahmed Cheema said the partnership is now "formal, government-backed and built for the long term under the Oman-Pakistan Intergovernmental Agreement".
"For PSO, this is about more than supply. It is about ensuring that Pakistan has the fuel it needs, when it needs it, on terms that protect our national interest," he said.
Oman's Energy & Minerals Minister Salim Al-Aufi and Pakistan's Petroleum Minister Ali Pervaiz Malik attended the ceremony, along with Mulham Al-Jarf, deputy president of investment at the Oman Investment Authority, which owns OQT.
The companies said the agreement will support reliable supply at a time of continued volatility in regional energy markets. They will now focus on implementation and deliveries, and will continue talks on wider petroleum and energy cooperation.
OQT trades crude oil, refined products, petrochemicals, LPG, liquefied natural gas, fertilisers and carbon-related products, and is expanding into metals. It has offices in Muscat, Dubai, London, Rotterdam, Singapore, Houston and Shanghai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21750539/main1214.jpeg -
Contractors bid for Aramco-backed logistics hub24 November 2026

Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, received proposals from contractors on 15 November for a contract to expand the logistics complex at King Salman Energy Park (Spark) in Saudi Arabia’s Eastern Province.
The logistics hub will add over 124,000 square metres (sq m) at Spark.
Al-Khobar-based engineering firm House of Consulting Office is the project consultant.
The tender for the expansion works comes after Asmo awarded an estimated SR820m ($218m) contract to build the logistics complex’s first phase in May this year.
The overall project will feature a 43,000 sq m, temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.
Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings in February to deliver the project at Spark.
Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.
It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.
The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.
Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.
According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.
Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21747071/main.gif