Saudi Arabia takes 2GW energy storage steps

1 May 2024

Saudi Power Procurement Company (SPPC) is several months away from seeking interest from developers for the contract to develop and operate the 2,000MW first phase of a battery energy storage system (bess) catering to the grid.

According to an industry source, the principal buyer and its consultants are finalising the project sites, and the start of the procurement process could be "a few months away".

SPPC plans to procure up to 10GW, equivalent to 40 gigawatt-hours (GWh), of bess capacity by 2030.

MEED previously reported that the principal buyer conducted a market-sounding event for the project in December 2023, in line with a plan to launch the procurement process for one-fifth of this capacity this year.

The 2GW first phase of the project involves building multiple battery energy storage systems across multiple locations, with individual capacities ranging from 50MW to 300MW. 

The project will be developed using an independent power producer (IPP) model.

The planned bess facilities are to be built near demand centres. They will boost the electricity grid's spinning reserves as more renewable energy enters its electricity production mix.

Bess comprises rechargeable batteries that can store and discharge energy from various sources when needed. It is one of the key solutions being considered to address the intermittency of renewable energy sources.

US/India-based Synergy Consulting is advising SPPC on the planned bess IPP.

The first-phase project may or may not become part of round six of the kingdom's National Renewable Energy Programme (NREP), which currently involves the development of wind IPPs, as MEED previously reported.

Growing renewable capacity

Saudi Arabia, through SPPC, publicly tendered over 6,600MW of renewable energy capacity under the first four rounds of NREP between 2017 and 2023.

Solar photovoltaic (PV) IPP projects account for 66% of the total capacity, or about 4,400MW. Wind IPPs account for the remaining capacity.

At least three of these schemes are now operational: the 300MW Sakaka solar PV, the 400MW Dumat Al Jandal wind IPP and the Rabigh solar IPP projects.

The bid results for the three wind IPPs under round four of the kingdom's NREP are yet to be released.

Round five

In February, SPPC tendered contracts to develop four solar PV IPPs under the NREP fifth procurement round.

The following solar PV IPP projects and their capacities make up round five of the NREP:

  • Al Sadawi solar IPP (Eastern Province): 2,000MW
  • Al Mas solar IPP (Hail): 1,000MW
  • Al Hinakiyah 2 solar IPP (Medina): 400MW
  • Rabigh 2 solar IPP (Mecca): 300MW

SPPC will procure 30% of the kingdom's target renewable energy installed capacity of 58,700MW through a public tendering process by 2030.

Saudi sovereign wealth vehicle, the Public Investment Fund, is procuring the rest through the Price Discovery Scheme.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11727063/main.gif
Jennifer Aguinaldo
Related Articles
  • Jordan to build cross-border railway

    27 August 2025

    Jordan will develop a railway network that will connect it to neighbouring countries, Minister of State for Economic Affairs Muhannad Shehadeh told local media.

    Shehadeh said the project is part of the second phase of Jordan’s Economic Modernisation Vision 2033.

    He added that under the first phase of the Economic Modernisation Vision (2023-25), Jordan launched 512 projects aimed at stimulating growth and improving public services.

    The second phase of the roadmap will span 2026 to 2029. During this phase, the country plans to undertake major infrastructure projects.

    The Economic Modernisation Vision – Amman’s flagship vehicle for its reform proposition – aims to increase average real income per capita by 3% a year, create 1 million jobs and more than double the country’s GDP over 10 years. The programme calls for the private sector to take the lead, accounting for 73% of the total $58.8bn of required investment.

    To realise the vision, a large pipeline of public-private partnership (PPP) projects is required, covering areas such as water desalination, school construction, clean energy, green hydrogen, transport improvements and road construction.

    Jordan is also developing several major infrastructure projects, most on a PPP basis. The most prominent is a phosphate railway line being developed in partnership with the UAE’s Etihad Rail.

    A detailed study on the railway alignment and requirements for handling potash and phosphate is expected to be completed by the end of this year, with main contract tenders to follow early next year.

    In September last year, Etihad Rail announced it had signed a $2.3bn memorandum of understanding with Jordan’s Transport Ministry and local firms to develop the project on a build-operate-maintain basis.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14550713/main.gif
    Yasir Iqbal
  • October deadline set for Abha airport PPP bids

    27 August 2025

     

    Saudi Arabia’s Civil Aviation Holding Company (Matarat) and the National Centre for Privatisation & PPP (NCP) have extended the tender closing date to mid-October for a contract to develop and operate a new passenger terminal building and related facilities at Abha International airport.

    MEED understands that the previous bid deadline was in late June.

    In early March, the clients held one-on-one meetings with prospective bidders in Riyadh, as reported by MEED.

    The companies prequalified to bid for the contract are:

    • GMR Airports (India)
    • Mada TAV: Mada International Holding (local) / TAV Airports Holding
    • Touwalk Alliance: Skilled Engineers Contracting (local) / Limak Insaat (Turkiye) / Incheon International Airport Corporation (South Korea) / Dar Al-Handasah Consultants (Shair & Partners, Lebanon) /  Obermeyer Middle East (Germany/Abu Dhabi)
    • VI Asyad DAA: Vision International Investment Company (local) / Asyad Holding (local) / DAA International (Ireland)

    Located in Asir Province, the first phase of the Abha International airport public-private partnership (PPP) project will expand the terminal area from 10,500 square metres (sq m) to 65,000 sq m.

    The contract scope includes a new rapid-exit taxiway on the existing runway, a new apron to serve the new terminal, access roads to the new terminal building and a new car park area.

    Additionally, the scope encompasses support facilities, including an electrical substation expansion and a new sewage treatment plant. 

    Construction is scheduled for completion in 2028.

    The project will be developed under a build-transfer-operate (BTO) model and involves designing, financing, constructing and operating a greenfield terminal.

    This will be the kingdom’s third airport PPP project, following the Hajj terminal at Jeddah’s King Abdulaziz International airport and the $1.2bn Prince Mohammed Bin Abdulaziz International airport in Medina.

    Higher capacity

    According to Matarat, Abha airport’s capacity will increase to accommodate over 13 million passengers annually—a 10-fold rise from its current 1.5 million capacity.

    Once completed, the airport will handle more than 90,000 flights a year, up from 30,000.

    The new terminal is also expected to feature 20 gates and 41 check-in counters, including seven new self-service check-in kiosks.

    The BTO contract duration is 30 years.

    The existing terminal, which served 4.4 million passengers in 2019, will be closed once the new terminal becomes operational.

    Matarat’s transaction advisory team for the project comprises UK-headquartered Deloitte as financial adviser, ALG as technical adviser and London-based Ashurst as legal adviser.


    READ THE AUGUST 2025 MEED BUSINESS REVIEW – click here to view PDF

    Gulf heads into a new era of aviation; Maghreb’s resilience rises despite global pressures; GCC banks expand issuance amid demand

    Distributed to senior decision-makers in the region and around the world, the August 2025 edition of MEED Business Review includes:

    > MAGHREB MARKET FOCUS: Maghreb pushes for stability
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14549177/main.jpg
    Yasir Iqbal
  • Kuwait tenders major wastewater consultancy

    27 August 2025

    Kuwait’s Public Authority for Housing Welfare (PAHW) has issued a tender for consultancy services covering the study, design, operation and maintenance of two wastewater purification and treatment plants.

    The plants will have capacities of 400,000 cubic metres a day (cm/d) and 60,000 cm/d.

    The scope includes the preparation of standard tender documents and all associated pumping lines. 

    The deadline for submitting bids is 31 August, and the duration of the contract is 18 months. 

    Conditions require firms to have designed at least three wastewater treatment plants, with a capacity of no less than 150,000 cm/d in the past 10 years. Each project must have had a consultancy services contract value of at least KD1.5m ($5m).

    Kuwait has been expanding its wastewater treatment capacity in recent years through projects such as the Umm Al-Hayman wastewater public-private partnership, which has an initial capacity of 500,000 cm/d.

    In August, MEED reported on the lowest bidder for phase two of a seawater desalination plant in Doha, Kuwait.

    This is part of Kuwait’s broader programme to expand water production capacity and reduce reliance on thermal desalination methods.

    Interested firms can obtain documents from PAHW’s headquarters in South Surra for a non-refundable fee of KD500 ($1,600).

    Bidders must provide an initial guarantee of KD50,000 valid for 90 days. The final guarantee will be equal to 10% of the total contract value.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14549154/main.jpg
    Mark Dowdall
  • Lowest bidder emerges for Oman Burj Al-Sahwa project

    27 August 2025

     

    The local subsidiary of Austrian firm Strabag has submitted the lowest main bid for the construction of the Burj Al-Sahwa roundabout and its associated roads in Muscat, Oman.

    According to the results published by the Oman Tender Board, Strabag submitted a main bid priced at RO201m ($522m).

    The other bidders were:

    • Galfar Engineering & Contracting: Main bid – $632m; Alternate bid – $320m
    • Sarooj Construction Company: Main bid – $871m; Alternate bid – $124m

    The tender for the main contract was initially issued in January this year. Technical bids were opened in May, followed by the opening of commercial bids on 20 August.

    UK analytics firm GlobalData expects the Omani construction industry to grow at an average annual rate of 4.2% between 2025 and 2028, driven by investments aligned with the Oman Vision 2040 strategy. Under this strategy, the government plans to allocate RO20bn ($52bn) to the tourism sector and aims to attract 11 million visitors annually by 2040. 

    The commercial construction sector is projected to expand by 1.4% in real terms in 2024, followed by an average annual growth rate of 3.6% between 2025 and 2028, supported by a rebound in tourism and growth in wholesale and retail trade activities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14549037/main.gif
    Yasir Iqbal
  • Developer cuts budget for Libya gas project

    27 August 2025

     

    The project to develop Libya’s Al-Atshan gas field has had its budget cut and is now on hold, according to industry sources.

    The project is being developed by Libya’s Zallaf Oil & Gas and is estimated to be worth about $350m.

    The project comprises several packages, focused on developing infrastructure for the field, including a central processing facility (CPF), an export pipeline, a gas receiving station and a residential facility.

    Earlier this year, companies submitted prequalification documents for the geotechnical and geophysical surveys associated with the project.

    Additionally, in early July, London-based Shell signed a conditional agreement with Libya’s National Oil Corporation (NOC) to develop the Al-Atshan field and other fields that the state-owned oil company controls.

    Libya’s NOC said on 7 July that its memorandum of understanding with Shell will allow the international oil company to evaluate hydrocarbons prospects and conduct a comprehensive technical and economic feasibility study to develop Al-Atshan.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14547125/main5118.jpg
    Wil Crisp